Tender Value
₹7.1 L
EMD Value
₹7,200
Closing Date
19 Jun 2026, 6:00 pmClosed
Executive Engineer, Panchayat (R&B) Division, DAHOD
Construction of Toilet Block @ Village Rupakheda Bhuriya Faliya Taluka: Govind Guru Limdi (Jhalod) Dist.Dahod under MPLADS Jogvai 2024-25
312584
06 of 2026-2027
Open
Civil Works - Buildings
Works
Dahod
7 documents required · 7 mandatory
₹900
Executive Engineer, Panchayat (R&B) Division, DAHOD
₹7,200
9 Jun 2026
9 Jun 2026
9 Jun 2026
19 Jun 2026
9 Jun 2026
No. figures Amount
Civil Work
1 1) Excavation for foundation up to 1.50 mt. depth including 24.80 Cu.m. 160.89
sorting out and stacking of usefull materials and disposing of the
excavated stuff up to 50 meter lead ( B ) Dence and hard soil
2 2) Providing and laying cement concrete 1:4:8 (1 - cement :4 3.49 Cu.m. 2679.92
Coarse sand :8 crushed stone aggregates 40 mm nominal size )
and curing complete excluding cost of formwork in ( A )
Foundation and Plinth
3 3) Brick work using common burnt clay building bricks having 4.36 Cu.m. 3853.23
crushing strength not less than 35 Kg./Sq.Cm in foundation and
plinth in cement mortar 1:6 ( 1 cement : 6 Fine sand) ( B )
Conventional
4 4) Providing and laying cement concrete 1:3:6 (1- Cement : 3- 1.20 Cu.m. 3992.43
Coarse sand : 6- graded stone aggregates 20 mm nominal
size) and curing complete including the cost of formwork in (A)
Walls Caps / Coping.
5 5) Brickwork using common burnt clay building bricks having 24.20 Cu.m. 4141.66
crushing strength not less than 35 kg./Sq.Cm. in superstructure
in Cement Mortar 1:6 (1- Cement : 6 -fine sand) (B)
Conventional
6 6) Filling available excavated earth ( Excluding Rock) in trenches, 45.70 Cu.m. 137.47
plinth, side of foundation etc. in layers not exceeding 20cm in
depth consolidating each deposited layer by ramming and
7 7) Providing and laying cement concrete work 1:2:4 ( 1 cement : 1.94 Cu.m. 4482.98
2 coarse sand: 4 graded stone aggregate 20 mm nominal size )
including the cost of form work with curing etc. complete.
(A) Foundation footing base.
8 8) Providing and laying cement concrete work 1:2:4 ( 1 cement : 3.48 Cu.m. 8447.55
2 coarse sand: 4 graded stone aggregate 20 mm nominal size )
including the cost of form work with curing etc. complete.
(A) Columns
9a 9A) Providing and laying cement concrete 1:2:4 ( 1 Cement : 2 0.81 Cu.m. 10219.39
Coarse sand : 4 graded stone aggregate 20 mm. nominal size )
for R.C.C lintel including finishing smooth with curing etc.
complete including the cost of formwork but excluding the cost of
reinforcement .
It. Rate in Total
Description of Item Qty. Unit
No. figures Amount
9b 9B) Providing and laying cement concrete 1:2:4 ( 1 cement : 2 0.00 Cu.m. 0.00
Coarse sand : 4 graded stone aggregate 20 mm. nominal size )
for R.C.C chhajjas not exceeding 10 Cm. thickness up to fllor
two level including finishing the exposed surface with cement
mortar 1:3 (1 cement :3 fine sand ) to give a smooth and even
surface centering and formwork and curing complete excluding
the cost of reinforcement .
10 10) Half brick masonry in common brunt clay building bricks 80.00 Sq.mt. 758.76
having crushing strength not less than 35 Kg/Sq.Cm. in Cement
mortar 1:3 ( 1-Cement : 3-coarse sand ) with 2 Nos of 6mm Mild
steel round bars after every three course embedded in Cement
Mortar in (B) Conventional.
11 11) Providing and laying ordinary cement concrete M250 5.25 Cu.m. 10824.26
Exposed and finishing smooth with,curing etc. complete
including the cost of formwork but excluding the cost of
reinforcement for R.C.C. work in (A) Beam (i) having cross
sectional area more than 0.05 Sqm. and upto 0.08 Sqm.
12 12) Providing and laying ordinary cement concrete 1:2:4 (1- 0.00 Cu.m. 0.00
Cement 2- coarse sand : 4- graded stone aggregates 20 mm
nominal size) and finishing smooth with,curing etc. complete
including the cost of formwork but excluding the cost of
reinforcement for R.C.C work in A) Beam (ii) having cross
sectional area more than 0.08 Sqm. and upto 0.12 Sqm.
13 13) Providing and laying dinary orcement concrete 1:2:4 ( 1 9.14 Cu.m. 6888.15
cement : 2 coarse sand: 4 graded stone aggregate 20 mm
nominal size ) and finishing smooth with curring etc.
Complete including the cost of form work but excluding the cost
of reinforcement for R.C.C work in (iii) slab having more than
cms and up to 13 cms. thickness.
14 14) Providing ISI Mark TMT Bar 415 Fe reinforcement for R.C.C. 1639.04 Kg. 68.33
work including bending, binding and placing in position complete
upto floor two level.
15 15) Providing 15 mm. thick cement plaster in single coat on fair 170.00 Sq.mt. 286.47
sides bricks / concrete walls for interior plastering up to floor two
level finished even and smooth in cement mortar 1:3 (1 cement :
3 coarse sand) including finishing with a floating coat of neat
cement slurry.
16 16) Providing 10mm thick cement plaster in single coat on 91.40 Sq.mt. 229.17
brick/concrete walls for interior plastering upto floor two level and
finished even and smooth in (i) Cement mortar 1:3 (1-cement:3-
sand) plastering on ceilings and sofits of stairs upto floor two
level instead of plasterning on walls for every additional storey.
17 17) 20mm thick sand faced cement plaster on walls upto height 84.00 Sq.mt. 353.98
10 metres above ground level consisting of 12mm thick backing
coat of C.M. 1:3 (1-cement : 3-sand) and 8mm thick finishing
coat of C.M. 1:1 (1-cement : 1-sand) etc. complete.
It. Rate in Total
Description of Item Qty. Unit
No. figures Amount
18a 18A) Providing and fixing steel door with shutter with frame 50 x 4.20 Sq.mt. 2343.62
50 x 6 mm. iron angle and BG 18 mm. steel plates with hinges,
handle, stopper, locking arrangement etc. steel work welded in
built section cutting hosting, finishing in position two coats of oil
paint and one coats of primer coat etc. comp.
18b 18B) Providing and fixing steel window with shutter with frame 0.00 Sq.mt. 0.00
size 50 x 50 x 6 mm. iron angle and BG 18 mm. steel plates with
10 mm dia round bars, hinges, handle, stopper, locking
arrangement etc. complete steel work welded in built section
cutting hosting, finishing in position two coats of oil paint of
approved quality over one coats of primer coat etc. comp.
19 19) Providing and laying white glaze tiles 6mm thick in flooring 73.40 Sq.mt. 911.46
treads of steps and landing laid on a bed of 12mm thick cement
mortar 1:3 (1-cement : 3-coarse sand ) finishing with flush
pointing in white cement.(A) White galzed tiles
20 20) Providing and laying white glaze tiles 6mm thick in skrting 15.60 Sq.mt. 1017.48
resers of steps and dedo on 10 mm thick cement mortar 1:3 (1-
cement : 3-coarse sand ) and jointed with white cement slurry. ()
White Glazed Tiles)
21 21) Providing and laying Plumbing & Drainage Work 2.00 Each 10100.00
22 22) Distempeing with dry distemper of approved brand and 170.00 Sq.mt. 66.01
manufacture (Two coats) of required shade on wall surfaces to
give an even shade, over and including a priming coat of whiting
after throughly brooming the surface free from mortar dropping
and other foreign matter.
23 23) White washing with lime on Ceiling surface (Two coats) to 91.40 Sq.mt. 13.52
give an even shade including throughly booming the surface to
remove all dirt, dust, mortar drops and loose scales of lime wash
24 24) Finishing wall with water proofing cement paint of on wall 84.00 Sq.mt. 96.29
surfaces (Three coats) to give an approved brand and
manufacture and of required shape even shade after thoroughly
brushing the surface to remove all dirt and remains of loose
powered materials.
25 25) Providing and fixing 20 cm x 15 cm x 2.5 cm. Thick year plate 2.00 Each 279.69
of marble stone set in C.M. 1:4 including finishing and engraving
letters etc. complete.
26 26) Providing and fixing M,S. grills of required pattern to wooden 0.00 Kg. 0.00
frames of windows etc with M.S. flats at required spacings and
frame alround square or round bars with round headed bolts and
nuts or by screws ( A ) plain grill.
Total Amount (Civil) TOTAL Rs.
Total Amount (Civil) TOTAL Rs.
i.e. Rupees Seven Lakh(s) Thirteen Thousand Five Hundred Nineteen And Paise Five Only
It. Rate in Total
Description of Item Qty. Unit
No. figures Amount
I/We am/are willing to carry out the work @ ______________ % above/below percent (Should be written
in figures and words) of the estimated rate mentioned above. Amount of my /our tender works out as under.
Estimated amount put to tender Estimated amount put to tender
Deduct………% below Add………% Above
Net Rs. ___________________________ Total Rs. ________________________
In words ____________________ In words ____________________
1. The Contractor shall exhibit a board with detailed specification and details of work as directed by the Engineer-In-Charge
for which no extra payment shall be made.
2. The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3. GST and Income tax TDS will be deducted at a source while making payments of bills.
4. In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R.: PRC-10/2017
Cement Consumption/16/C, Date:11/05/2017 as stated in S.O.R. therefore in R.C.C. items where there is a change as
per actual mix design the cost of difference of cement consumption have been deducted from the rate of original item at
the rate of input rate mentioned in all the tender.
Above all items of "Schedule-B" with Item Description, Unit, Rate & Amount have verified by me and found
Deputy Executive Engineer Deputy Executive Engineer
Panchayat (R & B) Sub Division Godhra Electrical Sub Division
JHALOD R&B Deptt. Godhra
Divisional Account Officer Executive Engineer
Panchayat (R & B) Division Godhra Electrical Division Executive Engineer
DAHOD R&B Deptt. Godhra Panchayat (R & B) Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
2. GRs - SBD with Index non BT.pdf
2.GR for Inspection 16.10.2025 NEW.pdf
2.GR for Mix Design 16.10.2025 NEW.pdf
BUILDING SPECIFICATION BOOKLET.pdf
01 SBD Book Toilet Block Rupakheda Bhuria Falia Ta.Limdi.pdf
01.E Tender Toilet Block Rupakheda Bhuria Falia Ta.Limdi.pdf
3. SC.B Bill of Qty.pdf
4. Specification Index.pdf
4.Specification Toilet Block Rupakheda Bhuria Falia Ta.Limdi.pdf
7. List of Work included in Pkg.pdf
7. Testing.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .