| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L2₹9.4 Cr+₹1.7 Cr (21.8%)Accepted-AOC | ₹9.4 Cr+₹1.7 Cr (21.8%) | L2 | Accepted-AOC Quoted reasonable and realistic rate |
| 2 | L1₹7.7 CrRejected-Finance | ₹7.7 Cr | L1 | Rejected-Finance Quoted abnormally low and unrealistic rate |
| 3 | Rejected-Technical | - | - | Rejected-Technical Non fulfilment of terms and conditions of tender |
Tender Value
Refer Docs
EMD Value
₹9.9 L
Closing Date
26 Dec 2024, 4:00 pmClosed
Executive Engineer, Yomcha Division, PWD, AP
O/o Executive Engineer, Yomcha Division, PWD, AP, West Siang District, AP
Road work
2024_PWDAP_2016_1
YCAD/CRF/WS-31/2024-25/414 dtd 07/12/2024
Open Tender
Civil Works – Roads
Item Rate
730 days
Liromoba
As mentioned in Tender Document
8 documents required · 8 mandatory
₹5,000
EE PWD Yomcha
₹9.9 L
Yes
18 Mar 2025
9 Dec 2024
27 Dec 2024
9 Dec 2024
26 Dec 2024
19 Dec 2024
17 Dec 2024 - 18 Dec 2024
Amount
Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. a)Girth from 300 mm to 600 mm
Cutting of trees, including cutting of trunks, branches and removal of stumps, roots, stacking of serviceable material with all lifts and up to a lead of 1000 metres and earth filling in the depression/pit. b)Girth from 600 mm to 900 mm
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. In area of thorny jungle
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto 1000 metres)
Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by mechanical means including cutting and trimming of slopes and disposal of cut material with all lifts and lead upto 1000 metres)
Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing
Preparation of sub grade (Preparation of sub grade by excavating earth to an average depth of 22.50 cm, dressing to camber and consolidating with road roller, making good the undulations etc. and disposal of surplus earth, lead upto 50 m.)
Consolidation of sub-grade with road roller of 8 to 12 tonne capacity including making good the undulations etc. with
Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2) (Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401) i) For Grading- I Material
Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.) Ordinary soil/Manual Means/Upto 3 mtr depth
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications Coursed rubble masonry (first sort)
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications Random Rubble Masonry
Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications ( PCC Grade M-15)
Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as per drawing and Technical Specification (RCC Grade M 25)
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
Plain/Reinforced cement concrete in sub - structure complete as per drawing and technical specifications ( RCC Grade M-20)
Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size aggregate, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete as per approved drawings and technical specifications.
Surface Drains in Soil (Construction of unlined surface drains of average cross sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to the requirement of clause 301 and 309. Excavated material to be used in embankment within a lead of 50 metres (average lead 25 metres)) By mechanical means
Surface Drains in Ordinary Rock (Construction of unlined surface drain of average cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions as per approved design and to the requirement of clause 301 to 309. Excavated material to be used in embankment at site.) By mechanical means
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres) II, A)Cement Concrete Grade M-15 & M-20
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres) II, B)Prestressed / Reinforced cement concrete grade M-20 & above
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres) III, Dismantling Stone Masonry B. Rubble stone masonry in cement mortar.
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Stone masonry work in cement mortar 1:3 for substructure complete as per drawing and Technical Specifications Random Rubble Masonry
Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specifications
Plain/Reinforced cement concrete in sub-structure complete as per drawing and technical specifications ( PCC Grade M-15)
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical specifications
Back filling behind abutment, wing wall and return wall complete as per drawing and Technical specification
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. PCC Grade M20
Plain/Reinforced cement concrete in sub - structure complete as per drawing and technical specifications( RCC Grade M-20)
Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and technical specifications
Ms. Barapani enterprises (BID ID -6135)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .