| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.2 LAccepted-AOC | L1 | Accepted-AOC ALL DOCUMENTS ARE FOUND CORRECT | |
| 2 | Rejected-Technical | - | Rejected-Technical L2 |
Tender Value
Refer Docs
EMD Value
₹21,150
Closing Date
20 Mar 2025, 4:00 pmClosed
ASSISTANT ENGINEER
Assistant Engineer LSGD Engineering wing Thalassery Municipality
GENERAL HOSPITAL MORTURY DRAINAGE COVERING SLAB
2025_LSGD_732168_21
E1-117/24
Open Tender
Civil Works - Others
Item Rate
180 days
THALASSERY
Please refer Tender documents.
10 documents required · 10 mandatory
₹1,865
Yes
₹21,150
Yes
28 Jun 2025
13 Mar 2025
21 Mar 2025
13 Mar 2025
20 Mar 2025
13 Mar 2025
Amount
DRAIN
15.3:Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge.
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
5.1.3:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
SATHEESH DAS K (BID ID -2165371)
Bidder Name
SATHEESH DAS K
KARUNAKARAN K P
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1213883.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .