| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹28.7 LAccepted-AOC BELOW SLAUGHTER HOUSE KRISHNA NAGER SHIMLA | SHIMLA | SHIMLA | HIMACHAL PRADESH | ₹28.7 L | L-1 | Accepted-AOC Being 1st lowest |
| 2 | L-2₹32.9 L+₹4.2 L (14.4%)Rejected-AOC | ₹32.9 L+₹4.2 L (14.4%) | L-2 | Rejected-AOC Being 2nd lowest |
| 3 | L-3₹33.2 L+₹4.5 L (15.6%)Rejected-AOC | ₹33.2 L+₹4.5 L (15.6%) | L-3 | Rejected-AOC Being 3rd lowest |
Tender Value
₹31.9 L
EMD Value
₹64,000
Closing Date
16 Apr 2026, 9:00 amClosed
EE Nirmand
Executive Engineer outer Seraj Division HP PWD Nirmand
Restoration of rain damages on Ranabag to Kandibag road portion Guhatan to Lot km 0/000 to 10/800
2026_PWD_133877_1
No PW OSDN NIT 2025 480-85 dated 02.04.2026
Open Tender
Civil Works
Percentage
90 days
Nirmand
Please refer Tender documents.
11 documents required · 11 mandatory
₹2,000
₹64,000
17 Jul 2026
9 Apr 2026
16 Apr 2026
9 Apr 2026
16 Apr 2026
9 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in soil in Hilly Area in all kinds of soil by all means including cutting and trimming of side slopes and disposing of excavated earth upto all leads and lifts as per drawing and technical Specification clauses 1603.1 and as per direction of The Engineer-In-Charge complete including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Cubic Metre | - | - |
| 2 | Excavation work by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains for all kinds of soil and ordinary rocks including dressing of sides and ramming of bottoms upto all lifts including getting out the excavated soil and disposal of surplus excavated soil as directed, within all leads and lifts including entire carriage of materials in all leads and lifts and as per drawings and technical specifications as per the direction of Engineer-in-Charge including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Cubic Metre | - | - |
| 3 | Providing and Laying plain cement concrete 1:5:10 (one cement : five sand : ten graded stone aggregate 40 mm (forty millimetre) nominal size) in open foundations complete as per drawing and technical specification clauses 802, 803, 1202 and 1203 including curing and carriage of materials in all leads and lifts as per direction of The Engineer-In-Charge including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Cubic Metre | - | - |
| 4 | Stone masonry work in cement mortar in sub-structure complete as per drawing and technical specifications Clause 702, 704, 1202 & 1203. Randaom rubble masnory in cement mortar 1:6 (one cement : six sand) including curing and carriage of materials in all leads and lifts as per direction of The Engineer-In- Charge including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Cubic Metre | - | - |
| 5 | Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 including carriage of materials in all leads and lifts as per direction of The Engineer-In-Charge complete including all incidentals. The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Cubic Metre | - | - |
| 6 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. including hauling of materials in all leads and lifts and as per entire satisfaction and direction of Engineer-in-charge. | - | Cubic Metre | - | - |
| 7 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/ binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405 by Mechenical Means including carriage of materials through all modes of transportaion with in all leads and lifts as per directions of the Engineer-In-Cherge including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | 1 | Cubic Metre | - | - |
| 8 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/ binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 3 as per Technical Specification Clause 405 by Mechenical Means including carriage of materials through all modes of transportaion with in all leads and lifts as per directions of the Engineer-In-Cherge including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Cubic Metre | - | - |
| 9 | Providing and applying priming coat with bitumen emulsion (SS-1) using bitumen distributor at the rate of 0.85 kg. (Zero point eight five Kilogramme) per square metre on the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specifications clause of 502 including carriage of materials, plants/equipments by all modes of transportation with in all leads and lifts and as per directions of The Engineer – in – Charge complete including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Square Metre | - | - |
| 10 | Providing and applying tack coat with bitumen emulsion (RS-I) using emulsion pressure distributor @ 0.275 kg (Zero point two seven five Kilogramme) per square metre of the prepared dry and hungry bituminous surface cleaned with Hydraulic broom as per Technical Specifications of clause 503 including carriage of materials, plants/equipments by all modes of transportation with in all leads and lifts and as per directions of The Engineer – in – Charge complete including all incidentals.The rates are inclusive of octroi, royality, malkana, toll tax, sale tax, GST or other taxes imposed by the Government. | - | Square Metre | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.17 MB
BOQ_197903.xls
BOQ • 0.40 MB
SBDNo1.pdf
Tender Documents • 3.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .