Loading…
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Tender Value
₹8.2 L
EMD Value
₹20,388
Closing Date
1 Jan 2026, 3:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Assistant Executive Engineer,
PH Sub Division Adimali
O and M Running Contract 2025-26 Anuual Maintenance of various water supply scheme RWSS to Munnar and RWSS to Devikulam in Munnar and Devikulam Panchayaths under PH Section Devikulam
2025_KWA_823130_1
WRD/KWA-CE(CR)/TR/22988/2025_5
Open Tender
Civil Works - Water Works
Item Rate
Munnar Devikulam
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,800
₹20,388
13 Jan 2026
20 Dec 2025
3 Jan 2026
20 Dec 2025
1 Jan 2026
20 Dec 2025
20 Dec 2025 - 1 Jan 2026
Supply of materials.
OD155038/2025-2026:Supply of 90 mm CIR Joint.
OD155057/2025-2026:Supply of 110 mm CIR joint.
OD155048/2025-2026:Supply of 140 mm CIR joint.
OD155128/2025-2026: Supply of 80mm class 10 CID joint.
OD155127/2025-2026: Supply of 100 mm class 10 CID joint.
OD155126/2025-2026:Supply of 150 mm class 10 CID joint.
OD155125/2025-2026:Supply of 200 mm class 10 CID joint.
OD155124/2025-2026:Supply of 300 mm class 10 CID joint.
OD155263/2025-2026:Supply of 15 mm medium class GI pipe.
OD155264/2025-2026:Supply of 32 mm medium class GI pipe.
OD155265/2025-2026:Supply of 40 mm medium class GI pipe.
OD155266/2025-2026:Supply of 50 mm medium class GI pipe.
OD155874/2025-2026:Supply of 65 mm medium class GI pipe.
OD155873/2025-2026:Supply of 80 mm medium class GI pipe.
OD155872/2025-2026:Supply of 100 mm medium class GI pipe.
100.98.232:Supply of PVC Pipe, 10kg/cm2, 40mm Dia.
100.98.234:Supply of PVC Pipe, 10kg/cm2, 63mm Dia.
100.98.236:Supply of PVC Pipe, 10kg/cm2, 90mm Dia.
100.98.237:Supply of PVC Pipe, 10kg/cm2, 110mm Dia.
100.98.238:Supply PVC Pipe, 10kg/cm2, 140mm Dia.
100.56.1:Supplying and fixing 15 / 20 mm PVC public tap after dismantling the damaged tap including all cost of materials, labour charges, hire for tools and as per the direction of the department officers etc complete.
Working Charge
100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil.
100.98.15:Supply of Red Coloured Flouracent caution tape.
100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals.
50.2.25.1:Filling with contractor's own earth ( excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix)
15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
100.47.1.2:Leak rectification work in 40mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the remaining portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe to the site, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or any available joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and without causing any damages to the existing utilities and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, lighting, watching, ribbon fencing, traffic controlling etc., complete as per the direction of Departmental officers including the cost of pipe and uPVC specials; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: All Socketed Jointing.
100.47.1.4:Leak rectification work in 63mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the remaining portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe to the site, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or any available joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and without causing any damages to the existing utilities and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, lighting, watching, ribbon fencing, traffic controlling etc., complete as per the direction of Departmental officers including the cost of pipe and uPVC specials; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: All Socketed Jointing.
100.47.1.6:Leak rectification work in 90mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the remaining portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe to the site, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or any available joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and without causing any damages to the existing utilities and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, lighting, watching, ribbon fencing, traffic controlling etc., complete as per the direction of Departmental officers including the cost of pipe and uPVC specials; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: All Socketed Jointing.
100.47.2.1:Leak rectification work in 90mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earth work excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the balance portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or repairable joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and refilling the trenches in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, without causing any damages to the existing utilities, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, lighting, ribbon fencing, watching, traffic control etc., complete as per the direction of Departmental officers, including the cost of pipe & specials but excluding the cost of C.I.R. Joints; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: Socket & C.I.R. Jointing.
100.47.3.1:Leak rectification work in 90mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the balance portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or repairable joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and refilling the trenches in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, without causing any damage to the existing utilities, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, ribbon fencing, lighting, watching, traffic control etc., complete as per the direction of Departmental officers, including the cost of pipe & specials but excluding the cost of C.I.R. Joints; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: C.I.R. Jointing.
OD151480/2025-2026:Leak rectification work in 110mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the remaining portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe to the site, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or any available joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and without causing any damages to the existing utilities and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, lighting, watching, ribbon fencing, traffic controlling etc., complete as per the direction of Departmental officers including the cost of pipe and uPVC specials; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: All Socketed Jointing.
100.47.2.2:Leak rectification work in 110mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earth work excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the balance portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or repairable joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and refilling the trenches in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, without causing any damages to the existing utilities, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, lighting, ribbon fencing, watching, traffic control etc., complete as per the direction of Departmental officers, including the cost of pipe & specials but excluding the cost of C.I.R. Joints; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: Socket & C.I.R. Jointing.
100.47.3.2:Leak rectification work in 110mm uPVC (Class 2 to 6) pipeline including detecting and locating leak, earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, cutting the pipe diametrically perpendicular to the axis of pipeline without causing any damages to the balance portion, dismantling and lifting the pipe from trenches, smoothening the cut ends, conveying the new pipe, cutting and lowering new pipe into the trenches, placing in position, aligning the pipe to line and level and jointing the new pipe with the existing pipe with solvent cement or repairable joint and testing the pipeline by operating the valves concerned, and rectifying the defects if noticed and refilling the trenches in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, charges for removing surplus soil from work site, without causing any damage to the existing utilities, including hire for tools and plant, conveyance of tools and materials, bailing out water, providing caution boards, ribbon fencing, lighting, watching, traffic control etc., complete as per the direction of Departmental officers, including the cost of pipe & specials but excluding the cost of C.I.R. Joints; uPVC Pipes and specials shall be of good quality and conforming to relevant standards: C.I.R. Jointing.
100.50.1.1:Rectification of leakages of 32mm, 40mm & 50mm G.I. Pipes by replacing lengths up to 1.0m including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar / concrete cutting, by cutting, removing and stacking the damaged portion from the existing line without causing any damages to the remaining portion and specials and conveying and replacing with G.I. Pipes of suitable size and jointing by thraded coupler and union of suitable size including threading, alignment, laying and jointing to make a water tight joint, testing the line to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges hire and conveyance of tools, plant and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion, including the cost of specials but excluding cost of pipe and as per the direction of departmental officers etc., complete.
100.50.1.2:Rectification of leakages of 65mm G.I. Pipes by replacing lengths up to 1.0m including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar / concrete cutting, by cutting, removing and stacking the damaged portion from the existing line without causing any damages to the remaining portion and specials and conveying and replacing with G.I. Pipes of suitable size and jointing by thraded coupler and union of suitable size including threading, alignment, laying and jointing to make a water tight joint, testing the line to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges hire and conveyance of tools, plant and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion, including the cost of specials but excluding cost of pipe and as per the direction of departmental officers etc., complete.
100.50.1.3:Rectification of leakages of 80mm G.I. Pipes by replacing lengths up to 1.0m including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar / concrete cutting, by cutting, removing and stacking the damaged portion from the existing line without causing any damages to the remaining portion and specials and conveying and replacing with G.I. Pipes of suitable size and jointing by thraded coupler and union of suitable size including threading, alignment, laying and jointing to make a water tight joint, testing the line to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges hire and conveyance of tools, plant and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion, including the cost of specials but excluding cost of pipe and as per the direction of departmental officers etc., complete.
100.50.1.4:Rectification of leakages of 100mm G.I. Pipes by replacing lengths up to 1.0m including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar / concrete cutting, by cutting, removing and stacking the damaged portion from the existing line without causing any damages to the remaining portion and specials and conveying and replacing with G.I. Pipes of suitable size and jointing by thraded coupler and union of suitable size including threading, alignment, laying and jointing to make a water tight joint, testing the line to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges hire and conveyance of tools, plant and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion, including the cost of specials but excluding cost of pipe and as per the direction of departmental officers etc., complete.
100.48.2.4:Rectification of minor joint leakages in 150mm C.I. Pipe including earthwork excavation in all kinds of soil for exposing leaking joint including tar cutting / concrete cutting, without causing any damages to the line and specials, cleaning the joints including raking out the damaged lead wool, conveying and inserting hemp and lead wool and caulking after cleaning the ends, charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of conveyance and hire for tools and plant, bailing out water, lighting, watching, ribbon fencing, providing caution boards, traffic diversion, including cost of materials and as per the direction of departmental officers etc., complete.
100.48.3.4:Rectification of joint leakages in 150mm C.I. Pipe including earthwork excavation in all kinds of soil for exposing leaking joint including tar cutting / concrete cutting, without causing any damages to the line and specials, cleaning the joints including raking out the damaged hemp and lead, conveying hemp and lead and providing lead joint after cleaning the joint, charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of conveyance and hire for tools and plant, bailing out water, lighting, watching, ribbon fencing, providing caution boards, traffic diversion, including cost of materials and as per the direction of departmental officers etc., complete, but excluding the cost of pig lead.
100.48.4.4:Rectification of breakages up to 2.0m length in 150mm C.I. Pipes, including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, by cutting and removing and stacking the damaged portion from the existing line without causing any damages to the line and specials and replacing with Collar and jointing with hemp & lead after cleaning the ends, centering the pipe, testing the line to the required test pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth, including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of hire & conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion and as per the direction of departmental officers etc., complete, but excluding the cost of pipes, collar and pig lead.
100.48.2.1:Rectification of minor joint leakages in 80mm C.I. Pipe including earthwork excavation in all kinds of soil for exposing leaking joint including tar cutting / concrete cutting, without causing any damages to the line and specials, cleaning the joints including raking out the damaged lead wool, conveying and inserting hemp and lead wool and caulking after cleaning the ends, charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of conveyance and hire for tools and plant, bailing out water, lighting, watching, ribbon fencing, providing caution boards, traffic diversion, including cost of materials and as per the direction of departmental officers etc., complete.
100.48.3.1:Rectification of joint leakages in 80mm C.I. Pipe including earthwork excavation in all kinds of soil for exposing leaking joint including tar cutting / concrete cutting, without causing any damages to the line and specials, cleaning the joints including raking out the damaged hemp and lead, conveying hemp and lead and providing lead joint after cleaning the joint, charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of conveyance and hire for tools and plant, bailing out water, lighting, watching, ribbon fencing, providing caution boards, traffic diversion, including cost of materials and as per the direction of departmental officers etc., complete, but excluding the cost of pig lead.
100.48.4.1:Rectification of breakages up to 2.0m length in 80mm C.I. Pipes, including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, by cutting and removing and stacking the damaged portion from the existing line without causing any damages to the line and specials and replacing with Collar and jointing with hemp & lead after cleaning the ends, centering the pipe, testing the line to the required test pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth, including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of hire & conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion and as per the direction of departmental officers etc., complete, but excluding the cost of pipes, collar and pig lead.
100.49.1.1:Rectification of joint leakages in 100mm D.I. Pipe (cutting, removing and laying back a length of 1.0m from one side of the joint) including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, by cutting and removing a portion of pipe from the damaged joint without causing any damages to the remaining portion of the line and specials and replacing the pipe with mechanical and tyton joint after cleaning the ends, centering the pipe, providing the joints, testing the line to the required test pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of hire and conveyance of tools, plants and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of mechanical joint and as per the direction of departmental officers etc., complete.
100.49.1.3:Rectification of joint leakages in 200mm D.I. Pipe (cutting, removing and laying back a length of 1.0m from one side of the joint) including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, by cutting and removing a portion of pipe from the damaged joint without causing any damages to the remaining portion of the line and specials and replacing the pipe with mechanical and tyton joint after cleaning the ends, centering the pipe, providing the joints, testing the line to the required test pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of hire and conveyance of tools, plants and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of mechanical joint and as per the direction of departmental officers etc., complete.
100.49.1.5:Rectification of joint leakages in 300mm D.I. Pipe (cutting, removing and laying back a length of 1.0m from one side of the joint) including earthwork excavation in all kinds of soil for exposing leak portion of the pipe including tar cutting / concrete cutting, by cutting and removing a portion of pipe from the damaged joint without causing any damages to the remaining portion of the line and specials and replacing the pipe with mechanical and tyton joint after cleaning the ends, centering the pipe, providing the joints, testing the line to the required test pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of hire and conveyance of tools, plants and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of mechanical joint and as per the direction of departmental officers etc., complete.
100.51.2:Disconnecting water connection from service mains along Concrete road without causing any damage to the existing line including charges of earth work excavation in all kinds of soil for exposing connection point including tar cutting / conrete cutting, making the disconnection point water tight charging and testing to the required pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other existing utilities, including the charges of hire for tools and plant, conveyance of tools and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion but excluding cost of materials and as per the direction of departmental officers etc. complete.
100.57.1:Rectifying the leakages in boring point of public tap connection including earth work excavation in all kinds of soil for exposing the boring point including concrete / tar cutting, dismantling the damaged saddle piece,cutting and removing damaged portion of pipe line,fixing new saddle piece,laying 20/25 mm PVC 10Kg/cm2 pipe in place of damaged portion of pipe and connecting with existing pipe line,testing the line to the required test pressure, rectifying any defects noticed and refilling the trenches using excavated earth in layers not exceeding 20cm depth including consolidating each layers by ramming, watering, removing the surplus soil from the work site, without causing any damages to any other utilities, including the charges of hire and conveyance of tools, plants and materials to the leak site, bailing out water, lighting, watching, ribbon fencing, caution boards, traffic diversion, including cost of pipe and saddle piece and as per the direction of departmental officers etc. complete.
100.98.1008:Engaging Coolie.
100.53.1.a:Washing OHSR/GLSR using brooms, brushes and bleaching powder by engaging coolies, scrubbing twice, washing and cleaning using fresh water, including side wall, floor slab and columns, disposing the the slurry / waste materials away from the immediate premises and within the initial lead of 50m from the periphery of the tank, without causing any damage to the existing structure and installations, charges including the operation of valves, conveyance and hire charges of tools and as per the direction of the department officers etc. complete.
50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete
100.98.1009:Engaging Fitter ( grade 1).
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.82 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
KWAGeneralConditionsforeTenderingV5.pdf
PDF • 0.69 MB
Tendernotice_1.pdf
PDF • 0.04 MB
Tendernotice_2.pdf
PDF • 1.04 MB
BOQ_1379596.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .