Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.7 LRejected-Finance | ₹5.7 L | L1 | Rejected-Finance DUE TO SINGLE TENDER |
Tender Value
₹6.9 L
EMD Value
₹6,866
Closing Date
17 Feb 2026, 5:00 pmClosed
EXECUTIVE OFFICER, PURI MUNICIPALITY
VIP ROAD
CIVIL
2026_ORULB_125283_14
PM 06/2025-26
Open Tender
Civil Works - Others
Percentage
120 days
PURI MUNICIPALITY
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,000
₹6,866
Yes
17 Aug 2026
4 Feb 2026
18 Feb 2026
4 Feb 2026
17 Feb 2026
4 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation of foundation in oridinary soil within the initial lead and lift including dressing and levelling the bed and depositing the excavated materials away from the work site etc. all complete as directed by the Engineer-in-charge | 19.75 | Cum | 206.06 | ₹4,069.69 |
| 2 | Sand Filling foundation and plinth with sand well watered and rammed including all cost, carriage, royality, taxes and all labour, T & P etc. all complete as per the direction of Engineer-in- charge. | 17.32 | Cum | 912.18 | ₹15,798.96 |
| 3 | Cement concrete (1:3:6) using 40mm and down gradedhard granite crusher broken metal including all cost , carriage, royality, taxes, and all labour involved for completion of item of work as per the direction of Engineer- in - charge. | 4.69 | Cum | 6,528.9 | ₹30,620.54 |
| 4 | Providing R.C.C. M20grade with 20mm and down graded CBHG chips including hoisting and laying with all cost carriage royality taxes and all labour involved for the completion of item of work as per direction of Engineer-in- charge.
Column Base | 2.3 | Cum | 6,956.36 | ₹15,999.63 |
| 5 | Column&Beam | 2.27 | Cum | 18,625.8 | ₹42,280.57 |
| 6 | Plinth Beam | 2.65 | Cum | 6,956.36 | ₹18,434.35 |
| 7 | Stair Case | 1.94 | Cum | 16,085.7 | ₹31,206.26 |
| 8 | Lintel | 1.05 | Cum | 14,617.3 | ₹15,348.16 |
| 9 | Slab | 5.44 | Cum | 14,201.9 | ₹77,258.34 |
| 10 | TMT reinforcement for R.C.C. work including cutting, bending, binding and placing in position Labor for including cost of binding wire 18 to 20 gauge and cost conveyance of M.S. rod etc. all complete. | 12.39 | Qtl | 8,433.16 | ₹1,04,486.85 |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
finance_578843.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.86 MB
Tendernotice_2.pdf
PDF • 0.68 MB
BOQ_578843.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .