| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC | ₹1.2 Cr | L1 | Accepted-AOC Amount is below Est Rate |
| 2 | L2₹1.2 Cr+₹2.4 L (2.02%)Rejected-AOC | ₹1.2 Cr+₹2.4 L (2.02%) | L2 | Rejected-AOC Amount is Above Est Rate |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Others-five years Turnover not submitted |
Tender Value
₹1.2 Cr
EMD Value
₹1.2 L
Closing Date
14 Dec 2023, 3:00 pmClosed
District Collector/Chairman
IInd Floor, DRDA Collectorate, Karur
Strengthining of the road from Panaiyur Neithalur road to Akkanakadu
2023_RDTN_378268_29
DRDA Karur - NABARD XXIX 2023-24
Open Tender
Civil Works - Roads
Item Rate
180 days
Karur
Please refer tender Documents
8 documents required · 8 mandatory
₹0
₹1.2 L
IInd Floor, DRDA Collectorate, Karur
30 Jan 2024
30 Nov 2023
14 Dec 2023
4 Dec 2023
14 Dec 2023
4 Dec 2023
6 Dec 2023
Amount
Name of the work : Strengthening the road from Panaiyur Neithalur Road To Akkanakadu-0/0 -2/5 (R330)
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of Prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Road Marking with hot applied thermoplastic Compound with Reflectorising Glass Beads on Bituminous surface
Provision for Cautionary sign board (60cm Equilateral Triangle)
Provision for KM Stones
Provision for HM Stones
Provision for Reflectors
Provision for Name Board
Name of the work : Construction of 2x5 m to span RCC Slab Culvert CH 110 of Panaiyur Neithalur Road To Akkanakadu-0/0 -2/5 (R330)
Earth work excavation For foundation in all soils and sub soil to full depth as may be directed except in hard rock requring blasting but inclusive of sharing strutting and requrirng the sides of foundation
Cement concrete 1:4:8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15 cm thick., compacting etc., complete complying with standard specification and as directed
Cement concrete 1:3:6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15 cm thick., compacting etc., complete complying with standard specification and as directed
Towards the cost of centering the the side wall including all other necessary support arrangements and labour charges etc complete
Below sill level
Above Sill level
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation including watering wherver necessary and laid in layers of not more than 15 cm thick., comnpacting etc., complete complying with standard and as directed
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for all RCC item of works exculding cost of reinforcement and fabricating charges , centering and shuttering but including curing and shall be finished smooth with cement mortar 1: 3 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specification
Supplying and fabricating and placing in position Ms steel or Ribbed for steel for all reinforced cement concrete works as per the design given including cost of steel and binding wires in all floors etc, Complete complying with standard specification .(MS rod or RTS bar will be suppiled departmentally at section stores and cost will be recovered at issue rate). the binding wire shall supplied by contractor
Providing and fixing 6mm bitumen felt for expansion joint between Dirtwall and Deck slab
Providing and fixing Tar paper for bearing Between Bed Block and Deck slab
Providing weepholes in brick masonry/stone masonry, plain /reinforced concrete abutment , wing wall , return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(v):20H towards drawing face complete as per drawing and techinical specfication clauses 614,709,1204.3.7
Gravel filling between body wall including cost and conveyance of garvel , labour for filling , watering and compacting etc complete complying with standard specification and as dirtected by the departmental officer
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP- 20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
PANDIYAN K
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .