| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 2₹44.0 L+₹3.8 L (8.61%)Accepted-AOC | 2 | Accepted-AOC 1st lowest | |
| 2 | 1₹44.0 LRejected-AOC | 1 | Rejected-AOC 2nd lowest |
Tender Value
₹50.4 L
EMD Value
₹50,000
Closing Date
23 Jul 2021, 5:00 pmClosed
PROJECT ENGINEER
KLDC LTD, SAI DARSAN, CHIRAKKADAVAM PO, KAYAMKULAM
VFPCK- Construction of building for farmers knowledge centre at Anayara,Trivandrum(Re-etender)
2021_KLDC_430423_1
02/KLDC/ PE (Kylm)/ 2021-22(1-2)(1)
Open Tender
Civil Works - Buildings
Item Rate
180 days
KLDC LTD, KAYAMKULAM
Please refer Tender documents.
6 documents required · 6 mandatory
₹2,950
Yes
₹50,000
Yes
4 Oct 2021
15 Jul 2021
27 Jul 2021
15 Jul 2021
23 Jul 2021
15 Jul 2021
15 Jul 2021 - 23 Jul 2021
Amount
STRUCTURAL FRAME WORK- GROUND FLOOR
2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
51.2.3 : Filling with Quarry Muck <br> Filling up low lying and water logged areas with local material/ quarry muck, spreading in layers, leveling the top at site and consolidation by ramming, etc complete for improving the CBR value of subgrade
2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
20.6.1.1 : Vertical load testing of piles in accordance with IS 2911( Part IV) including installation of loading platform and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of engineer -in-Charge.Single pile upto 50 tonne capacityInitial test
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.1.8 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.33.1 : Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately.All work upto plinth level
5.33.2 : Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer - in-charge. Note:- Cement content considered in this item is @ 330 kg/ cum. Excess or less cement used as per design mix is payable or recoverable separately.All work above plinth level upto floor V level
5.35 : Add for using extra cement in the items of design mix over and above the specified cement content therein
5.9.6 : Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
4.3.1 : Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
5.9.5 : Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.22A.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
10.17 : Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar, bent to shape with hooked ends in R.C.C. slabs or beams during laying, including painting the exposed portion of loop, all as per standard design complete.
RCC PILE & PILE CAP: M30 CONCRETE
od297580/2020_2021 : Bored cast-in-situ M30 grade R.C.C. Pile excluding Reinforcement complete as per Drawing and Technical<br>Specifications and removal of excavated earth with all lifts and lead upto 1000 m Using Concrete Mixer - Pile diameter-450 mm
12.38.C.2 : Cement Concrete for Reinforced Concrete in Pile Cap complete as per Drawing and Technical Specification<br> R C C Grade M-30- Using Batching Plant, Transit Mixer and Concrete Pump <br>
Mohammed Refeek R
Bidder Name
KM IKBAL KHAN
Mohammed Refeek R
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_610875.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .