| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹49.9 LAccepted-AOC | ₹49.9 L | L1 | Accepted-AOC Accepted as L1 |
| 2 | L2₹51.5 L+₹1.6 L (3.16%)Rejected-Finance | ₹51.5 L+₹1.6 L (3.16%) | L2 | Rejected-Finance Financial bid passion is L2 |
| 3 | L3₹53.3 L+₹3.4 L (6.73%)Rejected-Finance | ₹53.3 L+₹3.4 L (6.73%) | L3 | Rejected-Finance Financial bid passion is L3 |
| 4 | L4₹54.7 L+₹4.7 L (9.48%)Rejected-Finance FLAT NO 203 KADIRIS APURUPA URBAN 2 ND FLOOR LAXMI NAGAR BOTANICAL GARDEN ROAD KONDAPUR HYDERABAD 500084 RANGAREDDI TELANGANA 500084 | HYDERABAD | TELANGANA | 500084 | ₹54.7 L+₹4.7 L (9.48%) | L4 | Rejected-Finance Financial bid passion is L4 |
| 5 | Rejected-Technical | - | - | Rejected-Technical Not meeting NIT criteria. |
| Sl No | Description | Qty | Unit | JAYRAM INDUSTRIES INDIA PRIVATE LIMITED L4 | SHRI SAI ELECTRICAL L3 | IMPULSE TECHNOLOGY L2 | S2H Power Solutions Private Limited L1 |
|---|---|---|---|---|---|---|---|
| 1.00 | Annual maintenance and monitoring 2 MWp roof top type solar photovoltaic power plant installations comprising of installed solar PV modules, structural support system, power conditioning units, lighting and earthing protection systems, solar system cables, LT evacuation/injection points/terminals, auxiliary & control supply system, DC &AC distribution boards along with available switchgears & control gears, invertor rooms along with AC & DC power cables, other allied communication and control cables, including solar plant radiation & environment monitoring system excluding SCADA system and including cleaning of modules as per scope of works & technical specification enclosed and as directed by the Engineer-in-charge.
For 1st Year | 12 | Month | 1,61,030 ₹19,32,360 | 1,46,000 ₹17,52,000 | 1,45,833 ₹17,49,996 | 1,40,000 ₹16,80,000 Lowest |
| 2.00 | Annual maintenance and monitoring 2 MWp roof top type solar photovoltaic power plant installations comprising of installed solar PV modules, structural support system, power conditioning units, lighting and earthing protection systems, solar system cables, LT evacuation/injection points/terminals, auxiliary & control supply system, DC &AC distribution boards along with available switchgears & control gears, invertor rooms along with AC & DC power cables, other allied communication and control cables, including solar plant radiation & environment monitoring system excluding SCADA system and including cleaning of modules as per scope of works & technical specification enclosed and as directed by the Engineer-in-charge.
For 2nd Year | 12 | Month | 1,61,030 ₹19,32,360 | 1,46,000 ₹17,52,000 | 1,45,833 ₹17,49,996 | 1,45,000 ₹17,40,000 Lowest |
| 3.00 | Annual comprehensive maintenance of following invertors as per OEM standard and as directed by the Engineer –in-charge.
(i) 62.5 KWp 33 nos.
(ii) 33 KWp -01 no.
(Note: Rates shall be firm and consolidated including necessary repair, maintenance, replacement of any defective component of inverters or replacement of completely defective inverters with new inverters of equivalent ratings/specifications etc.)
For 1st Year | 12 | Month | 27,500 ₹3,30,000 Lowest | 49,000 ₹5,88,000 | 37,300 ₹4,47,600 | 30,000 ₹3,60,000 |
| 4.00 | Annual comprehensive maintenance of following invertors as per OEM standard and as directed by the Engineer –in-charge.
(i) 62.5 KWp 33 nos.
(ii) 33 KWp -01 no.
(Note: Rates shall be firm and consolidated including necessary repair, maintenance, replacement of any defective component of inverters or replacement of completely defective inverters with new inverters of equivalent ratings/specifications etc.)
For 2nd Year | 12 | Month | 27,500 ₹3,30,000 Lowest | 49,000 ₹5,88,000 | 41,200 ₹4,94,400 | 30,000 ₹3,60,000 |
| 5.00 | Annual comprehensive maintenance of the complete SCADA system (Hard ware & software) related to the above installations to deliver all the status of 2 MWp PV solar system as per item no. 01 on daily basis and as directed by the Engineer-in-charge.
(Note: Rates shall be firm and consolidated including any necessary hardware/software upgradation, proprietary software license fee, internet charges, laptop/desktop at AAI Office for SCADA monitoring etc.)
For 1st Year | 12 | Month | 19,500 ₹2,34,000 | 12,000 ₹1,44,000 Lowest | 14,499 ₹1,73,988 | 18,000 ₹2,16,000 |
| 6.00 | Annual comprehensive maintenance of the complete SCADA system (Hard ware & software) related to the above installations to deliver all the status of 2 MWp PV solar system as per item no. 01 on daily basis and as directed by the Engineer-in-charge.
(Note: Rates shall be firm and consolidated including any necessary hardware/software upgradation, proprietary software license fee, internet charges, laptop/desktop at AAI Office for SCADA monitoring etc.)
For 2nd Year | 12 | Month | 19,500 ₹2,34,000 | 12,000 ₹1,44,000 Lowest | 14,499 ₹1,73,988 | 20,000 ₹2,40,000 |
| 7.00 | The execution of DSR (E&M) 2022 of estimate Amount of Rs. 2,00,000.00 Item mentioned in chapter 1 to chapter 17 including Appendix-I & II as when required basis for repair/ maintenance/ addition/ alternation etc. of internal and external electrical installations.
[Quoting in the rate 10% below the Estimate amount of Rs. 2,00,000.00 means amount will be Rs. 1,80,000.00
Similarly quoting in the rate 10% above the estimated amount Rs. 2,00,000.00 means amount will be Rs. 2,20,000.00]
(Note: Payment of DSR rate will be made after deduction of GST considered in the rate of DSR - 2022)
For 1st Year | 2,00,000 | % above or below | 5 ₹2,10,000 | 20.02 ₹1,59,960 Lowest | 20 ₹1,60,000 | 12 ₹1,76,000 |
| 8.00 | The execution of DSR (E&M) 2022 of estimate Amount of Rs. 2,50,000.00 Item mentioned in chapter 1 to chapter 17 including Appendix-I & II as when required basis for repair/ maintenance/ addition/ alternation etc. of internal and external electrical installations.
[Quoting in the rate 10% below the Estimate amount of Rs. 2,50,000.00 means amount will be Rs. 2,25,000.00
Similarly quoting in the rate 10% above the estimated amount Rs. 2,50,000.00 means amount will be Rs. 2,75,000.00
(Note: Payment of DSR rate will be made after deduction of GST considered in the rate of DSR - 2022)
For 2nd Year | 2,50,000 | % above or below | 5 ₹2,62,500 | 20.02 ₹1,99,950 Lowest | 20 ₹2,00,000 | 12 ₹2,20,000 |
Tender Value
₹55.3 L
EMD Value
₹1.1 L
Closing Date
14 Aug 2024, 6:00 pmClosed
Sr Manager
Operational Office Building NSACBI AIRPORT KOLKATA
Work contract for Annual Comprehensive Maintenance Operation and Monitoring of 2MWp Roof Top type Solar Power Plant at NSCBI Airport Kolkata for the Year 2024 2026
2024_AAI_201511_2
AAC/EMD-VIII/ AMC of 2MWp SOLAR/2024-25
Open Tender
Electrical Works
Item Rate
730 days
NSACBI AIRPORT KOLKATA
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Yes
₹1.1 L
Yes
3 Sept 2025
24 Jul 2024
16 Aug 2024
24 Jul 2024
14 Aug 2024
24 Jul 2024
24 Jul 2024 - 1 Aug 2024
Amount
Annual maintenance and monitoring 2 MWp roof top type solar photovoltaic power plant installations comprising of installed solar PV modules, structural support system, power conditioning units, lighting and earthing protection systems, solar system cables, LT evacuation/injection points/terminals, auxiliary & control supply system, DC &AC distribution boards along with available switchgears & control gears, invertor rooms along with AC & DC power cables, other allied communication and control cables, including solar plant radiation & environment monitoring system excluding SCADA system and including cleaning of modules as per scope of works & technical specification enclosed and as directed by the Engineer-in-charge. For 1st Year
Annual maintenance and monitoring 2 MWp roof top type solar photovoltaic power plant installations comprising of installed solar PV modules, structural support system, power conditioning units, lighting and earthing protection systems, solar system cables, LT evacuation/injection points/terminals, auxiliary & control supply system, DC &AC distribution boards along with available switchgears & control gears, invertor rooms along with AC & DC power cables, other allied communication and control cables, including solar plant radiation & environment monitoring system excluding SCADA system and including cleaning of modules as per scope of works & technical specification enclosed and as directed by the Engineer-in-charge. For 2nd Year
Annual comprehensive maintenance of following invertors as per OEM standard and as directed by the Engineer –in-charge. (i) 62.5 KWp 33 nos. (ii) 33 KWp -01 no. (Note: Rates shall be firm and consolidated including necessary repair, maintenance, replacement of any defective component of inverters or replacement of completely defective inverters with new inverters of equivalent ratings/specifications etc.) For 1st Year
Annual comprehensive maintenance of following invertors as per OEM standard and as directed by the Engineer –in-charge. (i) 62.5 KWp 33 nos. (ii) 33 KWp -01 no. (Note: Rates shall be firm and consolidated including necessary repair, maintenance, replacement of any defective component of inverters or replacement of completely defective inverters with new inverters of equivalent ratings/specifications etc.) For 2nd Year
Annual comprehensive maintenance of the complete SCADA system (Hard ware & software) related to the above installations to deliver all the status of 2 MWp PV solar system as per item no. 01 on daily basis and as directed by the Engineer-in-charge. (Note: Rates shall be firm and consolidated including any necessary hardware/software upgradation, proprietary software license fee, internet charges, laptop/desktop at AAI Office for SCADA monitoring etc.) For 1st Year
Annual comprehensive maintenance of the complete SCADA system (Hard ware & software) related to the above installations to deliver all the status of 2 MWp PV solar system as per item no. 01 on daily basis and as directed by the Engineer-in-charge. (Note: Rates shall be firm and consolidated including any necessary hardware/software upgradation, proprietary software license fee, internet charges, laptop/desktop at AAI Office for SCADA monitoring etc.) For 2nd Year
The execution of DSR (E&M) 2022 of estimate Amount of Rs. 2,00,000.00 Item mentioned in chapter 1 to chapter 17 including Appendix-I & II as when required basis for repair/ maintenance/ addition/ alternation etc. of internal and external electrical installations. [Quoting in the rate 10% below the Estimate amount of Rs. 2,00,000.00 means amount will be Rs. 1,80,000.00 Similarly quoting in the rate 10% above the estimated amount Rs. 2,00,000.00 means amount will be Rs. 2,20,000.00] (Note: Payment of DSR rate will be made after deduction of GST considered in the rate of DSR - 2022) For 1st Year
The execution of DSR (E&M) 2022 of estimate Amount of Rs. 2,50,000.00 Item mentioned in chapter 1 to chapter 17 including Appendix-I & II as when required basis for repair/ maintenance/ addition/ alternation etc. of internal and external electrical installations. [Quoting in the rate 10% below the Estimate amount of Rs. 2,50,000.00 means amount will be Rs. 2,25,000.00 Similarly quoting in the rate 10% above the estimated amount Rs. 2,50,000.00 means amount will be Rs. 2,75,000.00 (Note: Payment of DSR rate will be made after deduction of GST considered in the rate of DSR - 2022) For 2nd Year
IMPULSE TECHNOLOGY
SHRI SAI ELECTRICAL
JAYRAM INDUSTRIES INDIA PRIVATE LIMITED
stage.html
html • 0.06 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .