Loading…
Loading…
Tender Value
₹383.8 Cr
EMD Value
₹3.8 Cr
Closing Date
30 Sept 2026, 5:00 pm7d left
Superintending Engineer (CG), GIDC, Bharuch
Engineering, Procurement, Construction (EPC) with Commissioning Including Testing, Trial Run and Comprehensive O&M&R of Common Steam Plant - Turbine Power Generation & Steam distribution Network for the Capacity of 210 TPH and 28 MW At Bulk Drug Park Industrial Estate, Jambusar, Bharuch, Gujarat ( Re- Invited).
343493
E-Tender Notice No. 05 of 2026-27 Sr. No. 03
Open
Mechanical - All
Works
Bharuch
15 documents required · 15 mandatory
₹21,240
Executive Engineer, GIDC, Bharuch
₹3.8 Cr
9 Sept 2026
9 Sept 2026
9 Sept 2026
30 Sept 2026
9 Sept 2026
MECHANICAL
BOILER
BOILER PRESSURE PARTS
Fully welded steam drum with internals, man holes and necessary nozzle connections for mounting valves & fittings. Steam drum will be complete with all nozzle connections for steam, feed water, down comers, drain valves, safety valves, vents, level gauges and required instruments etc.
Water cooled membrane enclosure with headers and necessary connections like drains
Bed tubes with SS studs and headers
Convection Super heater tube assemblies with inlet and outlet header along with coil supports
Radiant Super heater tube assemblies with inlet and outlet headers along with coil supports
Necessary links between Drum and main steam stop valve
Down comers and Riser as necessary
Economiser tube assemblies with inlet & outlet headers along with coil supports
Economiser casing & ash hopper with stiffener, access doors & isolation gate
Air preheater tubes and tube sheets (by pass ducting & last Six raws of corton steel)
Air heater casing & ash hopper with stiffener, access doors & isolation gate
Circulation system of the boiler including down comers, supply pipes and riser pipes
Economiser system including tubes, all inter connecting piping and headers. Economiser hanger tubes. Casing for economizer. Economiser intermediate headers
Saturated steam piping from steam drum to convection cage top header
Desuperheaters system Water flow measurement with three transmitter between superheaters. (Supplier to decide the number of attempreater)
Desuperheaters system Water flow measurement with three transmitter for PRDS, Deaerator, Process steam (Supplier to decide the number of desuperheater)
STEAM FLOW MEASURMENT
Steam Flow measurement with three number of transmitter along with totalizer at 1. Boiler Outlet 2.Turbine Inlet 3.Turbine Extraction 4.PRDS Inlet 5.Process steam to All consumer industries 6.Deaerator Inlet
RAW WATER MAKEUP MEASUREMENT
Water flow measurement at raw water makeup at Auxiliary cooling tower
RETURN CONDENSATE MEASUREMENT DEVICE
Return condensate flow measuring device from all the consumer. Return condensate flow to each south and North Location Return condensate flow to each deaerators at each North and South Location.
FUEL STORAGE FEEDING& FIRING SYSTEM
MS fabricated Fuel bunkers 2 x 85 m3 for each 30 TPH Boiler and 2 X 225 m3 for each 75 TPH boiler along with supporting structures. 2 Nos level indicators RF type and Load cell for each boiler bunkers
Coal evacuation from bunker with piping and isolating valve
SS 409 lining up to 1.6 mts from bottom conical portion
SS 409 lining up to 1.6 mtsin mixing hopper below each fuel feeder.
Manually operated rod pin cum rack & pinion gate at each fuel bunker outlet
Volumetric drag chain feeders with VFD, Pocket feeder with VFD
Motor operated knife-edge isolation gates in the fuel feed chute
Air bustle units for the fuel feed chutes
Fuel feed chute from bunker outlet to feeder and feeder outlet to combustor
Floor at an level 6m from bunker top for supporting the High rise conveyor discharge end with chute arrangement.
All the floors over bunker top shall be provided with chequered plate with adequate stiffeners
LIME STORAGE & FEEDING SYSTEM
1 X 10 m3 for each 75 TPH Boiler and 1 X 5 m3 for each 30 TPH boiler MS fabricated limestone bunker along with supporting structures. 1 Nos level indicators RF type for each.
Pocket feeder with VFD for feeding limestone
Manually operated rod pin cum rack & pinion gate at bunker outlet
Bunker top cover plate
SS 409 lining up to 1.6 mts from bottom conical portion
SS 409 lining up to 1.6 mts in mixing hopper below each feeder.
BED MATERIAL STORAGE AND FEEDING SYSTEM
1X10 m3 for 75 TPH boilers & 1X5 m3 for 30 TPH boilers MS fabricated bed material bunker along with supporting structures
Pocket feeder with constant speed drive motor for feeding bed material
Manually operated rod cum rack & pinion gate at bunker outlet
PRDS & DSH
Total 1 Nos. by pass PRDS along with all required instruments. Inlet of PRDS shall be from CSDH
1 No. DSH Control Station, Process Steam with all required instruments
START UP FUEL Supplier to decide the requirement
Flow meter, Igniter, scanner
Wind box with required pneumatic dampers
Instruments as required.
Instrument air piping with valves & fittings
SOOT BLOWERS
Two Retractable and Two rotary soot blowers For SH & Econmiser Zone
Drive motors
Control panel if required.(Soot blower operation shall be from DCS)
Pressure reducing station with accessories
Soot blower steam piping from attemprator header to individual soot blowers
Motorised Non-Inching type valve for main isolation for soot blower steam
Motorised Non-Inching type valve in drain laine for temperature control of soot blower steam
Pressure gauge
Temperature gauge
Pressure safety valve
BOILER DUCTING AND DRAFT SYSTEM
2 X 100 % (PA) (1W+1s)Primary air fan Each for Boilers: Horizontal, radial, simply supported and backward curved blade , complete with necessary base frame, foundation bolts, coupling, coupling guard, Grease lubrication system, speed of PA fan will be 1500 rpm (max.). Fan will be provided with bird and trash screen at inlet with silencer.
Outlet isolation dampers for PA fan motorized
Pneumatically operated control damper
VFD for PA Fans in case of LT motors / HT VFD in case of HT motors.
2 X 60 %(FD) Forced Draft Fan Each for Boilers: Horizontal, radial, simply supported and backward curved blade , complete with necessary base frame, foundation bolts, coupling, coupling guard, Grease lubrication system, speed of SA fan will be 1500 rpm (max.). Fan will be provided with bird and trash screen at inlet with silencer.
Outlet isolation dampers for SA fan motorized
Pneumatically operated control damper
VFD for SA Fans in case of LT motors /HT VFD in case of HT motors.
2 X 60 %(ID) Induced Draft Fans, Each for boilers : Horizontal, radial, simply supported and backward curved blade , complete with necessary base frame, impeller lining, foundation bolts, coupling, coupling guard, Grease lubrication system, speed of ID fan will be 1000 rpm (max.). Fan will be provided with bird and trash screen at inlet
Outlet isolation dampers for ID fans motorized
Pneumatically operated control damper
VFD for ID Fans in case of LT motors/ HT VFD in case of HT motors.
Air flow measuring device in PA, FD for each boiler, secondary air etc.
Complete primary and secondary air ducting with stiffeners, expansion joints, guide vanes for bends, dampers, insulation and cladding, supports
Complete flue gas ducting up to the terminal point as required, with stiffeners, expansion joints, guide vanes for bends, supports
Over Fire Air(OFA) nozzles and complete OFA ducting with required stiffeners, expansion joints, guide vanes for bends, supports
Seal air ducting with required stiffeners, expansion joints, guide vanes for bends, supports
Air heater air side bypass duct with required regulation dampers.
ELECTRO STATIC PRECIPITATOR No of field is to be decided by supplier the number of ESP field should be decided based on current emission norms 30 mg/Nm3 with first field out condition.
Boiler operating floor shall be of RCC. Civil work upto boiler operation floor shall be by Supplier. Supporting structure above the boiler operating floor shall be done by EPC supplier. RCC footings of +300 mm for ESP and other auxiliaries shall be by Supplier. ESP structure above +300 mm shall be in supplier scope.
Electrostatic precipitator to limit the outlet dust emission level as specified in design basis
ESP hopper - thermostatically controlled hopper with dust level monitoring system
Insulator compartment with thermostatically controlled heating element
T-R sets, rapping mechanism, discharge electrodes, collecting electrodes, gas distribution screens, hopper heaters, shaft insulators, electrical and mechanical interlock system, ESP TR set control panel, micro processor based controllers for T-R sets, hopper level indicators, access door for hoppers, poke holes. Inlet / outlet funnels for ESP. Hopper heaters are thermostatically controlled
ESP casing and hoppers, sliding supports
Metallic expansion bellows at inlet and outlet of ESP
All control panels of ESP, viz. TR set control panel, rapper controller and rapper distribution / temperature scanners / timers, ESP junction boxes & cabling from junction boxes to DCS .
Provision of serial communication facility in the TR set, rapper controllers of the ESP.
Local canopy over TR set
OTHER NON PRESSURIZED PART
Tubular air pre heater with casing and supports to preheat the combustion air with last six rows of airheater tubes shall be corten steel material of construction. (Airheater with flue gas flow outside the tubes and air flow inside the tubes). Airheater air bypass arrangement on AUTO with pneumatically operated damper is provided for both PA / FD airheater along with damper.
Bed ash cooler units (2 nos.) complete in all respects including connecting ducting, dampers, and air nozzles. Bed ash cooler drain pipe. Bed ash cooler discharge ducting to furnace. It should be with auto operation and monitoring from control room. The bed ash conveying complete including the bed ash silo is to be considered.
Complete bed assembly including Air nozzles, ash drains
Manhole, Peephole door, fire door, as required for operation and maintenance.
Boiler buckstays, tie connectors, corner connectors, stiffeners, channels and guides, seal boxes, cover plates as required
Suitable operating mechanism with access for operation and maintenance of all manual and power cylinder / motor operated dampers
Expansion bellow between economizer and air preheater
FEED WATER AND DEAERATOR
Deaerator and deaerated water tank with required piping, valves, fittings, platform, ladders, control and instrumentation. The Deaerator storage tank will be complete with required safety valve, vent, pressure indicator, gauge glass, drains, overflow nozzle, level transmitters
2 x 100 % (1W+1S) Boiler feed pumps (BFP) for 1 x 75 TPH Boiler and 2 X 100 % (1W + 1S) for 1 X 30 TPH Boiler (multistage, centrifugal, ring section) shall be complete with common base frame for pump & motor, couplings, coupling guard, mechanical seals, foundation bolts, suction strainers, piping, suction manifold, balancing leak off lines with all integral piping and valves and ring oil lubrication system. Suction and discharge headers shall be desined with consideration of next phase of installation.
VFD for BFP shall be considered for both pumps
Automatic Recirculation Valve for boiler feed pumps.
Minimum recirculation piping and balance leak off piping from the BFP up to the inlet of Deaerator with required valves, fittings
Deaerator overflow piping with solenoid valve and drain piping with manual isolation valve near the Deaerator
Bleed steam piping from inlet of Pressure Control Valve to Deaerator
Make-up water (DM water) piping to Condenstae Storage Tank (CST)
Feed control Station
1x100% & 1x30% feed control station complete with Control & Isolation valves
Feed control by pass for 1X100% control station along with pneumatic valve and intel outlet isolation valve.
Feed Flow measurement with three number of transmitter {along with totalizer at} For 3 element drum level control
BOILER MAKE UP WATER SYSTEM
Complete boiler make up water system including Piping, pumps from DM water storage tank upto CST with 2X100% pumps (1W+1S)
Make up water flow measurement for each derator.
MSRL DM water storage tank capacity 2 X 300m3 at WTP area and 2 X 300 m3 at plant area at each Plant CPP Location
PROCESS RETURN CONDENSATE MAKE UP SYSTEM
Complete process return make up water system including condensate storage tank at each location, Piping, pumps from condensate storage tank upto Deaerator with 2X100% pumps(1W+1S) through Plate type heat exchanger and Polishing unit with flow meter and all tank and pump, line instrumentation .
Raw water make up pump (1W+1S) along with piping, isolating valve upto cooling tower .
Cooling tower blow Down pit of 10 m3 with 2X100% transfer pump with suction and Discharge header and piping up to CETP area
SS insulated water storage tank capacity 20 m3 at each CPP Plant location
Online Steam & Water Analyzing System (SWAS) for each Boiler
CHEMICAL DOSING SYSTEM
Skid mounted HP dosing system with required pumps,tank,agitator,piping, valves & fittings instruments up to steam drum with common tank for 1x75 TPH and dedicated for 30TPH boiler with (1W+1S) pump configuration for each boiler.
Skid mounted LP dosing system (Ammonia/Hydrazine) with required pumps,tank,agitaor, piping, valves & fittings instruments up to Deaerator with common tank for 1x75 TPH and dedicated for 30TPH boiler with (1W+1S) pump configuration for each boiler.
Skid mounted pH correction dosing system (Sodium hyroxide) with required pumps,tank,agitaor, piping, valves & fittings instruments up to Deaerator
DM water required for HP,LP &pH dosing system from one point near the boiler to dosing tank
INTIGRAL PIPING
Feed water piping from Deaerator up to BFP suction with required valve, fittings. Deaerator for 1x75 TPH boilers and 1x30 TPH boiler with feed pump having set up of (1W+1S). Pump head calculation shall be submitted to GIDC/CONSULATNT for Approval during DDE.
Boiler feed pump suction & discharge headers
Piping for Boiler feed control station with required control valves, isolation valves and fittings, supports
Spray water piping from boiler BFP discharge to DSH for process steam
Sampling piping up to SWAS with all required valves and fittings
Continuous and intermediate Blow down tanks with required drain headers, drain and vent piping, valves, instruments
CBD & IBD piping from steam drum up to CBD / IBD tank as applicable and interconnection piping between CBD & IBD tank and further up to cooling tower along with pumps and piping.
CBD vent piping up to the inlet of Deaerator with required valves, fittings and supports.
Complete boiler integral piping consisting of all the interconnecting piping between the economiser inlet stop valve and the superheater outlet header, valves, fittings, drains, vents and safety valve exhaust piping
Pneumatic Startup vent valve with isolation valve, pressure reducing valve with diffuser & silencer.
Drum safety valve with exhaust piping with silencer up to safe elevation as required.
Super heater safety valve with silencer and exhaust piping up to safe elevation as required.
Main steam piping from final superheater outlet header up to inlet of boiler main steam stop valve (MSSV) with integral bypass.
All drain piping from headers and mainsteam line,etc up to a common drain header and further to the blow down tank as applicable.
Boiler initial filling line connection with required stub and isolation valve at the boiler drain header, etc from the terminal point.
Auxiliary & Main Cooling water supply and return piping to all equipment in scope requiring cooling water supply from cooling tower (Complete EPC Package equipment) with pressure and temperature gauge at each equipment.
Service water piping for Complete EPC Package equipment
Drinking water of required quality with water cooler adjacent Control room
Instrument air piping for equipment in scope from instrument air storage tank
Service air piping for equipment in scope from service air storage tank.
Temporary piping and target plates for steam blowing including motorised isolation valve, sacrifice valves.
Temporary piping, fittings, pumps for hydro test, steam blowing (with motorized valve returnable basis), alkali boil out.
EXTERNAL PIPING
Main steam piping from MSSV outlet to turbine inlet (ESV) including motorised valve with bypass valve at both ends.
Steam piping from main steam line to PRDS including its stess analysis
Steam piping from Boiler outlet to CSDH and CSDH to Turbine including its stress analysis. Inlet.
Steam piping from bleed to Deaerator including its stress analysis. Inlet.
Drains and vents wherever required for all the above piping up to safe elevation / blow down tank / Drain tank
All temporary piping, supports, valves, pumps and accessories required for steam blowing operation of the boiler and piping system shall also included
Condensate piping from CST outlet and up to Deaerator level control valve through ejector, GCV & L.P Heater.
Deaerator over flow piping up to flash tank.
Atmospheric Flash tank with automatic spray sytem with Level trasmitter and Associated Instrument IBR Approval is required. Drain pumps (1W+1S).
Pump (1W+1S) and piping from atmospheric flash tank to cooling tower
All turbine drain from turbine ESV to Condenser, drains after QCNRV and all steam piping drain to atmospheric flash tank
All drains of main steam line and all PRDS is to be terminate atmospheric flash tank.
All necessary Pipe supports and hangers
Necessary valves & fittings including strainers.
Miscellaneous Piping
DM tank over flow & drain piping
Condensate piping from Ejector to Condenser
Return condensate line to deaerator.
Raw water makeup pumps (1W+1S) along with piping from raw water reservoir to Cooling tower
Service air and Instrument & all other compress air piping from compressor to boiler, AHS, CHS and turbine area & individual instruments
AIR COMPRESSORS
2 x 100% (1W+1S) Lubricated compressor with VFD for boiler, turbine and balance of plant with its drives Common for instrument air, Service Air, 2 x 100% Desiccant type air drier for Instrument air at each location
Service air and instrument air receiver one for Common 1x75TPH and 1x30 TPH Boiler . 10 m3 Service Air and 5 m3 capacity Instrument Air for each CPP Plant.
CONTINEOUS EMISSION MONITORING SYSTEM (CEMS)
Complete Online analyser system for SOX, NOX and SPM dedicated for each boil with online remote calibration feature and hooked with DCS.
O2 measurement for combustion control loop as well as for AHP outlet ( 2 Nos)
SUPPORTING STRUCTURE
Boiler operating floor shall be of RCC. Civil work upto boiler operation floor shall be by Supplier. Supporting structure above the boiler operating floor shall be done by EPC supplier. RCC footings of +300 mm for ESP and other auxiliaries shall be by Supplier. ESP structure above +300 mm shall be in supplier scope.
Operating Platform (GI chequered plates and grills)
Staircases (Minimum 1.2 Meter width), ladders , Handrails , walkway shall be of hot dip GI
Foundation bolts for vendor supplied equipments
Complete steel supports for ducting
Refractory supports & casing along with stiffness
Hanger rods and spring support required as per Stress Analysis.
Supporting steel structures for boiler roof & side cladding
Approach platform from boiler to turbine hall.
Colour coated corrugated Galvalume sheets for roof and side cladding from operating floor level up to drum.
LIST OF MOTORIZED VALVE Not limited to Following but P&ID is to be approved as per enquiry specification.
Motorised Main Steam Stop Valve at Boiler with integral motorized valve
Motorised Main Steam Stop Valve at Turbine Inlet Line Near Turbne with integral motorized valve
Motorised isolation valve for start up vent valve
Motorised Intermittent blowdown valve
PRDS I for ejector & gland sealing inlet valve
PRDS II for Deaerator inlet valve
Inlet isolating valve for DSH. (1 Nos)
Inching type motorized damper for APH inlet and By pass Damper for both FD and PA system.(4 Nos)
LIST OF CONTROL VALVES -Not Limited to Following but P&ID is to be approved as per enquiry specification.
1x100% Pneumatic control valve and 1x30% Pneumatic bypass control valve for Boiler feed control station
Pmeumatic by pass valve for Attemparator spray water 1 & 2 (2 Nos)
Pneumatic control valve for Attemperator 1 spray water control
Pneumatic control valve for Attemperator 2 spray water control
Pneumatic control valve for CBD tank level control
Regulating start up vent valve with upstream motorized isolation valve
motorized feed check stop valve at ECO inlet
Pneumatic Deaerator pressure control valve
Pneumatic Deaerator Level control valve
Pneumatic CST level control valve
Pneumatic Pressure control valve for all PRDS (2 Nos)
Pneumatic Temperature control valve for all PRDS(2Nos)
BOILER REFRECTORY,INSULATION,CLADDING
Insulation and cladding with all fixing materials for boiler surface, piping, valves, air and flue gas ducting & auxiliaries
Cladding material should be Galvalume
Insulation and cladding with all fixing materials for ESP
Complete refractory material for boiler and ash coolers as required
Necessary anchors for refractory as required
Studs and retainers on pressure part surfaces for application of refractory
TURBINE
Back Pressure turbine steam turbine of 7 MW consists of
Horizontal split casing
Single piece solid forged rotor
Nozzles and Blades
Necessary thrust and radial bearings
Emergency stop valve
Steam strainer
Gear box and Couplings
Turning/Barring Gear
Gland sealing system with 2 nos of exhausters
Nozzle group control valves
Necessary interconnecting piping within the skid
Necessary cables and conduits along with junction boxes fixed on the skid
ESV & Control valves
QCNRV FFRV,Isolating Valve in all bleeds & extraction lines
Jacket Type Insulation for Turbine, Other insulation required for Piping shall be provided with AL. Cladding.
LUBE OIL SYSTEM
Main oil tank
Over head lube oil tank with associated piping& valves
Main oil pump shaft driven / Motor Driven MOP
Auxiliary oil pump and its motor
Emergency oil pump and its motor
Oil purifier(centrifuge) with associated piping
Vapour Extraction fans
Oil coolers (1W+1S)
Complete integral piping and its valves
Duplex oil filters
Necessary oil heaters
GOVERNING SYSTEM
Electro hydraulic governing system (Woodward)
Current to pressure converter
Necessary instruments for remote/manual operation
Governing system and OSPS should be with redundant power.
GENERATOR - 7 MW, 0.8 p.f- 11 kV
Three phase synchronous, brushless generator consists of
a) Stator frame
b) Stator core and windings
c)Single piece solid forged generator rotor with windings
d) Bearings and its pedestals
e) Necessary Space heaters
f) Generator cooling system (4 x 33 % SS cooler)
g) Necessary temperature monitoring, vibration monitoring system(Full Train) along with complete instrument
h) Brushless Exciter (PMG)
i) Necessary piping and its valves within the system
Excitation System
PMG & Exciter
AVR (Digital) (2A+2M), ABB Unitrol
Panels
NGR panel(As per SLD)
11KV Vacuum contactor in NGR panel for neutral isolation
LASCPT panel with metering cubical(As per SLD)
CT’s and PT’s for metering & protection (As per SLD)
Generator Relay cum metering panel ((As per SLD with redundant GPR)
Synchronising panel
E.O.P starter panel
MCC for TG auxiliaries
HT.Cables between Generator Terminal-NGR, Generator Terminal-LAVT-HT switchboard (Breaker Panel)
All electrical drives for Turbine
All power and control cables with cable trays including supports from TG MCC to individual drives
All instruments cables up to junction boxes including JB’s, and JB to DCS panel.
Local push button stations for Turbine Auxiliaries
Turbine gauge Panel (TGP) Mechanical / Digital with pressure and temperature gauges for various operating parameters. Impulse piping with fittings shall be supplied loose for interconnection between field tap-off points and gauge panel.
110 V Dc Battery & Battery charger at each location (Float& Float cum Boost )with DCDB required for entire CPP with 25% spare feeders & required for HT /LT panel. (600 AH + 600AH)
Five numbers per phase RTD for generator winding (All RTD should be of duplex type)
RTD for stator core temperature measurement 6 nos duplex
RTD for exciter field temperature 2 nos duplex
RTD for Cold air and Hot air measurement
TURBINE 7MW Controlled Extraction cum condensing type Skid mounted controlled Extraction, Cum condensing steam turbine consists of
Horizontal split casing
Single piece solid forged rotor
Nozzles and Blades
Necessary thrust and radial bearings
Emergency stop valve
Steam strainer
Gear box and Couplings
Motorized Turning/Barring Gear
Base plate for Turbine & Gear Box
Nozzle group control valves
Necessary interconnecting piping within the skid
Necessary cables and conduits along with junction boxes fixed on the skid
Control extraction for process steam
QCNRV in extraction line of process steam (Loose Supply)
Full flow relief valve in extraction line with silencer of process steam (Loose Supply)
Mannual Isolating Valve in extraction line of process steam (Loose Supply)
Turbine Exhaust hood spray system along with piping from CEP
Necessary temperature monitoring, vibration monitoring system(Full Train) along with complete instrument
Insulation and Cladding for Turbine and Piping
GOVERNING SYSTEM
Electro hydraulic governing system (Woodward 505XT)
load and speed control from DCS (zero speed autostart)
Turbine Auxiliaries control from DCS
Current to pressure converter
Necessary instruments for remote/manual operation
GENERATOR 7 MW, 0.8 p.f- 11 kV
Three phase synchronous, air cooled (CACW), brushless generator consists of (Preferred Make-TDPS)
Stator frame
Stator core and windings
Single piece solid forged generator rotor with windings
Bearings and its pedestals
Necessary Space heaters
Generator cooling system
Liquid leakage detector for Generator
Necessary temperature monitoring, vibration monitoring system(Full Train) along with complete instrument and communication port for DCS
Brushless Exciter (PMG/ Excitation TR)
Necessary piping and its valves within the system
LUBE OIL SYSTEM
Main oil tank
Over head lube oil tank (Capacity 30minutes or coasting down time of turbine whichever is higher) with associated valves and piping.
Shaft driven Main oil pump
Auxiliary oil pump and its motor
Aux Control oil pumps if Required
Emergency oil pump and its motor
Oil purifier(centrifuge) with associated Piping
Vapour Extraction fan
Oil coolers (1W+1S)
Complete integral piping and its valves
Duplex oil filters
Necessary oil heaters
Initial fill of oil
Oil flushing & conditioing
CONDENSING SYSTEM FOR EXT. CONDENSING TURBINE
Condensor Shell & Tube type, horizontal, divided water box (with sacrificial anodes), type condenser with integral hot-well, Rupture disc for condenser protection, Expansion bellow with spool piece between turbine exhaust and condenser inlet. (Capacity - 25TPH)
Start up steam ejector (hogging) with silencer,and neccessory pinpng
Steam jet air ejector system complete with:· Twin stage main ejectors (1 working + 1 standby), Inter and after condenser.Associatred air/vapour/condensate lines ( steam to be taken from controlled extraction)
Gland Steam Condenser(GSC) with complete piping for gland seal and leakage returns to GSC and GSC drains to condensor.
Complete Gland steam sealing system
Expansion bellows in condenser cooling Inlet/Outlet lines ( Loose Supply)
Condensate extraction pumps (CEP) with motors (2 x 100% capacity) Horizontal Pumps
Hot well level control on main and RC line with instruments.
Condensate piping from hot well through CEPs & ejector condensers and GSC upto recirculation, valve with pipe supports, strainers, steam traps, drains, vents with isolation.
Dry air/vapor line within specified battery limit.
GVC with complete piping for gland seal and leakage returns to GVC and GVC drains to condensor
ELECTRICALS
Main HT switchgear (as per SLD), Any HT VCB required in field .
LT SWGR, LT PCC, LT MCC, ACDB's, Ventilation DB, AC DB etc which shall be part of project and not mentioned here.
Excitation System
PMG / TR & Excitetion system
AVR (Digital) (2A+2M) Unitrol 1020
Control facility for voltage drop and power factor
NGR panel(As per SLD)
11 KV Vaccum contactor in NGR panel for netural isolation
LASCPT panel(As per SLD)
Generator Relay cum metering panel
Synchronising panel
CT’s and PT’s for metering & protection
E.O.P starter panel
MCC for TG auxiliaries
HT.Cables between Generator Terminal-NGR, Generator Terminal-LAVT-HT switchboard (Breaker Panel)
All electrical drives within the Battery limit
All power and control cables with cable trays including supports of all plant inside the battery limit
All instruments and communication cables, cable tray, with JB
Turbine control panel (TCP) Hard wired with logic controls and manual operation from Panel. Alarm announciator. Temp.scanner for generator and turbine with communication port. Turbine should be controlled from DCS too.
Turbine gauge Panel (TGP) with pressure and temperature gauges for various operating parameters. Impulse piping with fittings shall be supplied loose for interconnection between field tap-off points and gauge panel.
Generator relay panel (As per SLD)
Complete earthing above and under ground for the items/ equipments in CPP
Local push button stations for all auxiliaries.
110 V Dc Battery & Battery charger at each location (Float& Float cum Boost )with DCDB required for TG package with 25% spare feeders & required for HT /LT panel. 400 AH + 400AH)
All RTD should be of duplex type 3wire
Three numbers per phase RTD for generator winding
Above Ground Earthingfor equipments with in Battery Limit
MISCELLANEOUS
Steam Flow measurement device in Main steam line ( with two Transmitters) & Controlled Exraction Line (with one Transmitter)
Tempatature transmitter in hotwell
Level gauges in main oil tank and overhead oil tank
Foundation bolts for all items in vendor scope
Necessary insulation within the battery limit
Matting flanges all flanged end connections and loose supplied valves and fittings
Vent and exhaust piping up to building roof
Turbine Drain piping up to drain header in T.G Building
Painting
Packing & Forwarding
Transportation up to site
Transit Insurance
Unloading at site
Erection, Commissioning
Supervision of Erection and Commissioning & PG Test
Tools and Tackles for erection & commissioning
All Required Instruments necessary for control & monitoring of Turbine& its auxiliaries
Local Instruments up to junction box
Instrument Air piping from one point in turbine building up to individual control valves
Critical turbine instruments and I/Os wired upto junction box for control and monitoring from DCS.
Data ports on Governor, Turbovisory panel, Electrical relay panel etc. for monitoring from DCS
COAL HANDLING SYSTEM - (90 TPH) at each location
Covered Coal storage yard 8500 m2 for Each CPP Location shall be considered by EPC. Covered Storage Yard shall be 2 meter RCC Wall and Above that Structural shed for Coal storage shall be considred. Necessary Fire fighting system shall be covered in Coal Yard.
Ground hopper with Grizzly 2 X 75 m3 capacity
Electromechanical vibratory feeder below ground hopper with VFD
Suspension type Permanent Magnetic separator(2Nos. One at raw coal belt and another at product belt)
Metal detector
Motorized knife gate at oulet of coal feeder
Bed Ash drain pipe SS310 with knife gate pneumatic power cylinder
2 X 90 TPH Crusher with Drive
Pre and post Vibratory screen ( Circular and flip flop type) with motor (2 Nos) Moisture content should be considered 35 % in Imported coal for design purpose.
Reject conveyor
Final product conveyor (BC3, BC4 for proposed boiler)
Fire hydrant line with spraying arrangement is to be considered
Belt weigher at Product Belt
Reversible belt conveyor for feeding to bunker with motorized diverting chute for both coal bunkers, limestone and bed material.
Manual Flap gates
Bunker level measurement system, load cell / Radar type level measurement at each bunker
Dust Extraction System at Crusher house, BC-2, junction tower and bunker (4 Nos).
Dryfog Dust Suppression System at truck unloading,Crusher house, BC-2, junction tower and bunker (4 Nos), transfer points.
Bunker sealing arrangement
Inter connecting chutes
Belt Scrapper (Internal & External)
Impact pads/ idlers & Deck sheet at feeding points
Seal plate for conveyors
Conveyor system shall be dust proof with closed gantry (top & sides) GI sheets/ metapoly 0.6 mm thickness.
Grating & Hand rails (GI) for both side walk way
750 mm width Both side walkway for conveyors
Take-up arrangement
Monorail & Manual Hoist for Crusher and vibratory screen
Transfer Tower(s) 2 nos as per Layout drawing required.
Roofing & side cladding for Transfer tower(s)
Safety Switches
- Pull cord switches
- Belt sway switches
- Zero speed switches at tail pulley
Dust Suppression system with 2 X 100 % water pumps and piping spray nozzles (for Grizzly, Silos)
BED ASH HANDLING SYSTEM (dense phase) AS PER TENDER SPECIFICATION AT EACH LOCATION
Bed ash removal with suitable control devices.
Bed ash removal system from furnace with flap based isolation system
Vessel for bed ash removal with associated pipe and air line
Biomass Handling System
Complete Biomass handling system consist of gizzly hopper, Jow crusher, screem, bucket elevator, scree or belt conveyor, bunker etc. is the scope of EPC supplier,
RCC Bed Ash storage silo -35 m3 at each location
Dust Extraction, Dust suppression and Telescopic chute, expansion bellows and pneumatic knife gate at RCC Silo.
FLY ASH HANDLING SYSTEM AS PER TENDER SPECIFICATION AT EACH LOCATION
Dense phase handling system for all the fly ash hoppers
Air lock feeder below fly ash silo
Dustless unloader below fly ash silo
Bypass ash chute with ash feeder and mechanised telescopic unloading chute
Control of ASH through DCS
Ash pipes
Pipe rack with gantry
Power and control cables, cable tray, earthing
RCC/STEEL Fly Ash storage silo - 200 m3 at each location
Dust Extraction, Dust suppression and Telescopic chute, expansion bellows and pneumatic knife gate at RCC Silo.
2x100% (1W+1S)fluiding blowers with heaters for ash hoppers
Dust Extraction, Dust suppression and Telescopic chute, expansion bellows and pneumatic knife gate at RCC Silo.
Wet ash disposal with nylon fabric chute , along with Knife Gate valve, Rotary vane feeder.disposal system shall be designed for (10 tph for bed ash and 20 tph for fly ash considered.
Dry ash disposal with telescopic chutealong with Knife Gate valve, Rotary vane feeder. Disposal system shall be designed for (10 tph for bed ash and 20 tph for fly ash considered).
2x 100% (1W+1S) Lubricated Screw type(water cooled) compressor with air receiver tank and its drives for Service Air for ash conveying requirement
Instrument & control cables and cable trays from field junction box to DCS marshalling panels.
MAIN CUM AUXILIARY COOLING TOWER- 2200 m3/hr at each locations
Induced draft counter flow Cooling tower of FRP with RCC basin and FRP wall & Stack of capacity of circulating flow 735 m3/hr capacity with 3 cells each of 735 m3 capacity to meet cooling water requirement of Condenser, Turbine and Boiler Auxiliaries.
COOLING WATER SYSTEM
3x60 % ACW Pumps along with all accessories like strainer, isolating valves, header and instrumentation for the systems.
Entire cooling water piping from cooling tower outlet for Auxiliary cooling ,Sample coolers & BFP cooling with return piping up to cooling tower inlet
EOT CRANE ( Main hook capacity heaviest equipment with margin,Auxiliary hook 5 T)
EOT crane shall be suitable as per proposed TG Building.
Long Travel (LT) Gantry girder
Foundation bolts for LT gantry girder
Rail for LT motion
Main bridge double girder
Square bar for CT motion
End carriage
Trolley frame
Rubber buffer Stoppers for LT motion
Rubber buffer Stoppers for CT motion
Hook for Main hoist
Main hoist capacity is to be decided by bidder
Auxiliary hoist (5 tones)
Drives for CT and LT
Shrouded GI conductors
DSL for current collection to EOT drives
Pendant control panel
MCC for the drives
RCC Chimney : 2 nos at each locations
Complete Civil work including Earthwork , Mud matt laying, Reinforcement fabrication for foundation, Casting of suitable foundation
RCC Chimney for each Boiler shall be as per CPCB/GPCB Norms, and top dia of Chimney shall be as per exist velocity of 18 M/s.
Casting OF RCC full platforms -3 No’s (one at Top & Two nos at middle) full circle & 3 nos RCC quarter circle. 32mm NB pipe handrails at each Platform with flue gas smpling as per GPCB norms.
Construction of Acid Resistant lining upto Top height of Chimney shall be considered.
Ash hopper with isolation valve, height of isolation valve 1.55 meter.
Access Door One Number 800mm X 1500mm
Providing flue gas entry openings One Number with outside projection on all four side and fixing of MS plate for connection for flue gas technic
Applying refractory castable around the duct opening.
Fabrication & erection of M.S ladder with cage for full height.
Fixing of CI cap at chimney top.
Supply & Fixing of Aviation warning arrangement twin LED type lamp - 2no’s. at full circle platforms with necessary cabling.
Supply&Fixing of 1no Lightning arrestor arrangement with 50x6 Copper down conductor with Support Insulator and earthing arrangement.
Providing & fixing 4nos 150 GI/MS pipe as Sample-taking portholes.
Painting Shell wall outer surface with 2 coats of Epoxy paint over a coat of primer for full height.
Structural Painting ( lader, door and railing) with two coats of redoxide and two coats of Epoxy paint.
Fixing of necessary air inlet /outlet pipes with GI wire mesh.
Conventional processes which includes winch machine, mixer machine, vibrator, patterns etc.
Insurance coverage for works men for erection
Removal of scaffoldings
Cast iron cap at top of chimney (6 to 8 segments)
Sampling points for Sox, Nox and SPM analyser
WATER TREATMENT PLANT 2 X 100 m3/hr capacity
Water Treatment Plant from filtered water storage onward m3/hr permeate for Boiler Makeup, softener capacity m3/hr for CT makeup. Soft water tank 1x300 m3 at each location in plant area and 1x300 m3 at WTP location Softner Plant capacity 2x80 m3/hr at WTP area
INSTRUMENTATION & CONTROL minimum as per the EPC specification /P&ID approved.
All transmitters shall be SMART transmitters with local display unit and HART communication capability also. Temperature Element RTD/ Thermocouple shall be DUPLEX and K-type only.
Thermocouples/RTD to measure
Bed temperature
Flue gas temp. after economizer
Flue gas temp. before economizer
Flue gas temp. after multi-tubular air preheater
Air temp. after multi-tubular air preheater
Feed water temp. before economizer
Feed water temp. after economizer
Feed water temp. HP heater 1 inlet/outlet
Feed water temp.HP heater 2 inlet/outlet
Feed water temp.LP heater 1 inlet/outlet
Main Steam Line at ESV
Extraction Steam to HP heater and LP heater
Extraction Steam to Deaerator
Turbine exhaust
Turbine Front Journal Bearing
Turbine Rear Journal Bearing
Turbine exhaust Bearing
Generator Front Journal Bearing
Generator Rear Journal Bearing
Gear Box Bearing inlet
Gear Box Bearing out let
Pressure gauges to measure
Steam pressure at steam drum & super heater outlet
Feed line pressure before feed control valve
Main Steam Line at ESV
Extraction Steam to HP heater and LP heater
Extraction Steam to Deaerator
Steam Line to hogging ejector
1st stage and 2nd stage of Steam Jet Air Ejector (SJAE)
Condensate water from CST inlet
Condensate water from CST outlet
Gland steam inlet
Gland steam outlet
De-superheating water line
Control Oil Line
Lube oil line
Main oil Pump Discharge
ACW Pumps & common Discharge Header
ACW Return Header
Pressure Transmitter to measure
Three nos drum pressure
One nos deareator pressure
Draught transmitters to measure
Air box pressure
Bed pressure
Furnace pressure 3 nos.
Super Heater 1 inlet and outlet
Super Heater 2 inlet and outlet
Air pressure at primary air header
Flue gas pressure after ESP
Flue gas pressure before economizer
Draught gauges to measure
Air box pressure
Furnace pressure
Flue gas pressure before economizer
Flue gas pressure before and after multi-tubular and air preheated
Air pressure before and after multi-tubular air preheated
Air pressure at primary air header
Temp Gauges to Measure
Main Steam Line at ESV
Extraction Steam to HP heater and LP heater
Extraction Steam to Deaerator
Steam Line to hogging ejector
1st stage and 2nd stage of Steam Jet Air Ejector (SJAE)
Condensate water from Ejector inlet
Condensate water from Ejector well outlet
Gland steam inlet
Gland steam outlet
De-superheating water line
Control Oil Line
Lube oil line
Main Steam Line at ESV
Extraction Steam to HP heater
Extraction Steam to Deaerator
Turbine exhaust
H.P.Heater steam Inlet& outlet
After Gland Steam Desuperheater
At lube oil header and Barring gear interlock.
At control oil header
Dampers for Various FANS
ID fan Suction inching type motorized damper, and non inching type motorized discharge damper
SA fan non inching type motorized discharge damper
PA fan non inching type motorized discharge damper
APH inlet and Bypass with RPC (2 nos.) control damper
Three element drum level control consists of
Three no. drum level transmitter
Three no. steam flow transmitter
Three no. feed flow transmitter
One no smart positioner
Furnace draught control consists of
Two no. furnace pressure transmitters
One no smart positioner
Auto combustion control consists of
Three no. steam pressure transmitter
One no. air flow transmitter
Superheater steam temperature control consists of
One no. thermocouple
One no. temperature transmitter
One no control valve with smart positioner
Deaerator level control
Two nos. level transmitters
One no control valve with smart positioner
Deaerator pressure control
One no. pressure transmitter
One no control valve with smart positioner
Following Controls for PRDS
a.One no control valve with smart positioner
b.Pressure control valve
c.Spray control valve
d.Pressure transmitter
e.Temperature transmitter
CONTROL SYSTEM
All trip logic for Boiler and Turbine triping shall be 2 out of 3 logic, necessary field instruments are to be considered.
DCS (Common DCS of entire plant) for EACH CPP
Redundancy in DCS power supply, processor / controller and communication level redundancy in DCS, critical closed loops
Printer in DCS ( 3 Nos) at each location 1)2 Nos. A4 laser jet printers for DCS Black and white (1 nos. at control room, 1 nos at CHP control room) 2) 1 nos A4 printer & A3 size colour laser jet printers
Total Five operating station in DCS industrial grade ( 1 at FHS Control room) + 1 OPC server (if applicable) at each location
One Engineering station cum operating station at each location
All OS/ES/OPC computer shall be workstation grade with min. 1 TB Hard disk, 8GB RAM with Latest operating system.
OS shall have Latest windows operating system minimum and supplier shall ensure that minimum 15 years of support shall be available from the supplier of OS as well as its hardware.
Antivirus of minimum 3 years subscription
2 x 100 % UPS with 2 No battery bank, with 60 minute back up time. One UPS bypass system & servo control voltagestabilizer (SCVS) separate for each boilers
Instrument cables from field instruments to DCS system and DCS system to field instruments, From MCC to DCS and DCS to MCC & control panel, shall be supplied by vendor
Communication cable from DCS to various equipment at remote location shall be supplied by vendor
Interconnecting cables between local control system and main DCS system for control & monitoring purpose.
Provision for Management information system in proposed plant DCS
256 point Sequence of Event Recorder.
ELECTRICALS SYSTEM(AS PER SLD)
Main HT SWGR as per SLD
CPP HT SWGR as per SLD
All interconnecting HT cable between main HT SWGR to CPP SWGR
All interconnecting HT cable between main CPP SWGR to drives/ panels
Metering cubical in CPP SWGR as per SLD
Operation of HT SWGR / LT SWGR/ LT MCC shall be through DCS and control panel
Power and control cable, cable tray between SWGR's and DCS
All Motor should be minimum IE-3 type with Class F insulation
Motor for SA fan with VFD Incase of LT Motor andHT VFD In case of HT motor.
Motor for ID fan with VFD Incase of LT Motor andHT VFD In case of HT motor.
Motor for PA fan with VFD Incase of LT Motor andHT VFD In case of HT motor.
VFD for BFP motor
VFD for fuel feeders mounted in a proper panel in individual cubicles
VFD for lime stone feeders mounted in a proper panel in individual cubicles
Active harmonic filters shall be considered for all VFD having motors rating more than 100 KW. Below 100 KW consider passive harmonic filter.
MCC for CPP equipments ( refer Enquiry Document)
415 V LT PCC (65 kA) with two incomers and one bus coupler along with various out going feeders for different MCC as required & following items:
1. Control transformer
2. Potential transformer (line and Bus)
4. Push buttons
5. Indicating lamps
6. Ammeters
7. Voltmeters
9. Local synchronizing panel
10. Various protections as per SLD
All ACB should be EDO type
Various MCCs (65 kA) shall have following items, but not limited to:
1. Control transformer
2. Potential transformer
4. Push buttons
5. Indicating lamps
6. Ammeters
7. Voltmeters
9. Interconnecting LT power & control cables including cable trays from LT PCC to LT MCC and LT MCC to drives
10. Various protections as per SLD
MCC incomer should be ACB/ MCCB(refer Enquiry Document)
11 kV HT AL cable (UE) connecting between Generator (P &N) up to HT switchgear (as per SLD)
11 kV HT switchgear with two nos incomer from each auxiliary transformers, bus coupler and various outgoing feeders (as per SLD)
11 kV HT cable (UE) connecting between step-down Auxiliary distribution transformer & HT switchgear
6 nos 2 x 100 % Step down auxiliary transformer (ONAN) for power plant auxiliary’s power supply (with REF protection). Please refer tender specifications
LT AL XLPE cable connecting between step-down Auxiliary distribution transformer & LT PCC incomer feeder
ELECTRICAL MISCELLANEOUS
Local push button stations (IP-65)for the motors
Entire plant Earthing of electrical equipments above ground level
Entire plant Underground earthing met with required earth-pits(chemical type).
copper earth pit at generator neutral, transformer neutral, DCS panel with copper busbar to be consider (2Nos earth pit for each equipment)
Entire Interconnecting LT power and control cables of entire plant
Cable trays for vendor supplied cables within power plant (including 10% spare space)
All power and control cables lugs should be copper.
2 X 100 % Lighting transformer at each location (capacity to be decided by Supplier considering lighting for entire plant)
Complete lighting distribution with MLDB, APDB, SLDB, ACDB,PDB along with emergency lighting (including separate lighting transformer) and DC lighting
Base frame for control room all panels shall be considered
CEIG formalities from engineering to obtaining drawing and instalation approval (fees shall be paid by EPC supplier for site CEIG formalities).
Electrical hoist for boiler from ground level to drum level.
Street lighting within CPP area shall be considered in EPC supplier scope.
HT Aluminium cables applicable only for motors & transformer incomer. Balance will be as per SLD.
1No. 3phase 4 wire PDB for each area to be provided.(TG building each floor, boiler,ESP, coal yard,WTP,)
SCOPE OF SERVICE/ERECTION/COMMISIONING
IBR formalities from engineering to obtaining site provisional certificate (fees shall be paid by EPC supplier for site IBR formalities).
Erection / Testing & Commissioning of mechanical, electrical, C & I equipments entire civil work as included under scope of supply
Grouting of base plates, bolts, anchor boxes with non shink grout.
Supervision of grouting for foundation
Final adjustment of equipment foundations.
Conducting boiler hydro test, alkali boil out, steam blowing, safety valve floating
Training of PURCHASER’s operating personnel. (Schedule to be mutually discussed).
Operation and maintenance manuals
Drawing / Documents required for statutory clearance
Initial Fill of Lubricants and chemicals
Flushing oil and first fill of oil along with top up quantity up to Commissioning for Turbine
Packing & Forwarding
Transportation up to site
Transit Insurance
Unloading & shifting of all equipment at site
Site storage insurance
P.G Test. And required instrument for PG test
Instrument Air piping
Foundation bolts, lighting protection, above ground earthing , Under ground Earthing & Earth Mat
Two years operating & maintenance spares
Commissioning spares
Special maintenance tools and tackles
Chemicals for Alkali boil out
Hydro test pump for boiler (on loan basis)
Fasteners, gaskets, mating flanges as required
N2 cylinders, header, regulators and piping up to one point near boiler front column.
Providing Erection tools, tackles, hoists, derricks, slings, scaffolding, rigging tools, welding sets, instruments, appliances, consumables required .
Stress relieving of welded joints
Pre-commissioning check, mass flushing alkali boil out, steam blowing, trial run of all equipment calibration of instrument & control etc.
OTHERS MISCELLANEOUS
Public Address System 10 locations
25 Nos of intercom points with instruments, wiring and EPBX
Installation of CCTV Camera with 2 Nos. display units (Each Plant) at various locations.
Air Conditioning System
Centralized AC plant with AHU for Main Control room in TG building and shift incharge/conference room, C&I panel room, VFD room etc as per the equipment need based.
Split AC for ESP control room, CHP, WTP or any other rooms need based.
Ventilation System
Pressurized Wet Ventilation system for HT SWGR room
Roof extractor fan for T.G hall
Wet Ventilation system for Turbine Area
Ventilation System for AHS, FHS and ESP MCC area, cable cellar room.
FIRE FIGHTING SYSTEM
Design and Engineering of complete Fire fighting system
Pressurized water for the system shall be provided at battery limit by GIDC
Complete fire fighting system for entire plant with required number of hydrant points with hose for all fire prone zones, all panel and control room, Turbine, CHP system complete including coal storage shed requirement, boiler all floors, cable cellar, MCC room, transformer area, lub oil tank lub/control oil circuit etc.
Fire Buckets at required points filled with sand
Portable Fire Extinguishers (Please refer Annexure for location of fire fighting equipments)
MVWS/HVWS Systems
Fire Alarm system, annuncoator, etc. Smoke Detectors
CIVIL
Complete civil works including chimney including Design and construction of buildings, foundations for all the equipment, trenches and other civil works, land levelling & grading and below ground, motorable roads, drains,
Control rooms
Effluent disposal pit, if any, drainage & sanitary works.
Above ground civil including turbine house, boiler civil work, and control room,MCC Room, CHP area gizzly hopper, crusher screen house, equipment foundation etc all other control room, WTP including N-pit, Cooling water sumps, ash silos etc. shall be considered in EPC supplier scope
Toe guard plates at periphery of boiler where ever required (6mm thick, 150 height)
False flooring of 1 mtr. Depth shall be considered.
STEAM DISTRIBUTION NETWORK
Laying steam line on pipe rack as a part of steam network from boiler/turbine outlet through Headers, PRDS etc. upto each individual consumer industry with all proper engineering for minimum pressure loss and avoiding condensation, with steam trap,expansion loops and all proper pipe supports for expansion with proper interconnection at multiple location for isolation without interruption of steam supply to consumer industry Steam meter with flow measurment devise and hooking up with DCS for accounting and Billing purpose is the EPC supplier scope.
RETURN CONDENSATE NETWORK
From each consumer industry pressurised Good condensate after three way valve will be connected to the main central collecting header with flow metre/totaliser for each consumer industry and will feed to return condensate tank at each location. The condensate shall be pumped to the polishing unit through the PHE to heat up the deaerator feedwater.
PAINTING
Painting material for items under scope. Surface cleaning : SA21/2 For insulated surfaces, 2 coats of Zinc rich epoxy primer (50 microns per coat) For Uninsulated surfaces 2 coats of Zinc rich epoxy primer (50 microns per coat) and 2 coats of Zinc rich epoxy final painting (50 microns per coat)
Necessary insulation & Cladding as Required
GENERAL - PLANT BOP
Isolation valves for the cooling water inlet and outlet lines of TG auxiliaries such as oil coolers, Generator coolers with Instruments
Necessary Expansion bellows at all required points
Matting flanges all flanged end connections and loose supplied valves and fittings
Hoist, Elevator, Monorail with chain pullet blocks. for Maintenance of Equipments.
EPC Supplier shall consider 500 kg Personnel/Freight Elevator for approach to TG Building.
EPC Supplier shall consider 1000 kg Personnel/Freight Elevator for approach to Boiler Top.
Miscellaneous structure materials such as Insert plates, Ladders, staircases, platforms within the battery limit.
Applicable Drain piping up to flash tank.
Vent and exhaust piping up to building roof.
Construction Power , Water and drinking water shall be arranged by EPC supplier
Under ground earthing - earth pit (chemical type) & earth grid.
DESCRIPTION
T.G. BUILDING
RCC framed construction with RCC intermediate floors, brick wall, precoated galvalume sheet roof with MS truss for TG bay. Structure steel column above EOT Bracket level with brick wall / window / door shall be provided. Adequate nos. of Eco Ventilator and Roof light sheet shall be provided. Access to roof shall be provided.
Cable Cellar Room
MCC room
Control room
TG floor
Deaerator floor
Miscellaneous Rooms for Mechanical and Electrical equipment's
Maintenance Bay
Miscellaneous Items
Insert plate, curb angle, pipe sleeves, foundation bolts to be provided.
Alluminium partition for control room / offices.
Toilet block / Office shall be in EPC Contractor's scope.
Lift for TG Building
Flooring - Turbine floor / Stair case - Polished kota stone.
Motorable road and Road side Flood drain
Balance area - IPS flooring.
FOUNDATION FOR MAIN & AUX. COOLING TOWER
Cooling Tower Basin
Material of cooling water fore bay
BOILER
Civil / RCC structure for Boiler shall be upto Boiler operating floor 5 to 5.5 mtr elevation as per IBR Requirement
MS structure for Boiler shall be from boiler operating floor
Supporting sturcutre for roof / side cladding / louvers.
Precoated Galvalume sheet for Roofing / Side Cladding / Louvers from Firing floor onwards.
Rain water gutters and drain piping from roof to ground level.
Boiler operating floor / other platform - Grating / Chequered plate.
Civil / RCC structure for ESP shall be upto +300mm.
MS structure for ESP shall be from +300mm level onwards.
Platform - Grating / Chequered plate.
ESP & CHP MCC ROOM
RCC framed structure with brick wall and RCC roof slab.
CRUSHER HOUSE
RCC framed construction with RCC intermediate / roof floors, brick wall with necessary doors / windows / opening / staircase.
Structure steel column above Primary screen floor onwards with MS truss and precoated Galvalume sheet - roofing / side cladding to be provided.
COAL HANDLING PLANT
Necessary civil / structural work required for coal handling plant to be provided.
Conveyor foundation, crusher/screen building, gizzly hopper and tunnel, coal shed, MCC room
RCC CHIMNEY
RCC Chimney each of xx mtr and xx mtrs height (Height as per GPCB Norms),
ROAD AND STORM WATER DRAIN
Plant internal road & approches - (RCC) to be provided.
Precast Storm water drain of adequate design to be provided.
PAVEMENTS
Pavement of the North, South and WTP area where the 210 TPH project is coming is the scope of EPC Bidder.
RCC Paving works with nominal reiforcement for Boiler, Bunker, ESP, Fan foundations, around TG Building / Cooling tower and in the area of new Power plant.
Boundry
Green Belt & Plantation
BURRIED PIPE LINE
Civil works for burried pipe line including rapping / coating etc.
Proper supports for all the above ground line.
Complete civil work for softner, DM plant and storage area, N-Pit etc.
Foundation for ID, FD & PA fan, Blow down tank, duct suuport etc.
Conveyor support pedestal.
Transfer tower support including steel structure.
Plumbing and sanitary works for the proposed power plant area.
Site grading works upto + / - 300mm level.
Drain sump pit.
Washroom at TG floor and 0.0 mtr floor.
GENERAL
The scope of EPC contractor covers the desing, construction of civil, structural and architectural work including supply of all materials, labours and tools as required for successful execution of the new power plant. This includes the piling as well civil / structural work required for the proposed power plant.
OPC/ SRC cement will be used for Substructures & Superstructures.
TMT Fusion bonded Epoxy coated Fe 500 D reinforcement steel bars confirming to IS : 1786 will be used.
Disposal of surplus earth upto a distance of 1.0 km with in estate as directed by EIC
Backfilling of required quantity in proposed power plant area shall be in the scope of EPC contractor.
The power and water required for the construction, erection and commissioning of the power plant shall be in EPC supplier scope
Building Painting
Construction of Site office / store will be EPC contractor's scope.
Temporary covered shade for storing free issue cement - EPC Contractor's scope.
Any modification required for the new power plant is in the scope of EPC contractor. Such modification made may be brought to its required state fo which it is intended to use for.
Any other works required to be executed for the new power plant which is not mentioned in the scope shall be in the EPC contractor. No extra claim will be entertained for such work.
Architectural, Structural, furniture, plumbing and electrical layout for all building works needs to approved from competent authority of GIDC and the make of each item shall be as per approved make list enclosed with this document.
3D modelling of the entire steam plant site will be in the EPC contractor’s scope.
Proof checking from the 3rd Party as approved from the competent authority for all civil and structural design and drawings shall be in EPC contractor’s scope.
Bidder to do site survey, soil investigation, contour survey, etc. required for bidding process by their own. Moreover, Finish Ground Level of the plant plot area shall be considered minimum 300 mm above finish road level of the Estate area.
Refer approved make list for the all building and eletro mechanical items
UNITS
Kcal/kWh
Kcal/kWh
Months
DESCRIPTION
Type of Boiler
Type of circulation
Type of support
No. of Boilers
Boiler design code
Boiler Predicted Performance
No of Boilers
Boiler Capacity (MCR)
Peak Capacity of Boiler
Steam temperature at Superheater outlet
Superheated steam control range
Steam pressure at superheater outlet
Minimum continuous rating of the Boiler with automatic controls
Feed water temperature at Economiser inlet
Excess air
Oxygen content in flue gas at Boiler outlet
Boiler efficiency based on G.C.V with 100% Imported coal
Fuel consumption
Lime stone consumption with 100% Imported coal and 70% Imported + 30% Biomass
Sox in the flue gas : Without lime dosing
Sox in the flue gas for 100 % Imported : With lime dosing
Sox in the flue gas with 70 % Imported+30% Biomass : With lime dosing
Boiler design for firing other fuels 100% Imported coal and 70% Imported + 30% Biomass on heat basis
Breakup Losses Breakup Losses Breakup Losses
a. Unburnt carbon loss
b. Sensible heat loss through ashes
c. Dry flue gas loss
d. Loss due to moisture and Hydrogen in fuel
e. Loss due to moisture in Air
f. Radiation Loss
g. Other loss - Manufacturer’s Margin
h.Unaccounted loss
i. Total losses
Flue Gas Temperature Flue Gas Temperature
a. Furnace temperature
b. Economiser inlet
c. Airpreheater inlet
d. Airpreheater outlet
e. APH outlet temperature with Petcoke firing
f. ESP outlet
g. Chimney outlet
Water Temperature
a. Economiser inlet
b. Economiser outlet
Ciculation ration of water
Air Temperature leaving Airheater
Air Pressure at
a. FD Fan outlet
b. Airheater inlet
c. Airheater outlet
d. Airbox
e. PA Fan inlet
f. PA Fan header
Flue Gas Pressure at
a. Furnace outlet
b. Superheater inlet
c. Superheater outlet
d. Economiser outlet
e. Airheater inlet
f. Airheater outlet
g. ESP inlet
h. ESP outlet
i. ID fan inlet
j. ID fan outlet
Flue Gas Velocities
a. Fluidised bed
b. Furnace
c. Primary Superheater
d. Secondary Superheater
e. Economiser
f. Air Preheater
Water Velocities
a. Economiser
b. Feed water line
Steam velocities
a. Primary superheater
b. Secondary Superheater
c. Main steam line
Steam Pressure Profile
a. At main steam stop valve
b. Superheater safety valve set pressure
c. Pressure drop across Primary Superheater
d. Drum Safety valve I set pressure
e. Drum Safety valve II set pressure
Auxiliary Power Consumption at MCR condition at MCC
Provided Heat Transfer Areas
a. Bed coil (Area is considered without ss studs. Bed coils are with SS studs)
b. Furnace
c. Primary Superheater
d. Secondary Superheater
e. Economiser
Boiler bank
pressure part area
f. Air pre heater
g. Total area
Boiler Construction Details
Drums
a. Internal diameter
b. Drum shell material
e. Drum dished end thickness
c. Drum dished end material
d. Type of drum support
e. Drum operating pressure at MCR
f. Drum Design pressure
g. No. of Direct level gauges on drum
h. Type of Steam Drier / Separator provided
Bed Tube Assembly
a. Type of tube arrangement
b. Tube size (OD x T)
c. Bed Tube material
d. Header size (OD x T)
e. Pitch
f. Stud material
Water wall Assembly
a. Type of construction
b. Tube size (OD x T)
c. Tube material
d. Header Size (OD x T)
e. Header material
f. Fin material and thickness
g. Water wall size (L x W)
h. Water Wall height from Bottom Header to Top Header
Convection Superheater
Primary Superheater
a. Type of flow
b. Arrangement
d. Tube size (OD x T)
e. Tube material
f. Inlet Header material
g. Tube pitch arrangement
Secondary Superheater
a. Type of flow
b. Arrangement
d. Tube size (OD x T)
e. Tube material
f. Header Size ( OD X T )
g. Inlet Header material
h. Tube pitch arrangement
Desuperheater
a. Type
b. Number
c. Material of pipe
Economiser
a. Tube size (OD x T)
b. Tube material
c. Header size (OD x T)
d. Header material
e. Casing material
Soot Blowers (Motorised)
a. Economiser zone Rotory type
b. SH Zone, Long rectractable
PRDS I , (for HP steam)
a. Inlet pressure
b. Inlet temperature
c. Outlet pressure
d. Outlet temperature( Tentative)
e. Outlet steam quantity (Tentative)
PRDS II , (for LP steam)
a. Inlet pressure
b. Inlet temperature
c. Outlet pressure
d. Outlet temperature( Tentative)
e. Outlet steam quantity (Tentative)
PRDS III . (Process steam bypass)
a. Inlet pressure
b. Inlet temperature
c. Outlet pressure
d. Outlet temperature( Tentative)
DSH for Process steam
e. Outlet steam quantity (Tentative)
Airheater
a. Arrangement and type
b. Tube size (OD x T)
c. Tube material
d. Flow medium
• Inside tubes
• Outside tubes
e. No. of blocks of Airheater
f. APH Dampers (Manual)
Fluidised Bed
a. Fluidised bed size
b. Bed area / Compartment
c. No. of Compartments
d. Bed plate material
e. Bed plate size (L x W)
f. Fuel Nozzle material
g. Fuel Nozzle cap material
h. No. of fuel Nozzles / Compartment
i. Material of Air Nozzle
j. Recommended fuel particle size at the inlet of furnace (mm)
k. No. of ash drain pipes /Compartment
l. Ash drain pipe material
Fuel Feeding System
a. Type of feeders
b. Location
c. Number of feeders
d. Feeder Drive Rating
Overbed feeder Loading
e. Type of feed control system
f. Method of feed rate adjustment
g. Method of feed rate adjustment
h. Feeder motor capacity
Ducting Specification
a. Material of construction
b. Thickness (mm)
c. Blowdown Tank (common for CBD& IBD)
d. Material
Sample cooler
a. Type
b. Sampling Points
c. MOC of Shell
d. MOC of Coil
Online SWAS for Ph and conductivity only
Feed Water Pumps (1W + 1S) 20% Margin of flow & 5% on head over second safety valve set pressure
a. Pump Type
b. Fluid Temperature
c. Rated Flow
d. Differential head at rated Condition
e. Speed
f. Recirculation type
g. Intermediate low stage bleed for desuperheter.
DEAERATOR CUM STORAGE TANK
Deaerator
a. Type
b. Design standard
c. Storage capacity - from NL to LL
Design Conditions
a. Deaeration capacity
b. Design temperature
c. LP Steam pressure at pressure control valve inlet
d. LP steam temperature @ ( º C) :pressure control valve inlet
e. Temperature of incoming water
f. Deaerated Water temp.
g. Dissolved Oxygen in Deaerated water
h. Quantity of Steam required
i. Corrosion Allowance considered
j. Storage for normal capacity between NWL & LWL (Min 20 minutes storage)
k. support type
l. MOC of Shell,Dishedend & storage tank
m. MOC of Pipe nozzles
n. MOC of spray nozzle /trays
o. Internals
p. Piping between transfer pump and feedpump
FANS - 10% extra capacity for flow and Head.
a. Quantity/Boiler
b. Flow at MCR ( margin of 20% extra on MCR)
c. Flow at Test Block (TB)
d. Head at MCR
e. Head at Test Block (TB)
f. SPEED
g. DRIVE ( with star delta changeover system)
CHEMICAL DOSING SYSTEM
a. Type of system
b. Tank Capacity
c. Tank/Piping Material
e. Type of stirrer
f. Type of pump
g. No. of pumps
h. Capacity of the pump
i. Head developed by pump
j. Motor rating
k. Chemical to be dosed
FUEL STORAGE BUNKER
a. No. of Bunker
b. Type
c.Material to be stored
d.Material of construction
e.Storage volume of the bunker
f. Discharge gate type
g. SS Lining in Bunker Conical portion Considered
g. SS Lining in surge Considered
h. Thickness of Lining
i. Top cover (Chequered plate)
j. Supports
k. Valley angle (Degrees)
BED MATERIAL HANDLING SYSTEM
a. Bed material bunker
b. Bed material handling system
LIMESTONE HANDLING SYSTEM
a. Limestone material bunker
b. Limestone handling system
ELECTRO STATIC PRECIPITATOR
a. Type
b. Number of precipitator/Boiler
c. Number of gas path
d. Number of Electrical fields in series, in the direction of gas flow
e. Space between the centres of collecting Electrodes across the gas path
f. Nominal width x height of collecting electrodes per field, in the direction of gas flow
g. Nominal lengths of collecting electrodes per field, in the direction of gas flow
h. Total effective collecting area provided
i. Total number of HV TR units
j. Rating of each HV TR units
a). Collecting electrode plate
b). Emitting electrode
l. Flue gas flow
m. Gas inlet temperature
n. Inlet dust concentration (dry basis)
o. Collecting efficiency with all the fields in service
p. Collection efficiency with one field out of service
q. Outlet dust concentration 100 % Imported and 70%Imported+30% Lignite mix.
q. Outlet dust concentration with lime dosing 100 % Imported and 70%Imported+30% Lignite mix.
r. Guaranteed outlet dust concentration with First field out of service
s. Total power consumption of the ESP system for all fields
t. Specific collecting area
v. Casing thickness
w. Insulation material and density
x. Cladding material and thickness
y. Remote indication for KV and mA provided through transducer for each TR of Rectifier unit
z.ESP MCC/Rapper control panel/ TR set control panel bided
All safety interlocks for HV bus system and earthing switch considered/supplied
Predicted Boiler performace at various load for different fuel mix.
DESCRIPTION
Type of Boiler
Type of circulation
Type of support
No. of Boilers
Boiler design code
Boiler Predicted Performance
No of Boilers
Boiler Capacity (MCR)
Peak Capacity of Boiler
Steam temperature at Superheater outlet
Superheated steam control range
Steam pressure at superheater outlet
Minimum continuous rating of the Boiler with automatic controls
Feed water temperature at Economiser inlet
Excess air
Oxygen content in flue gas at Boiler outlet
Boiler efficiency based on G.C.V with 100% Imported coal
Fuel consumption
Lime stone consumption with 100% Imported coal and 70% Imported + 30% Biomass
Sox in the flue gas : Without lime dosing
Sox in the flue gas for 100 % Imported : With lime dosing
Sox in the flue gas with 70 % Imported+30% Biomass : With lime dosing
Boiler design for firing other fuels 100% Imported coal and 70% Imported + 30% Biomass on heat basis
Breakup Losses Breakup Losses Breakup Losses
a. Unburnt carbon loss
b. Sensible heat loss through ashes
c. Dry flue gas loss
d. Loss due to moisture and Hydrogen in fuel
e. Loss due to moisture in Air
f. Radiation Loss
g. Other loss - Manufacturer’s Margin
h.Unaccounted loss
i. Total losses
Flue Gas Temperature Flue Gas Temperature
a. Furnace temperature
b. Economiser inlet
c. Airpreheater inlet
d. Airpreheater outlet
e. APH outlet temperature with Petcoke firing
f. ESP outlet
g. Chimney outlet
Water Temperature
a. Economiser inlet
b. Economiser outlet
Ciculation ration of water
Air Temperature leaving Airheater
Air Pressure at
a. FD Fan outlet
b. Airheater inlet
c. Airheater outlet
d. Airbox
e. PA Fan inlet
f. PA Fan header
Flue Gas Pressure at
a. Furnace outlet
b. Superheater inlet
c. Superheater outlet
d. Economiser outlet
e. Airheater inlet
f. Airheater outlet
g. ESP inlet
h. ESP outlet
i. ID fan inlet
j. ID fan outlet
Flue Gas Velocities
a. Fluidised bed
b. Furnace
c. Primary Superheater
d. Secondary Superheater
e. Economiser
f. Air Preheater
Water Velocities
a. Economiser
b. Feed water line
Steam velocities
a. Primary superheater
b. Secondary Superheater
c. Main steam line
Steam Pressure Profile
a. At main steam stop valve
b. Superheater safety valve set pressure
c. Pressure drop across Primary Superheater
d. Drum Safety valve I set pressure
e. Drum Safety valve II set pressure
Auxiliary Power Consumption at MCR condition at MCC
Provided Heat Transfer Areas
a. Bed coil (Area is considered without ss studs. Bed coils are with SS studs)
b. Furnace
c. Primary Superheater
d. Secondary Superheater
e. Economiser
Boiler bank
pressure part area
f. Air pre heater
g. Total area
Boiler Construction Details
Drums
a. Internal diameter
b. Drum shell material
e. Drum dished end thickness
c. Drum dished end material
d. Type of drum support
e. Drum operating pressure at MCR
f. Drum Design pressure
g. No. of Direct level gauges on drum
h. Type of Steam Drier / Separator provided
Bed Tube Assembly
a. Type of tube arrangement
b. Tube size (OD x T)
c. Bed Tube material
d. Header size (OD x T)
e. Pitch
f. Stud material
Water wall Assembly
a. Type of construction
b. Tube size (OD x T)
c. Tube material
d. Header Size (OD x T)
e. Header material
f. Fin material and thickness
g. Water wall size (L x W)
h. Water Wall height from Bottom Header to Top Header
Convection Superheater
Primary Superheater
a. Type of flow
b. Arrangement
d. Tube size (OD x T)
e. Tube material
f. Inlet Header material
g. Tube pitch arrangement
Secondary Superheater
a. Type of flow
b. Arrangement
d. Tube size (OD x T)
e. Tube material
f. Header Size ( OD X T )
g. Inlet Header material
h. Tube pitch arrangement
Desuperheater
a. Type
b. Number
c. Material of pipe
Economiser
a. Tube size (OD x T)
b. Tube material
c. Header size (OD x T)
d. Header material
e. Casing material
Soot Blowers (Motorised)
a. Economiser zone Rotory type
b. SH Zone, Long rectractable
PRDS I , (for HP steam)
a. Inlet pressure
b. Inlet temperature
c. Outlet pressure
d. Outlet temperature( Tentative)
e. Outlet steam quantity (Tentative)
PRDS II , (for LP steam)
a. Inlet pressure
b. Inlet temperature
c. Outlet pressure
d. Outlet temperature( Tentative)
e. Outlet steam quantity (Tentative)
PRDS III . (Process steam bypass)
a. Inlet pressure
b. Inlet temperature
c. Outlet pressure
d. Outlet temperature( Tentative)
DSH for Process steam
e. Outlet steam quantity (Tentative)
Airheater
a. Arrangement and type
b. Tube size (OD x T)
c. Tube material
d. Flow medium
• Inside tubes
• Outside tubes
e. No. of blocks of Airheater
f. APH Dampers (Manual)
Fluidised Bed
a. Fluidised bed size
b. Bed area / Compartment
c. No. of Compartments
d. Bed plate material
e. Bed plate size (L x W)
f. Fuel Nozzle material
g. Fuel Nozzle cap material
h. No. of fuel Nozzles / Compartment
i. Material of Air Nozzle
j. Recommended fuel particle size at the inlet of furnace (mm)
k. No. of ash drain pipes /Compartment
l. Ash drain pipe material
Fuel Feeding System
a. Type of feeders
b. Location
c. Number of feeders
d. Feeder Drive Rating
Overbed feeder Loading
e. Type of feed control system
f. Method of feed rate adjustment
g. Method of feed rate adjustment
h. Feeder motor capacity
Ducting Specification
a. Material of construction
b. Thickness (mm)
c. Blowdown Tank (common for CBD& IBD)
d. Material
Sample cooler
a. Type
b. Sampling Points
c. MOC of Shell
d. MOC of Coil
Online SWAS for Ph and conductivity only
Feed Water Pumps (1W + 1S) 20% Margin of flow & 5% on head over second safety valve set pressure
a. Pump Type
b. Fluid Temperature
c. Rated Flow
d. Differential head at rated Condition
e. Speed
f. Recirculation type
g. Intermediate low stage bleed for desuperheter.
DEAERATOR CUM STORAGE TANK
Deaerator
a. Type
b. Design standard
c. Storage capacity - from NL to LL
Design Conditions
a. Deaeration capacity
b. Design temperature
c. LP Steam pressure at pressure control valve inlet
d. LP steam temperature @ ( º C) :pressure control valve inlet
e. Temperature of incoming water
f. Deaerated Water temp.
g. Dissolved Oxygen in Deaerated water
h. Quantity of Steam required
i. Corrosion Allowance considered
j. Storage for normal capacity between NWL & LWL (Min 20 minutes storage)
k. support type
l. MOC of Shell,Dishedend & storage tank
m. MOC of Pipe nozzles
n. MOC of spray nozzle /trays
o. Internals
p. Piping between transfer pump and feedpump
FANS - 10% extra capacity for flow and Head.
a. Quantity/Boiler
b. Flow at MCR ( margin of 20% extra on MCR)
c. Flow at Test Block (TB)
d. Head at MCR
e. Head at Test Block (TB)
f. SPEED
g. DRIVE ( with star delta changeover system)
CHEMICAL DOSING SYSTEM
a. Type of system
b. Tank Capacity
c. Tank/Piping Material
e. Type of stirrer
f. Type of pump
g. No. of pumps
h. Capacity of the pump
i. Head developed by pump
j. Motor rating
k. Chemical to be dosed
FUEL STORAGE BUNKER
a. No. of Bunker
b. Type
c.Material to be stored
d.Material of construction
e.Storage volume of the bunker
f. Discharge gate type
g. SS Lining in Bunker Conical portion Considered
g. SS Lining in surge Considered
h. Thickness of Lining
i. Top cover (Chequered plate)
j. Supports
k. Valley angle (Degrees)
BED MATERIAL HANDLING SYSTEM
a. Bed material bunker
b. Bed material handling system
LIMESTONE HANDLING SYSTEM
a. Limestone material bunker
b. Limestone handling system
ELECTRO STATIC PRECIPITATOR
a. Type
b. Number of precipitator/Boiler
c. Number of gas path
d. Number of Electrical fields in series, in the direction of gas flow
e. Space between the centres of collecting Electrodes across the gas path
f. Nominal width x height of collecting electrodes per field, in the direction of gas flow
g. Nominal lengths of collecting electrodes per field, in the direction of gas flow
h. Total effective collecting area provided
i. Total number of HV TR units
j. Rating of each HV TR units
a). Collecting electrode plate
b). Emitting electrode
l. Flue gas flow
m. Gas inlet temperature
n. Inlet dust concentration (dry basis)
o. Collecting efficiency with all the fields in service
p. Collection efficiency with one field out of service
q. Outlet dust concentration 100 % Imported and 70%Imported+30% Lignite mix.
q. Outlet dust concentration with lime dosing 100 % Imported and 70%Imported+30% Lignite mix.
r. Guaranteed outlet dust concentration with First field out of service
s. Total power consumption of the ESP system for all fields
t. Specific collecting area
v. Casing thickness
w. Insulation material and density
x. Cladding material and thickness
y. Remote indication for KV and mA provided through transducer for each TR of Rectifier unit
z.ESP MCC/Rapper control panel/ TR set control panel bided
All safety interlocks for HV bus system and earthing switch considered/supplied
Predicted Boiler performace at various load for different fuel mix.
UNITS
7 MW Normal condiion.
Constant pressure
Kg/cm2 (g)
As per ASME-TDP-1 (Latest)
Kg/cm2 (g)
GS17CrMo55
GS17CrMo511
X22CrMoV12.1
30CrMoNiV511
Chest GS17CrMo511 X22CrMoV12.1
Wrought/ Forged CS Shell and tin based Babbitt Lining
To be indicated by Supplier
m x m x m
Stainless steel after the filters up to the bearings.
MOP AOP EOP
ltr / min
kg/sq cm
Duplex type filters with online switchover & stainless steel element. The filter element size shall be 10 microns (nominal) or a size to meet the requirement of the turbine
Kcal / hr
centrifuge
Continuous shall be connected Permanently with main oil tank.
As per Turbine EPC Supplier
Separate or common for lube oil and control oil (as per the equipment EPC Supplier’s practice)
Stainless steel
2 x 100% duplex filter (replaceable cartridges shall be used for each filter) , the filter rating shall be 5 microns (nominal) or a size to meet the requirement of the turbine.
Meter
Cu.m3/hr
Automatic
Shell and Tube (SS-304) type
Labyrinth
Double acting eletro- hydraulic/pneumatic piston type
ASME SEC VIII Div. 1
ASTM A285 Gr.C
ASTM A285 Gr.C
ASTM A106 Gr.B
ASTM A285 Gr.C
ASTM A105
ASTM A193 Gr. B7
ASTM A193 Gr. 2H
Spiral wound SS 316 with graphite
Kg/Cm2 (g)
Kg/Cm2 (g)
Continuous and suitble for parallel operation
Yes/No
m x m x m
Brush less
Unitrol 1020
0.2(metering)
0.2S(metering)
Vacuum contractor
Mounting - plug in type
3 phase supply
FC + FCBC
Yes / No
Yes / No
Yes / No
Yes / No
UNITS
Kg/Cm2(g)
Controlled Extraction cum Condensing
Anticlockwise
Woodward Latest Model
m x m x m
Shell & Tube
Steam Jet Air Ejector
Kg/Cm2(a)
Synchronous; Brushless
TDPS Preffered
Yes/No
Yes/No
m x m x m
Brush less
ABB prefered
Digital
0.2(metering)
0.2S(metering)
100A for 30sec
Vacuum contractor
Simplex
Mounting - plug in type
3 phase supply
FC + FCBC
liters
ltr / min
kg/sq cm
Yes/No
Kcal / hr
Centrifugal
Horizontal
Shell & Tube
Welded/ Seemless
Admiralty Brass
Woodward Latest Model
Yes / No
Yes / No
Yes / No
Yes / No
UNITS/ DATA
Air/ Water
200 BHN mini
Net.Cu M/Hr
This includes manual knife gate valve, motorised rotary vane feeder and ash conditioner.
Telescopic chute
cub m/hr
cub m/hr
Meter
UNITS
mm x mm
mm x mm
V / HZ / Ph
BC-1, BC-2, BC-3
kg/Cu.m
Numbers.
Yes/No
Both Side
PRIMARY SCREEN/ SECONDORY SCREEN
Kg/Cum
mm x mm
(Yes / No)
Kg/Cum
Units
PULTRUDED FRP Induced draft Counter flow (RCC construction upto Basin Foundation)
mkcal/hr
Meters ( LXWXH)
Meters ( LXWXH)
Meters ( LXWXH)
Meters
Meters
Meters
415 V/3 Ph/50 hz
kW/rpm
cfm or m3/hr
Gear box
Pultruded FRP structural componenets
Pultruded FRP structure.
Corrugated FRP
Corrugated FRP
multi pass zigzag type Cellular PVC
MSHDG
Polypropelene
Polypropelene supported by MSHDG frame
Cast Alluminium Alloy / hollow cast FRP
HDG steel & SS 304 HARDWARE
HDG steel
Pultruded FRP ( Anti Skid type)
PVC mini V2 Bar
FRP Louvers must be properly designed to give uniform distribution of air with minimum pressure drop
Kg/hr/sq.m
Kg/hr/sq.m
Kw/cell
Boiler Supplier
In Door (TG Building)
415V, 50Hz AC, 3 Phase, Neutral
110V AC / 230V AC
M5 for Indoor operations
MAIN HOIST
To be decided based on turbine supplier recommendation
No. of Falls
steel core
Electro Hydraulic Thruster
Qty. Total / Driving
Shall be as per TG building layout
Shall be as per TG building layout
Cum/hr
Carbon Steel
ASTM A 743 Gr. CF8M
ST ASTM A276-410
ASTM A 276 Type 410
As per NEMA TR-1
As per IS 1180(Part - 2)
Resistance grounded
Solidly grounded
Electrolytic grade copper
Primary winding
Cable (Size: R X C x mm2)
Bus-Duct /Cable (Size: R X C x mm2)
Earth strip/ Cable
Window type (bar primary), Epoxy cast resin
Standby E/F and REF
5P15 and PS
Litres
Litres
Litres
NIFPS
45 (above average ambient temp)
40 (above average ambient temp)
Epoxy paint, shade RAL 7032
Yes/No
As per approved manufacturer’s list.
V/ph/Hz
Non effectively earthed (Thro NGR)
Indoor
Floor Mounted, Metal Clad, Drawout Type, Single Tier
Bottom
As per single line diagram
kV(rms)
kV(peak)
Copper
Color coded Heat shrinkable PVC sleeve. Bus bar joints with shrouds of 26kV insulation
Silver faced.
As per specification
kV, ph, Hz
Motor charged spring. Manual trip and close facility to be provided.
Shall be provided
kA(peak)
V, Phase
Cast resin bar primary
26.3 kA for 3 sec.
kA, 2.5 times of Ik
Ratio 50/ 1.
Cast resin
Star / Open
1.2 continuous,
Class ‘E’ or better
kV(rms)
kV(peak)
As per SLD enclosed
As per SLD enclosed
Numerical
By vendor at factory
IEC 61850/ MODBUS
UNITS/ DATA
3 Phase, 4 Wires
Solidly grounded
Fixed/ Draw-out
Single Front/ Double Front
Bottom
CRCA, Sheet Steel
min. 2 mm
min. 3 mm
3 mm thick sheet steel
4 mm thick aluminium
Air cooled (Natural)
7 tanks process for surface preparation
2 coats of epoxy based primer , powder coating
2 coats of epoxy based finish paint, powder coating
60 Micron
Anodised Aluminium
2 mm (min.)
Aluminium grade 6106 T6 /copper
Electrolytic grade
Yes, Colour coded, Heat shrinkable sleeves.
SMC/ DMC/ FRP/ Epoxy
Epoxy / SMC / DMC
65 kA for 1 sec
Copper
110V AC/ 230V AC +/- 10% through control transformer
110V AC/ 230V AC +/- 10%
110V AC/ 230V AC +/- 10%
Drawout Air Circuit Breaker
65 kA for 1 sec
O - 3 min.- CO - 3 min. - CO
Stored energy spring charged
watts
watts
watts
Yes / No
100 % Icu for all applications including motor starters
As per SLD
As per SLD
As per SLD
High rupturing
85 to 110 % of rated Volatge
# % rated voltage
85 to 110 % of rated Volatge
# % rated voltage
Cast resin wound / bar primary
Cast resin
Microprocessor based
Bimetallic / Electronic
Electromechanical / static
Electromechanical / static
Electromechanical / static
Electromechanical / Numerical
Yes / No
Yes / No
Incomer/Buscoupler -
By vendor at factory
As per SLD enclosed
As per SLD enclosed
Analog/ Digital
Analog/ Digital
Digital
Digital
Taut Band, 240 degree
min. 96 x 96 mm
min. 96 x 96 mm
IEC/ MODBUS
Yes / No
Dry type, Air cooled,vacuum impregnated
based on load, minimum 100 VA
110 V AC/ 230 V AC
+/- 5% in steps of 2.5 %
Clustered LED with min. 8 mm dia
Red/ Green/ Amber
White
Rotary, stayput
Pistol grip, T-N-C Switch, spring return to neutral
spring return
spring return
Stay put type, Mushroom head, turn to release
Thermostat with MCB
Cable chamber / Bus bar chamber
As per space heating requirement
Feeder protection
50Hz, IEC Standard, English language
Flush mounting
Screw type / plug-in type
Graphic display
English
samples per cycle
USB serial interface
MODBUS-TCP/IP
Parallel Redundancy Protocol (PRP)
Multi mode
PCC / MCC
As per SLD
As per SLD
As per SLD
watts.
Indoor
0.6 for Al, 1.0 for CU (A/mm2)
65 kA for 1 sec
105 kA(peak)
Static wt (Kgs)/ Dynamic wt / (Kgs) /Dimensions (MM)
Static wt (Kgs)/ Dynamic wt / (Kgs) /Dimensions (MM)
Width of Panel in mm ( single front /Double front)
UNITS/ DATA
As per Vendor List
Preliminary/Final
Non- Hazardous
Outdoor
Continuous
(Yes/No)
TEFC / TETV / CACA
A(Starting/ No load/ Full load)
% ( Full load)
KW (No load/ Full load)
KW (No load/ Full load)
Yes/ No
Yes/ No
Vacuum CB
Class F
Class B
ohms at 95°C
ohms at 95°C
2 nos. RTDs per phase (Duplex) (RTD shall be provided between the coil sides to correctly measure the winding temperature.)
2 nos. RTDs (1 per DE & NDE bearing) (Simplex)
Yes / No
3 nos. RTDs Duplex (one per phase) located at the base of the slots, placed 120° apart.
3 wire, PT-100
Squirrel Cage
Single/ Double
DOL / VFD
Constant Torque/ Constant Power
70°C over an ambient of 50°C
°C (Stator / Rotor)
°C (Alarm / Trip)
°C (Alarm / Trip)
Bottom / Side
250mV - In case of antifriction ball bearing 400mV - In case of sleeve bearing
1 phase 240 volts AC
Parallel
Descriptions
Name of Manufacturer.
Applicable Standard to which cable confirms
Type of cable
Voltage Grade.
Conductor detail
Conductor material
Nominal cross-sectional Area
Min Number-of strands in each conductor.
Shape of conductor
Screening on Conductor :
Type &-Material.
Approx. . Thickness
Continuous working temperature.
Insulation :
Material.
Nominal thickness
Screening on Insulation :
Non metallic part
Material / Type
Approx. thickness
Armouring :
Material.
Nominal dimension of Round wire
Outer Sheath :
Material.
Extruded or Wrapped
Thickness (Min.).
Colour of outer sheath
Approximate overall diameter.
Standard drum length
Non-standard drum length
Overall Quatity Tolerance
Continuous Current Rating for Standard IS Condition when Laid.
Direct in ground at 30°c
In-air at 40°c
Allowable max. cond. Temp. when carrying cont. rated current
Short Circuit Rating
Short Circuit-current rating for 1 Sec. duration
Allowable max. cond. Temp.-at the time of short circuit
Electrical parameters
Conductor DC Resistance at 20°C. ( Max.)
Conductor AC Resistance at 90°C( approx..).
Approx. Reactance-of-cable at 50HZ
Approx. capacitance of cable
Insulation Resistance.( Volume resistivity )( Min)
at 27 Deg.C
at 90 Deg. C
Marking detail (Embossing/printing)
Sequential marking of length
UNITS/ DATA
3 Phase, 4 Wires
As per Part II B
As per Part III
CRCA Sheet steel
IP 41 for indoor, IP55 for outdoor
min. 2 mm thick Anodised Aluminium
min. 2 mm
min. 3 mm
sheet steel for 3 core Cables and non magnetic for 1C cables.
Aluminium
Electrolytic
As per IS-13947
Yes, Colour coded Heat shrinkable sleeves.
SMC/DMC/ FRP/ Epoxy
SMC / EPOXY / DMC
Clustered LED type
Analog / Digital
Digital
spring return
Stay put type, Mushroom head, turn to release
2 coats of epoxy based primer, powder coating
2 coats of epoxy based primer, powder coating
7 tanks process for surface preparation
Shade 632 of IS-5
60 Microns
UNITS/ DATA
3 Ph, Squirrel Cage Induction Motor
Indoor / Outdoor
Volts, 3 Phase ± %
YES/NO
YES for LT VFD
Voltage Source Interver, sine wave PWM
IGBT (Third Generation)
150 % for 1 minute
YES / NO
YES / NO
YES (Using Thermistors / RTDs)
YES / NO (kW & Above)
Pot, Free Contact
Pot, Free Contact
Pot, Free Contact
4-20 mA Analog active
4-20 mA Analog active
Pot, Free Contact
Pulsed Pot. Free Contact
Latched Pot. Free Contact
Latched Pot. Free Contact
4-20 mA Analog active
RS-485 / 232 / Ethernet
Profibus / Modbus / LON
Copper cables / Fibre Optic
UNITS/ DATA
kVA, V, Hz
1 Ph. 2 Wire
Parallel Redundant Online UPS with
3 Phase, 4 Wire
230 V, ± 1 % on UPS (Free run); ± 10 % on Bypass
50 Hz, ± 1 % on UPS (Free run); ± 5 % on Bypass
Sinusoidal
6 pulse /12 pulse
IGBT / SCR - Diode Module
2 % RMS ( max.)
IGBT / SCR
A for msec
VRLA ( 2 V Per Cell )
As per ACDB feeder list
SFU - HRC Fuse / fast acting semiconducting device
As per ACDB feeder lis
2 mm thick CRCA sheet steel.
Bottom
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
MODIFIED SCHEDULE.pdf
Vollume I_Pre-Qualification.pdf
Volume II_Technical Specification.pdf
Volume III_ Price Bid.pdf
1 Annexure I Scope chart for entire power plant.xlsx
XLSX
2 Annexure II Fuel Analysis.pdf
3 Annexure III HMBDs.pdf
4 Annexure IV Plot Plan Layout R1.pdf
5 Annexure V Single Line diagram 2 X 7 MW CPP R2-Model.pdf
6. Annexure VI DCS Architecture-Model 29.5.25.pdf
7 Annexure VII Specifications of Painting R1.pdf
8 Annexure VIII Specifications of Insulation R1.pdf
9 Annexure IX Vendor List R1.pdf
10 Annexure X A Data Sheets Mechanical.xlsx
XLSX
10 Annexure X B Data Sheets Electrical.xlsx
XLSX
11 ANNEXURE XI - Coal Sieve Analysis.pdf
12 Annexure XII_GIDC-2-032024-M001_LEGEND.pdf
12 Annexure XII_GIDC-2-032024-M004_Water _ Steam-Model.pdf
12 Annexure XII_GIDC-2-032024-M005_Cooling Water-Model.pdf
12 Annexure XII_P and ID.pdf
13 Annexure XIII AHS-Model.pdf
14 Annexure XIV UPS Schematic Block diagram.pdf
15 Annexure XV WTP Scope Matrix WTP.pdf
16 Annexure XVI Water Treatment Plant SchemeR1.pdf
17 Annexure XVII Coal Handling System Scheme.pdf
18 Annexure XVIII Construction Safety Manual.pdf
19 Annexure XIX PFD-Model.pdf
20 Annexure XX Water Analysis Report 1.pdf
21 Annexure XXI_1_Geotechnical Investigation Report_Medafer.pdf
21 Annexure XXI_2_Geotechnical Investigation Report_Bakorpur Timbi.pdf
21 Annexure XXI_3_Geotechnical Investigation Report_Asanvad.pdf
21 Annexure XXI_4_Geotechnical Investigation Report 1.pdf
21 Annexure XXI_5_Geotechnical Investigation Report.pdf
21 Annexure XXI_6_Geotechnical Investigation Report.pdf
21 Annexure XXI_7_Geotechnical Invest Report_Thakor Talavadi.pdf
21 Annexure XXI_8_Geotechnical Invest Report_Kansagar.pdf
22 Annexure XXII Public Addressing System.pdf
23 Annexure XXIII Fire Fighting System locations.pdf
24 Annexure XXIV CCTV Locations.pdf
25 Annexure XXV TG Building Layout.pdf
26 Annexure XXVI Typical Steam distribution.pdf
27 Annexure XXVII Return Condensate System.pdf
28 Annexure XXVIII Abbreviated List.pdf
29 Annexure XXIX Codes Standards.pdf
30 Annexure XXX Man Power Schedule.pdf
31 Annexure XXXI Pipe rack drawing.pdf
32 Annexure XXXII Road Specifications.pdf
33 Annexure XXXIII Compound wall specifications-.pdf
34 Annexure xxxiv_ Details Civil Specification.pdf
Vollume IV_Form C Agreement.pdf
BDP Steam Plot coordinates.pdf
Details for NGL FGL.pdf
Geotechnical Investigation Report.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .