Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹35.0 LAccepted-AOC | L1 | Accepted-AOC Admitted | |
| 2 | L2₹36.1 L+₹1.0 L (2.95%)Rejected-AOC | L2 | Rejected-AOC Verified |
Tender Value
₹36.1 L
EMD Value
₹50,000
Closing Date
9 Jan 2020, 3:00 pmClosed
The Executive Engineeer
The Executive Engineeer PWD Roads division kollam
Deposit work 2019-20. Urgent restoration work in Kottiyam Kundara road due to pipe laying works between Km 1/760 and 3/000
2019_PWD_330707_2
143/Et/EE/2019-20
Open Tender
Civil Works - Roads
Item Rate
60 days
Kollam
Please refer Tender documents.
4 documents required · 4 mandatory
₹2,760
Yes
The Executive Engineeer PWD Roads division kollam
₹50,000
Yes
26 May 2020
31 Dec 2019
13 Jan 2020
31 Dec 2019
9 Jan 2020
31 Dec 2019
Amount
3.3 : Excavation for road way in soil with Dozer including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead 50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.Excavation for road way in soil with Dozer including cutting and pushing the earth to site of embankment upto a distance of 100 metres (average lead 50 metres), including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections.
4.1.B.1 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br> Grading-V - For sub base cum drainage layer - Mix in Place MethodConstruction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub base cum drainage layer - Mix in Place Method
4.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
5.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.
5.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.
5.3.2.a : Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder (VG 30), transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction.<br> For Grading II - (19 mm nominal size)<br>Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder (VG 30), transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction.For Grading II - (19 mm nominal size)
5.6.2.a : Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder( NRMB) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects Grading - II (13.2 mm Nominal Size)<br>Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder( NRMB) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respectsGrading - II (13.2 mm Nominal Size)
Sudheer Sukumaran
Bidder Name
PRABHAKARAN GOVINDAN
Sudheer Sukumaran
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_464263.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .