Loading…
Loading…
Tender Value
₹36.3 L
EMD Value
₹37,000
Closing Date
9 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Executive Engineer, Salinity Control Division, Porbandar
REPAIRING OF CHECKDAM CUM CHECK STRUCTURE ON PBFC CANAL AT VILLAGE RINAVADA IN PORBANDAR TALUKA & DISTRICT UNDER S.S.J.A-2026
290380
48 of 2025-26
Open
Civil Works - Others
Porbandar
10 documents required · 8 mandatory · 2 optional
₹1,500
Yes
Executive Engineer, Salinity Control Division, Porbandar
₹37,000
Yes
26 Mar 2026
26 Mar 2026
26 Mar 2026
9 Apr 2026
26 Mar 2026
BILL OF QUANTITIES
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and
are given to provide a common basis for bidding. The basis of payment will be
the actual quantities of work ordered and carried out, as measured by the
Contractor and verified by the Engineer and valued at the rates and prices
tendered in the priced Bill of Quantities, where applicable, and otherwise at such
rates and prices as the Engineer may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so
far as it is otherwise provided under the Contract, include all constructional
plant, layout, supervision, materials, erection, maintenance, insurance, profit,
taxes and duties, together with all general risks, liabilities and obligations set out
or implied in the Contract.
4. The rates and prices shall be quoted entirely in Indian Currency.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed
to enter a rate or price shall be deemed to be covered by other rates and prices
entered in the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be
included in the items provided in the priced Bill of Quantities, and where no
Items are provided the cost shall be deemed to be distributed among the rates
and prices entered for the related items of Work.
7. General direction and descriptions of work and materials are not necessarily
repeated or summarized in the Bill of Quantities. References to there levant
sections of the contract documentation shall be made before entering rates or
prices against each item in the Bill of Quantities.
8. The method of completed work of payment shall be in accordance with the
specification for this work. For building works specifications for building are to
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledge hammers, or the use of
compressed air drilling for its removal, and which cannot be extracted by
ripping with a tractor of at least 150kw with a single rear mounted heavy duty
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
Description of Item (with brief Rate
specification and reference to book of Qty Unit (Without
No. (Without GST)
specifications) GST)
1 Jungle clearance (Ganda Baval etc) of 7100.00 SQ.Mt. 5.00
Light/heavy dence (work done by
manually or by machinery ) including
grabbing of & removing the roots &
girth completely from the ground &
back fill with earth & making surface
good as directed including depositing
& removing the material away from
the site of work at own risk and cost
as and where directed etc completed
for following.(b) Heavy density
2 Drilling 25mm dia holes at distance 34.00 Rmt. 252.00
as specified and depth upto 3.0mt for
check dam foundation & fixing
anchor bars of specified diameter
with cement grout incl cleaning holes
as directed etc.(excluding cost of
3 Dismantling C.C. foundation or 97.00 Cumt 828.00
flooring sorting & stacking useful and
unuseful material in lead upto 200mt
as directed etc. complete.
4 Excavation in all sort of strata and 516.00 Cumt 79.00
formations incl. depositing the
unuseful excavated stuff as and
where directed incl.sorting and
stacking useful materials in
measurable conditions as directed
upto 200mt lead and all lift etc.
complete incl. dewatering. (A) IN
OVERBURDEN INCL. HARD
5 Prov. and Laying in position 754.00 Cumt 3822.00
'NOMINAL MIX' cement concrete
using cement, sand and crushed
aggregate by machine mix including
necessary formworks centering
scaffolding compaction by
mechanical vibrator,curing as
directed with all lead & lift etc
complete (c) Concrete grade (1:2:4)
and MSA-40mm(graded).
6 Providing,cutting,bending,binding 4.25 MT 76574.00
and fixing in position as per drawing
.TMT BAR ,reinforcement for R.C.C.
works and anchor bars incl cost of
black annealed 16 to 18 BWG
M.S.Wire etc. complete with all lead
and lift.(B)Fe-500
7 Providing murrum including 1530.00 Cumt 166.00
spreading the same and dressing the
side slope & top surface in required
grade and camber with lead upto
km etc complete.
Total Amount :-
Total Amount :-
In words (Rupees Thirty Six Lac Twenty Six Thousand Three Hundred Fifty Five and
Fifty Paisa Only)
percent (Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our
tender works out as under.
Estimated amount put to tender Estimated amount put to tender
In words In words
(B) For Item Rate Tender (For Above INR 50 Cr. )
Description of Item (with brief
specification and reference to Quantity Unit Amount
book of specifications)
(A) Total Tendered Amount
(C)Net Tendered Amount (A- EE
1 The Contractor shall exhibit a board with detailed specification and details of work as
directed by the Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analys`is Standard Cement Consumption has been taken as
per Govt. G.R.: No. MIS 102010/17/K1, dtd. 30/07/2018 as stated in S.O.R. therefore
in R.C.C. items where there is a change as per actual mix design the cost of difference
of cement consumption have been deducted from the rate of original item at the rate
of input rate mentioned in all the tender.
Signature of Contractor Executive Engineer
Salinity Control Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
48 of 2025-26 tender notice.pdf
SBD Checkdam on PBFC canal 36.26.pdf
BOQ Checkdam on PBFC canal 36.26.pdf
Download all tender documents and submit your bid