Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹717.12Accepted-AOC | ₹717.12 Quoted ₹7.2 Cr | L1 | Accepted-AOC Bid is responsive |
Tender Value
₹5.4 Cr
EMD Value
₹10.8 L
Closing Date
6 Jan 2020, 1:00 pmClosed
Chief Engineer
Chief Engineer, URRDA, First Floor in Directorate Panchyati Raj, Opposite IT park, Shastradhara Road, Dehradun,
UT03-23 Construction and Maintenance 2 years of Kalsir to Gudam Nail Nouli Kunji motor road Stage-I Length -10.225 Km
2019_CCUK_86481_1
UT03023
National Competitive Bid
Civil Works - Roads
Item Rate
540 days
Pokhari
As per technical Bid
4 documents required · 4 mandatory
₹5,000
CE URRDA
₹10.8 L
SE PMGSY Gopeshwar HQ Gaucher
23 Apr 2020
25 Dec 2019
6 Jan 2020
25 Dec 2019
6 Jan 2020
27 Dec 2019
28 Dec 2019
Amount
Earth work in hill road (hill side cutting):- Excavation in hilly area for construction of road in all types of soils & rocks as met at site , true to lines as per plan, L section , camber, super elevation as required , also including uprooting & cutting of bushes, dressing of road surface to the required level and slopes, with all lead, lift and safe disposal of surplus excavated material at suitable dumping places by mechanical means/ manual means as directed by Engineer in charge without damaging forest , forest land , utility and private properties ,including slip clearance during hill side cutting as directed by Engineer-in-charge and as per MORD specifications clause 1600
Removal of landslide (Slip clearance) in all types of soil and rock by mechanical means/ manual means and disposal of safe side only in after completion of hill side cutting as per road design as directed by Engineer in charge and MORD specification, clause 1611(Slip clearance considered only those reaches where the Hill side cutting has been completed and handed over to Engineer in charge)
Excavation for Structures: - Earth work in Excavation foundation for cross drainage structures, retaining walls, breast walls & other similar structures in all types of soils and rocks as met at site with all leads, lifts and disposal of surplus earth as directed by engineer in charge including supply of all material labour, T&P etc. required for proper completion of work in accordance with the MORD specification.
Random Rubble masonry for structure laid in 1:5 cement and sand mortar by locally available approved stone and sand from approved quarry including supply of all material,labour,T&P etc., required for completion of work as per drawing as per MORD specification for cross drainage structure, retaining wall, breast wall as other similar structure directed by Engineer in charge
Random Rubble stone masonry for structure laid dry by locally available approved stone, including supply of all materials, labour, T&P etc required for proper completion of work as per drawing & as per MORD specification for retaining walls, breast walls & other similar structures as directed by Engineer-in-Charge.
Hand packed stone filling in the back of retaining walls, abutments, wing walls etc. by locally available approved stone including supply of all material, labour, T&P etc. required for proper completion of the work as directed by Engineer in charge.
Providing edge stones on valley side of formation as directed by Engineer-in-charge and MoRD Specification Clause 1608.4
Providing and laying of boulder apron laid in wire crates with 4 mm dia G.I. Wire conforming to IS: 280 & IS: 4826 in 100mm x 100mm mesh (woven diagonally) including 10% extra for laps and joints laid with stone boulders weighting not less than 25 Kg each as per drawing and technical specification of MORD and as directed by Engineer in charge.
Construction of parapet in RR stone masonry laid in 1:5, C/S mortar providing M10 cement concrete in top, plaster in 1:4 C/S mortar & flush pointing in 1:3 C/S mortar as required and specified in detailed drawing with white washing complete as per the direction of Engineer in charge.( witht base CC M10 )
Construction of hill side Pucca drains as per drawing including supply of all material, labour, T&P etc. required for proper completion of the work as directed by Engineer-in-charge and MORD Specification for Rural Roads 2014.
Construction of hill side KUCCHA drainsIn according with the requirment of specfication true to line and grades. required for proper completion of the work as directed by Engineer-in-charge and MORD Specification for Rural Roads 2014.`
Granular sab-bas /base /surface course with lacal materials by mix in place method normal. Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared sueface,mixing by mix in place mothod with smooth wheeled roller to achieve the desired density complete as per clause 401.4 and as per technical specification clause 408.SI No 4.11 (1)(ii)
Construction of pucca scupper including catch pit including supply of all materials, labour, T&P etc required for proper completion of work as per drawing mord specification as directed by Engineer-in-Charge.
Construction of Dry scupper including catch pit including supply of all materials, labour, T&P etc required for proper completion of work as per drawing mord specification as directed by Engineer-in-Charge.
Providing & laying M10 grade plain cement concrete in open foundation asper MORD material labour specification including all material labour T&P etc. as directed by Engineer in charge.(for causeway)
Providing & laying RCC M25 grade plain cement concrete in open foundation asper MORD material labour specification including all material labour T&P etc. as directed by Engineer in charge.(for causeway)
providing and fixing 5 Kilometer stone as per standard drawing made of Precast R.C.C. M15 grade fixed with pcc M10 grade .including excavation of pit, painting and printing letters on kilometer stone with two coat of synthetic enamel paint of approved quality as directed by engineer in charge.
providing and fixing 1 Kilometer stone as per standard drawing made of Precast R.C.C. M15 grade fixed with pcc M10 grade .including excavation of pit, painting and printing letters on kilometer stone with two coat of synthetic enamel paint of approved quality as directed by engineer in charge.
providing and fixing of hectometer stone as per standard drawing made of Precast R.C.C. M15 grade fixed with pcc M10 grade .including excavation of pit, painting and printing letters on kilometer stone with two coat of synthetic enamel paint of approved quality as directed by engineer in charge.
Providing fixing of Title Information Board with PMGSY Logo at suitable place in the starting of the road as per attached standard drawing duly painted and written as per the MORD specification and direction given by Engineer in charge.
Providing & fixing of semi reflective traffic sign board (cautionary mandatory & informatory) as per attached drawing dully painted and written as per the mord specification and as direted by Engineer in charge
Providing fixing of PMGSY Logo board at suitable place in the starting of the road as per attached standard drawing duly painted and written as per the MORD specification and direction given by Engineer in charge.
Providing & fixing of Citizen Information Board with PMGSY Logo at starting or prominent location (where maximum no. of citizens can view the detail of the road) as per attached standard drawing dully painted and written as per the MORD specification and direction of Engineer-in-charge.
Providing & fixing of semi reflective Direction and place identification sign board up to 0.90sqm as per attached standard drawing dully painted and written as per the MORD specification
Construction of reference pillar (totally under ground) of length km 200mm, width 200mm and height 300mm) as per 1600.1 (b) and Technical specification clause 1602.3 of MORD specifications for rural roads
Construction of back pillrs, of length 300mm,width 300mm and km height 400mm of which 100mm shall be below ground level as per Fig. 1600.1 (b) and Technical specification clause 1602.3 of MORD specifications for rural roads
Construction of job pillar of length 400mm,width 400mm and km height 600mm of which 100mm shall be below ground level as per Fig.1600.1 (d) and Technical specification clause 1602.4 of MORD specifications for rural roads.
Emergency Maintenance
Major Slip Clearance in all Type of Soil ,rock and boulders including cost of all material , machine,T&p etc required for proper compeletion of work as per mord specification of work 1611
Ist Year
Iind Year
Deploying Hydraulic excavator of 0.90cum bucket for clearence of Major slip in all type of soil rock and boulders including its operator ,pol, and all other charges required for proper compeletion of work
Ist Year
Iind Year
Providing and laying of boulder apron laid in wire crate with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and techniacal specification 1301
Ist Year
Iind Year
Coolie Walling including supply of all material, labour, T&P,royalty etc. required for proper completion of the work,as directed by Engineer-in-charge and as per PWD specifications 8.90 (For opening communication only)
Ist Year
Iind Year
Routine Maintenance- Under PBMC:
Maintenance under PBMC for 1] Trimming of grass and weeds from the shoulders/berms and disposing off the same to suitable locations as per technical specifications Clause 1914. 2] Maintenance of road side Drains including minor slip clearence , reshaping ,deepening and ,regrading ,as well as catch water drains as per technical specification Clause 1907. 3]Maintenance of shoulders to the required level by filling/cutting the soil and its compacting including disposal of the surplus material in approved muck disposal points as per specification clause 1903 . 4] Maintenance of scuppers & Culverts by way of clearing, Cleaning, Erosion repair, repairs to cracks, parapet walls and Protection works as per drawing and technical specification Clasue 1908. 5] Maintenance of Causeway by way of minor Surface repairs, replacing Guide Posts, repair of flood gauges, removal of debris, providing boulders and protection work and painting as per technical specification Clause 1909. 6] Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory / cautionary / informatory and place identifications sign board as per drawings and technical specification Clause 1910. 7] Maintenance of 200 metre km stone by way of refiting of tilted stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone and 5th km stone as per drawing and technical specification Clause 1912. 8] Two coat white washing on parapet walls of CD work ,edge stones, tree truncks, and prominent rock patches on hill sides including preparation of surface by cleaning scraping etc. as per technical specifications Clause 191.
Ist Year
Iind Year
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .