Executive Engineer, Petlad Irrigation Division Petlad
Constructing Box type VRB in place of damaged pipe VRB at ch. 0 mt on Baliya kaka kyari lateral drain.
332870
05 of 2026-2027
Open
Miscellaneous Works
Turn-key
Anand
13 documents required · 10 mandatory · 3 optional
₹900
Executive Engineer Petlad Irrigation Division Petlad
₹22,000
11 Aug 2026
11 Aug 2026
11 Aug 2026
25 Aug 2026
11 Aug 2026
Memorandum showing items of works to be carried out
NAME OF Constructing Box type V.R.B.in place of damaged pipe V.R.B. at Ch. 0 mt. on Baliya
WORK :- kaka kyari lateral Drain
I. accoarding to
but may Item of work Rs. in Unit
No. Rs. in figs. estimated
be more words quantities
Dismantling the existing R.C.C. Pipes including
sorting out and stacking of the useful materials
of the following diameters including refilling the Rs. Eight
trenches etc. complete as directed.600 mm. to Hundred Sixty
900 mm Six & Forty
Dismantling R.C.C. work and disposing off Rs. One
stuff including stacking of the useful materials Thousand
etc. complete as directed.(a) heavy Seven
2 12.00 reinforcement (Main bar up to 16mm Dia) 1732.80 Hundred CM
Excavation for foundation in all sorts of soil
including yellow sandy gravelly soils ,soft &
hard murrum etc. in dry condition including Rs. One
depositing the excavated stuff in uniform layers Hundred
3 383.00 in banks or as and where directed etc. complete 107.80 Seven & CM
for lead up to 500m and all lift. (BY Eighty Paise
MACHINERY) Including Dewatering Only
Providing & Laying in position "NOMINAL MIX"
cement concrete using cement, sand and
crushed aggregate by mass and machine mix for
C.C./R.C.C work incl. necessary formworks Rs. Three
centering, scaffolding, compaction by vibrator, Thousand
4 57.00 curing as directed with all lead & lift etc 3346.00 Three CM
complete Without Dewatering and excluding Hundred Forty
cost of steel reinforcement. Six Only
Providing & Laying in position "DESIGN MIX"
cement concrete using cement sand and
crushed aggregate for C.C./ R.C.C work by
"FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator,
curing as directed with all lead & lift etc
complete without dewatering and excluding the
5 (A) 60.00 cost of steel reinforcement.. (A) For Footing of 4190.00 CM
column / Abutment / Pier / Bottom slab of
barrel / Plinth course / Coping /Approch slab
etc. (e) Concrete grade M-15 and MSA-20 mm
Providing & Laying in position "DESIGN MIX"
cement concrete using cement sand and
crushed aggregate for C.C./ R.C.C work by
"FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator,
curing as directed with all lead & lift etc Rs. Four
complete without dewatering and excluding the Thousand Six
5 (B) 41.00 cost of steel reinforcement. (A) For Footing of 4651.00 CM
column / Abutment / Pier / Bottom slab of One Only
barrel / Plinth course / Coping /Approch slab
etc. (e) Concrete grade M-25 and MSA-20 mm
Providing & Laying in position "DESIGN MIX"
cement concrete using cement sand and
crushed aggregate for C.C./ R.C.C work by
"FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator,
curing as directed with all lead & lift etc
complete without dewatering and excluding the
5(C) 106.00 4457.00 Four Hundred CM
cost of steel reinforcement. (B) For Pier and
Abutments / Wing wall / Head wall / Return
wall/ Dowel wall etc. (h)Concrete grade M-15
Providing & Laying in position "DESIGN MIX"
cement concrete using cement sand and
crushed aggregate for C.C./ R.C.C work by
"FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Five
curing as directed with all lead & lift etc Thousand
5('D) 9.00 complete without dewatering and excluding the 5481.00 Four Hundred CM
cost of steel reinforcement. (D) For Kerb / Eighty One
Wearing coat. (n) Concrete grade M-25 and MSA Only
Providing & Laying in position "DESIGN MIX"
cement concrete using cement sand and
crushed aggregate for C.C./ R.C.C work by
"FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator,
curing as directed with all lead & lift etc Rs. Five
complete without dewatering and excluding the Thousand Six
cost of steel reinforcement. (E) For Column / Hundred Forty
Beam / Solid Slab of Road Bridge / Barrel / Two Only
Cutoff wall etc. (q) Concrete grade M-25 and
Providing & Laying in position "DESIGN MIX"
cement concrete using cement sand and
crushed aggregate for C.C./ R.C.C work by
"FLORI" including necessary formwork,
centering, scaffolding, compaction by vibrator, Rs. Eight
curing as directed with all lead & lift etc Thousand
5('F) 2.00 complete without dewatering and excluding the 8023.00 CM
cost of steel reinforcement. (F) For Perapet wall Only
of Road Bridge / Structure (t)Concrete grade M-
25 and MSA -10 to 20 mm
Providing & Placing in position reinforcement Rs. Seven
bars including cutting, bending, welding joints Thousand One
6 75.500 where necessary, hooking etc. complete as per 7194.00 Hundred QTL
drawing for all lead and lifts.TMT Ninety Four
Providing and laying in position 110 mm dia (6
kgf/sqcm) P.V.C. Pipe for weep holes with non Rs. Two
corroding jali in abutments, wing walls, Hundred Sixty
retaining walls etc. complete. Two & Fifty
Providing and fixing 110 mm diameter
P.V.C..Pipe (6 kgf / sq cm) Water spout with Rs. Three
necessary iron grating as per design Hundred Sixty
Back filling the foundation trenches around the
structures etc with selected excavated stuff Rs. Thirty Six
9 69.00 including watering, ramming, compacting etc. 36.90 & Ninety Paise CM
complete. (By Machinery) Only
Providing temporary all weather and fair
weather diversion suitable for traffic during the Rs. One
construction period of the structure including Thousand
all safty measures including red lamps/ signals Nine Hundred
at night for traffic etc. comp Fifteen &
Providing temporary all weather and fair
weather diversion suitable for drain diversion
during the construction period of the structure
11 15.00 including all safty measures including red 2611.37 RMT
lamps/ signals at night for traffic etc. comp
Providing drone videography on the occaion of
function or for before/on going/after completion
of construction work including dubbing , titeling Rs. Four
12 1.00 etc. complete including cost of cassette/CD 4000.00 Thousand
Rs. Twenty One Lac Thirty One Thousand Four Hundred Ninety Four & Sixty One Paise Only
1 The rate quoted in above schedule-B shall be considered for approved & present.
2 The qty. shown above may be adjusted more or less than est. quality keeping the cost of excavation of one tank
I / We am /are willing to carry out the work at ............ % above /below................................
.................................................( percent should written in figures and words )
of the estimated rate mentioned above.Amount of my / our tender work out as under.
Estimated Estimated amount
Deduct :- ____ % Below Rs. _______________ Add ____ % above Rs. ______
Net Tender amount Rs. ______________ Net Tender amount Rs.
Notes 1 - All work shall be carried out as per Public Works Department Handbook and specifications of Division or as
directed by supervisory staff.
Notes 2 - The persons of firm submitting the tender should see that the all the columns in the schedule should be filled in
inkand total of entries in last column should be struck by the contractor under his signature.
Notes 3 - Rates quoted include clearing of site (prior commencement of work and at its close ) in all respects and hold
good for work under all conditions, site, moisture, weather etc.
Note 4 - The meaning of abbreviationss used in units are as under.
CM - Cubic Meter SM - Square Meter RMT - Running Meter
Deputy Executive Engineer
Drain Sub Division
Signature of contractor. Khambhat
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Tender Notice 05 of 2026-27 online.pdf
1 Front Page.pdf
2. Notice Inviting online Tender.pdf
3.SBD-Documen baliaya kaa kyari ch 0m.pdf
5.iteamwise specification.pdf
BOQ.pdf
Cement Consumption baliayakaaka.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].