| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹14.4 LAccepted-AOC | ₹14.4 L | L1 | Accepted-AOC Based on BOQ chart, work awarded to the L1 bidder at the quoted amount |
| 2 | L2₹14.5 L+₹8,981.15 (0.62%)Rejected-AOC | ₹14.5 L+₹8,981.15 (0.62%) | L2 | Rejected-AOC L2 bidder |
Tender Value
₹14.6 L
EMD Value
₹36,412
Closing Date
17 Jun 2025, 5:00 pmClosed
CEO Technopark
Technopark Phase 1 campus, Trivandrum
Construction of new sports ground
2025_ETPK_765493_1
ETPK/PH1/226/2025-26
Open Tender
Civil Works - Others
Item Rate
30 days
Technopark Phase 1 Campus
As mentioned in Bid1 document
2 documents required · 2 mandatory
₹2,950
₹36,412
25 Jul 2025
21 May 2025
18 Jun 2025
21 May 2025
17 Jun 2025
21 May 2025
Amount
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. The rate inclusive of all material charge, labour, transportation, Scaffolding (If needed) loading/unloading at the work space and removal of debris outside Technopark campus etc for all floors and all heights, complete as per the direction of engineer in charge.
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. 2.6.1 All kinds of soil. The rate inclusive of all material charge, labour, transportation, Scaffolding (If needed) loading/unloading at the work space and removal of debris outside Technopark campus etc for all floors and all heights, complete as per the direction of engineer in charge.
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. The rate inclusive of all material charge, labour, transportation, Scaffolding (If needed) loading/unloading at the work space and removal of debris outside Technopark campus etc for all floors and all heights, complete as per the direction of engineer in charge.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:2:4 (cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).The rate inclusive of all material charge, Labour, transportation, Scaffolding (If needed) loading/Unloading at the work space and removal of debris outside Technopark campus etc.for all floors and all heights,complete as per the direction of engineer in charge.
Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 10nn dia round bar and nuts , bolts and washers as required complete as per the direction of Engineer-in- charge.Made of G.I. wire of dia 4 mm.The rate inclusive of all material charge, Labour, transportation, Scaffolding (If needed) loading/Unloading at the work space and removal of debris outside Technopark campus etc.for all floors and all heights,complete as per the direction of engineer in charge.
Steel work in built up GI tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing position and applying a priming coat of approved steel primer(after removing existing oil content of the G.I section), including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes.The rate inclusive of all material charge, Labour, transportation, Scaffolding (If needed) loading/Unloading at the work space and removal of debris outside Technopark campus etc.for all floors and all heights,complete as per the direction of engineer in charge.
Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, MS flat, TMT round rod, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.The rate inclusive of all material charge, Labour, transportation, Scaffolding (If needed) loading/Unloading at the work space and removal of debris outside Technopark campus etc.for all floors and all heights,complete as per the direction of engineer in charge.
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade: Two or more coats on new work.The rate inclusive of all material charge, Labour, transportation, Scaffolding (If needed) loading/Unloading at the work space and removal of debris outside Technopark campus etc.for all floors and all heights,complete as per the direction of engineer in charge.
Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel including two coats of enamel paint.etc. as required. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works.The rate inclusive of all material charge, Labour, transportation, Scaffolding (If needed) loading/Unloading at the work space and removal of debris outside Technopark campus etc.for all floors and all heights,complete as per the direction of engineer in charge.
SAM GEORGE (BID ID -2226541)
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1247394.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .