| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.1 LAccepted-AOC | L1 | Accepted-AOC Accepted | |
| 2 | L2₹5.4 L+₹32,918.39 (6.47%)Rejected-AOC | L2 | Rejected-AOC Rejected |
Tender Value
₹5.1 L
EMD Value
₹12,800
Closing Date
17 Jan 2022, 5:00 pmClosed
Assistant Engineer
The Assistant Engineer, LSGD Section,Muriyad GP
2021-22 Muriyadu GP Construction of motor shed in Harithasree cole padav(pro no.266)
2022_LSGD_466568_1
06/2021/AE/LSGD/MYD
Open Tender
Civil Works - Buildings
Item Rate
90 days
Anandhapuram
Please refer Tender documents.
3 documents required · 3 mandatory
₹1,239
Yes
₹12,800
Yes
16 Feb 2022
10 Jan 2022
19 Jan 2022
10 Jan 2022
17 Jan 2022
10 Jan 2022
Amount
motor shed
2.8.1 : Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
4.1.6 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 ( 1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
5.2.2 : Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
5.3 : Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size).
5.9.1 : Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.5 : Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.6 : Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
50.6.2.1 : Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x15 cm or nearest available size confirming to IS 2185 part I of 1979 for foundation and plinth with thickness 15cm in: CM 1:6 ( 1 cement :6 coarse sand) etc complete
5.22A.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
50.10.2 : Steel work for purlin/single section with G I pipes including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete
od1520856/2021_2022 : Roofing with G.I hard colouur powder coated traffod sheets 0.35 mm thick or nearest availablethickness with overlaps of 150 mm at ends and GI hook or crank C.I. bolts and nuts includingplain washers and bitumen washers etc complete
od1520857/2021_2022 : Ridge capinging with pre painted galvenised steel sheets 0.5 mm thick 60 cm wide including all<br>cost and materials, conveyance, labour charges etc. complete.
50.2.3.1 : Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
60.1.2 : RING BUND Type II Putting up ring bund with earth fille gunny bags of top width 1.0m bottom width 2.0m height 2.0 m side and filling in between with earth to form ring bund and maintaining the same leak proof till the completion of the work and clearing the site by dismantling the bund after completion of the work.etc.complete.
60.8 : Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete
od1522949/2021_2022 : Supplying and fixing chain block including all cost and conveyance etc. 2 tonne
N V RAMESH
Bidder Name
N V RAMESH
kr rajendran
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .