| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.5 CrAccepted-AOC KERALA KL KERALA | PALAKKAD | KERALA | 678621 | ₹2.5 Cr Quoted ₹2.8 Cr | L1 | Accepted-AOC L1 |
| 2 | Not Admitted-Fee/PreQual/Technical/Finance | - | - | Not Admitted-Fee/PreQual/Technical/Finance Others-Scanned copy of invoice and challan of GST amount paid to the GST department directly not submitted. |
| Sl No | Description | Qty | Unit | MALABAR PLUS CONSTRUCTIONS PRIVATE LIMITED L1 |
|---|---|---|---|---|
| 1.00Construction of Under Pass | ||||
| 1.00 | 2.5.2.A:Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately Bituminous course - By Mechanical Means | 52.5 | cum | 573.46 ₹30,106.65 |
| 1.00 | 12.1.B.1:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Ordinary Soil - Depth upto 3m - Mechanical Means | 1,217.52 | cum | 85.97 ₹1.0 L |
| 1.00 | 3.4:Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections. | 202.92 | cum | 309.97 ₹62,899.11 |
| 1.00 | 3.8.B:Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections. Manual Method | 1,582.78 | cum | 3,573.32 ₹56.6 L |
| 1.00 | 12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. | 12.72 | cum | 7,980.26 ₹1.0 L |
| 1.01 | 12.8.G.2.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. RCC Grade M30 - Using Batching Plant, Transit Mixer and Concrete Pump | 261.69 | cum | 9,008.13 ₹23.6 L |
| 1.01 | 13.5.G.p.2:Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications RCC Grade M30 - Height upto 5m - using Batching Plant, Transit Mixer and Concrete Pump | 410.75 | cum | 9,573.87 ₹39.3 L |
| 1.01 | 14.1C.2:Furnishing and Placing Reinforced Cement Concrete Grade M30 Using Batching Plant, Transit Mixer and Concrete Pump in super-structure as per drawing and Technical Specification | 19.44 | cum | 8,729.22 ₹1.7 L |
| 1.01 | 13.6:Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and Technical Specifications | 87.74 | MT | 1,10,175.02 ₹96.7 L |
Tender Value
₹2.6 Cr
EMD Value
₹1 L
Closing Date
13 Feb 2026, 2:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer, PWD Roads , North circle kozhikode
DEPOSIT Vechicular Under pass in Nattukal Velanthavalam Road at Km 6/200 for M/s Ahalia international foundation Civil work General Civil Work
2026_PWD_829542_2
PWD/RB/TR/794/2025_5_1_1/1
Open Tender
Civil Works - Roads
Palakkad
Please refer Tender documents.
8 documents required · 8 mandatory
₹8,270
Yes
₹1 L
Yes
17 Mar 2026
5 Feb 2026
16 Feb 2026
5 Feb 2026
13 Feb 2026
5 Feb 2026
Construction of Under Pass
2.5.2.A:Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately Bituminous course - By Mechanical Means
12.1.B.1:Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Ordinary Soil - Depth upto 3m - Mechanical Means
3.4:Excavation for roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing the cut earth to site of embankment upto a distance of 100 metres ( average lead 50 metres ), trimming bottom and side slopes in accordance with the requirements of lines, grades and cross sections.
3.8.B:Excavation for roadway in hard rock (blasting prohibited) with rock breakers including breaking rock, loading in tippers and disposal within all lifts and lead upto 1000 metres, trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections. Manual Method
12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.
12.8.G.2.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. RCC Grade M30 - Using Batching Plant, Transit Mixer and Concrete Pump
13.5.G.p.2:Plain/Reinforced cement concrete in sub-structure complete as per drawing and Technical Specifications RCC Grade M30 - Height upto 5m - using Batching Plant, Transit Mixer and Concrete Pump
14.1C.2:Furnishing and Placing Reinforced Cement Concrete Grade M30 Using Batching Plant, Transit Mixer and Concrete Pump in super-structure as per drawing and Technical Specification
13.6:Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and Technical Specifications
14.2:Supplying, fitting and placing HYSD bar reinforcement in super-structure complete as per drawing and technical specifications
OD225865/2024-2025:PVC WHEEP HOLES- Providing wheep holes using 75mm dia PVC pipes working pressure 4kg/sqcm including cost of materials,conveyance,labour charges etc
8.20:Providing, Fixing and erecting 50 mm dia GI pipe railing in 3 rows duly painted on Tubular Steel Railing on Medium Weight Steel Channel ( ISMC series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m centre to centre, complete as per approved drawings including painting over suitable primer .
13.9.A:Back filling behind abutment, wing wall and return wall complete as per drawing and Technical Specification Granular material
OD43164/2025-2026:Construction of sub-grade and earthen shoulders with approved DEPARTMENTAL material with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2
4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.
5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.
5.3.2.a:Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with a bituminous binder (VG 30), transported to the site, laid over a previously prepared surface with paver finisher to the required grade, level, and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction For Grading II - (19 mm nominal size)
5.6.2.a:Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with a bituminous binder( NRMB) @ 5.4 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level, and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects For Grading - II (13.2 mm Nominal Size)
8.13:Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads on Bituminous Surface @ 250 gms per sqm area, the thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform, and free from streaks and holes.
8.4.3:Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign with 7years warranty manufactured as per IRC :67 made of Type IV micro prismatic grade sheeting vide clause 801.3.3 fixed over aluminium sheeting, 2 mm thick/ aluminium composit material sheeting 4 mm thick with suitable back supporting frame of MS angle 25x25x3 and supported on GI pipe pole 50mm NB confirming to IS 1239 firmly fixed to the ground by means of properly designed foundation with M 15 grade cement concrete min size 45 cm x 45 cm x 60 cm, 60 cm below ground level including painting all exposed surface with 2 coats of epoxy painting over epoxy primer and as per approved drawing and clause 801 including lettering symbols etc. 60 cm circular
8.8:Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces
OD240784/2024-2025: Providing and Placing in position suitable PVC water stops conforming to IS : 12200 for construction / expansion joints between two RCC members and fixed to the reinforcement with binding wire before pouring concrete etc. complete: Serrated with central bulb ( 225 mm wide, 8-11 mm thick)
OD111173/2025-2026:Supplying and laying of polyester needle punched non woven geotextile as filter media behind Gabion/ gabion fascia units, as per MORTH 700 type - III geotextile. The width of geotextile roll shall not be less than 4.5m, at easily accessible location including top and bottom, with all leads and lifts, manpower and machinery, materials, labour etc. complete and as directed by Engineer in charge.
5.15:Providing and laying 25 mm thick mastic asphalt wearing course with paving grade bitumen (VG - 30) meeting the requirements given in table 500-40, prepared by using a mastic cooker and laid to the required level and slope after cleaning the surface, including providing an antiskid surface with bitumen precoated fine grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into the surface when the temperature of surfaces is not less than 1000C, protruding 1 mm to 4 mm over mastic surface, all complete as per clause 516
4.1.B.2:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-VI - For sub-base cum drainage layer - Mix in Place Method
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
BOQ_1402539.xls
BOQ • 0.32 MB
nit.pdf
Tender Documents • 0.03 MB
sbd.pdf
Other Document • 3.33 MB
Download all tender documents and submit your bid