Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC | ₹1.1 Cr | L1 | Accepted-AOC LOWEST RATE |
| 2 | L2₹1.1 Cr+₹1.0 L (0.98%)Rejected-Finance H NO 236 VILLAGE RAZAPUR GHAZIABAD | GHAZIABAD | GHAZIABAD | UTTAR PRADESH | ₹1.1 Cr+₹1.0 L (0.98%) | L2 | Rejected-Finance ABOVE FROM L1 |
| 3 | L3₹1.2 Cr+₹9.1 L (8.63%)Rejected-Finance | ₹1.2 Cr+₹9.1 L (8.63%) | L3 | Rejected-Finance ABOVE FROM L1 |
| 4 | L4₹1.2 Cr+₹10.3 L (9.76%)Rejected-Finance VINOD VIHAR COLONY HATHRAS | HATHRAS | UTTAR PRADESH | 202139 | ₹1.2 Cr+₹10.3 L (9.76%) | L4 | Rejected-Finance ABOVE FROM L1 |
Tender Value
Refer Docs
EMD Value
₹2.6 L
Closing Date
21 Oct 2021, 5:00 pmClosed
SE,MGCCC, BULANDSHAHAR
Office of The SE,MGCCC, BULANDSHAHAR
Construction of Drainage Syphon at Km. 24.500 of Hasanpur Dy and Construction of Canal from Km. 24.450 to Km. 24.600 of Hasanpur Dy
2021_UPIDC_629585_3
01/SE/2021-22
Open Tender
Civil Works - Canal
Item Rate
120 days
HASANPUR
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,714
₹2.6 L
14 Dec 2021
13 Oct 2021
22 Oct 2021
13 Oct 2021
21 Oct 2021
13 Oct 2021
13 Oct 2021 - 21 Oct 2021
Amount
Earthwork in Excavation of foundation in ordinary soil including all lift & lead and including back filling, watering and ramming excavated earth as per site requirement and with removal and proper disposal of surplus earth including all cost of material, labour, T&P etc. as per directed by engineer-in-charge for proper completion of work.
Ordinary Form for Cement Concrete Block including cost of all material, labour, T&P, etc. as per directed by engineer in charge complete for proper completion of work.
Supply and laying of stone grit size 10 to 20 mm in 75mm gap between concrete block and inverted filter including cost of all material labour T&P etc. as per directed by engineer in charge complete for proper completion of work.
Supply and laying of Shingle size 4.75 to 10 mm in inverted filter including cost of all material labour T&P etc. as per directed by engineer in charge complete for proper completion of work.
Supply and laying of Coarse Sand in inverted filter including cost of all material labour T&P etc. as per directed by engineer in charge complete for proper completion of work.
Cement Concrete in (1:2:4) M15 mix with Cement, Coarse Sand (F.M. not less than 2.00), Stone Grit (A-20) including cost of all material, labour, T&P, Machanical Mixing, Curing etc. as per directed by engineer in charge complete for proper completion of work
Providing and fixing Centering & shuttering for P.C.C. work of Cut off, Box etc. including cost of all material, labour, T&P, all lifts and leads, etc complete for proper completion of work as per directed by engineer in charge .
Cement Concrete in (1:1.5:3) M20 mix with Cement, Coarse Sand (F.M. not less than 2.00), Stone Grit (A-20) including cost of all material, labour, T&P, Machanical Mixing, Curing etc. as per directed by engineer in charge complete for proper completion of work
Cement Concrete in (1:1:2) M25 mix with Cement, Coarse Sand (F.M. not less than 2.00), Stone Grit (A-20) including cost of all material, labour, T&P, Machanical Mixing, Curing etc. as per directed by engineer in charge complete for proper completion of work
Centering & shuttering fo R.C.C. work in defferent parts of structures all leads & lifts required for proper completion of work including cost of all materials and scaffolding, labour, T&P. etc.
Cutting, Bending, Binding & Placing in position of steel reinforcement with all wastage, carriage and including all labour material and T&P etc complete for proper completion materials, labour and T&P etc.
S/L of Two coat Tar Felt Painting above sleepers including cost of all material, labour, T&P complete for proper completion of work as per direction of Engineer - in charge.
Providing 125 micron polythin sheet below lining including cost of all material, labour, T&P complete for proper completion of work as per direction of Engineer - in charge.
Providing 150 mm thick Cement Concrete Lining in (1:2:4) mix with Cement, Coarse Sand (F.M. not less than 2.00), Stone Grit (A-10) i/c cost of all material, labour,T&P etc. complete for proper completion of work as per direction of Engineer - in charge.
Provide & Laying Boulder 40.00 to 70.00 kg.wt in bed & sides with all lead and lift including cost all labour, T&P material etc complete for proper completion of work as per direction of Engineer - in charge.
Providing and cutting, bending, branzing and crimping 690 mm wide 20 SWG of U-type Stainless Steel seal as approved shape and size required for proper completion of work including cost of materials, labour, T&P, etc as per direction of Engineer - in charge.
Earth work in Filling in embankment in ordinary soil including ramming and dressing the surface to be required levels and slopes and also including all lift and Lead upto 1 km distance including cost of all Labour T&P etc complete as directed by Engineer-in- charge.
Providing & Fixing of Year Plate for proper completion of work as per directed by Engineer In Charge
Providing & Fixing of BM Plate for proper completion of work as per directed by Engineer In Charge
M/s Lisa Construction
gopi construction
SUNIL KUMAR CONTRACTOR
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .