| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹96.3 LAccepted-AOC BB 52 SECTOR 1 SALT LAKE CITY KOLKATA 700 064 | KOLKATA | 24 PARAGANAS NORTH | WEST BENGAL | 700064 | L1 | Accepted-AOC 1st lowest bidders. | |
| 2 | L2₹96.6 L+₹28,903.92 (0.30%)Rejected-Finance | L2 | Rejected-Finance 2nd lowest bidders. | |
| 3 | L3₹97.3 L+₹1.0 L (1.05%)Rejected-Finance | L3 | Rejected-Finance 3rd lowest bidders. |
Tender Value
₹96.3 L
EMD Value
₹1.9 L
Closing Date
4 Feb 2026, 3:00 pmClosed
EE, PWD
BMC
Construction of pump and filtration house with underground reservoir for Olympic Standard Swimming Pool at Narayantala Depomath within Ward No.17 under Bidhannagar Municipal Corporation. (15th Finance)
2026_MAD_989340_1
NIT No.2042/PWD(BMC) dt.15/01/2026
Open Tender
CIVIL WORKS
Percentage
120 days
Bidhannagar Municipal Corporation
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹1.9 L
12 May 2026
15 Jan 2026
6 Feb 2026
15 Jan 2026
4 Feb 2026
15 Jan 2026
Surface Dressing of the ground in any kind of soil including removing vegetation inequalities not exceeding 15 cm depth and disposal of the rubbish within a lead upto 75 m as directed.
Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1500 mm
Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. Depth of excavation for additional depth beyond 1,500 mm. and upto 3,000 mm. but not requiring shoring
Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. Depth of excavation for additional depth beyond 3000 mm. upto 4000mm. excluding cost of shoring as necessary.
Hire and labour charges for shoring work (including necessary close plank walling, framing, Eucalyptus/Jhou bulla piling, strutting etc) complete as per direction of the Engineer-in-charge for foundation excavation (vertical surface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge). Depth upto 1.5 m.
Hire and labour charges for shoring work (including necessary close plank walling, framing, Eucalyptus/Jhou bulla piling, strutting etc) complete as per direction of the Engineer-in-charge for foundation excavation (vertical surface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge). For additional depth beyond 1.5 m. and upto 3.00 m
Hire and labour charges for shoring work (including necessary close plank walling, framing, Eucalyptus/Jhou bulla piling, strutting etc) complete as per direction of the Engineer-in-charge for foundation excavation (vertical surface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge). For additional depth beyond 3.00 m.
Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) With earth obtained from excavation of foundation
Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity)
Anti termite treatment to bottom surface ( in case of masonry foundation and basements) and the sides (upto a height of 300 mm. from bottom) of the excavation trenches with chemical emulsion by admixing chloropyrofos emulsifiable concentrates (1% concentration) with water by weight at the rate of 5 Litres per sq. m. area. The work shall be carried out as per specification described in 6.2.1. of code IS6313 (part -II) 1981. (Mode of measurment will be the plan area of foundation treated.)
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. Pakur Variety
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) (When the height of a particular floor is more than 4 m the equivalent floor height shall be taken as 4 m and extra for works beyond the initial 4 m ht. shall be allowed under 12 (e) for every 4 m or part thereof) Steel shuttering or 9 to 12 mm thick approved quality ply board shuttering in any concrete work.
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. For works in foundation and upto roof of ground floor/upto 4 m. Tor steel/Mild Steel : SAIL/TATA/RINL
Supplying ready mixed concrete of M 25 Grade with well graded stone chips of 20 mm nominal size containing designed quantity of cement per Cu.m of wet concrete produced in computerised batching plant under controlled condition using approved super plastisizer, designing concrete mix following I.S. 10262 and I.S. 456, transporting the mix with agitation in transit mixer to work site depositing the mix on a platform erected for the purpose at required levels of concreting and then placing the mix in its final location of form work compacting and curing the same complete as per specification & direction of the Engineer-in-charge including computerised batching plant transit mixer with all accessories vibrators etc. inclusive of all other incidental charges in this connection complete but excluding cost of hire charge of platform and its supporting staging which would be paid through separate item. [cement to be supplied by the Manufacturer/ supplier] In Ground Floor and Foundation. With approved concrete pump
Brick work with 1st class bricks in cement mortar (1:4) In foundation and plinth
125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor.
Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor). [Excluding cost of chipping over concrete surface] With 1:6 cement mortar : 25 mm thick plaster
Supplying, fitting & fixing Glass mosaic tiles at finished plain wall surface of size 20 mm x 20 mm x 4 mm in all colour, design, fixing in customize design as per direction of Engineerin- Charge. The glass mosaic tiles to be fixed on the wall surface with the help of approved adhesive applied at the rate of 2.5 kg per sqm and grouting of the same. The rate is inclusive of all operation, material and required pattern approved by Engineer-in-Charge. [At Ground Floor] Gradation/ Progression Type
Sunflower Wall Painting (hand painted sunflower) artwork on wall using acrylic / weather resistant colors. Underwater Theme Wall Painting (detailed underwater scene with fishes, corals, plants, gradients and shading).
Alpana Decorative Work (Traditional Alpana design using white & color paints on floor / walls as required).
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.63 MB
Tendernotice_2.pdf
PDF • 1.36 MB
BOQ_2417254.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .