Loading…
Loading…
Tender Value
₹2.7 L
Closing Date
21 Oct 2026, 3:00 pm
The Executive Engineer City-I (East) Bilaspur
Estimate for replacement of 10 nos. detoriated PCC pole by RS joist LT pole at various location under basant vihar zone of City Dn.-1 CSPDCL Bilaspur. Estimate for replacement of 0.24 KM burn AB LT cable at sheela vihar R K NAGAR under basant vihar zone of City Dn.-1 CSPDCL Bilaspur. Estimate for replacement of 02 nos detoriated 11 kv pole LT pole 2 span AB Cable at bajarnag chouk R K nagar under basant vihar zone of City Dn.-1 CSPDCL Bilaspur. B43028260459 B43028260492 B43028260413 B43028260414 B43028260461 B43028260491
108603
EE/CITY DN - I /BSP/2026-27/ T-24
Bilaspur, Chhattisgarh
1 Oct 2026
1 Oct 2026
21 Oct 2026
Materials for LT POLE Estimate for replacement of 10 nos. detoriated PCC pole by RS joist LT pole at various location under basant vihar zone of City Dn.-1 CSPDCL Bilaspur.
1913/27.08.2026 199290.5 WITH GST WITHOUT GST
S.NO B43028260459 QTY UNIT GST+RATE TOTAL Ex.RATE TOTAL
3 SUSPENSION CLAMP 10 NO 576.46 5,764.60 488.53 4885.25
4 INSULATING PIERCING CONNECTOR AB CABLE(S 40 NO 98.54 3,941.60 83.51 3340.34
5 UDC- UNIVERSAL DISTRIBUTION CONNECTOR 10 NO 161 1,610.00 136.44 1364.41
DISTRIBUTION BOX 3 PH 4 CONNECTOR 10 EA 1,603.46 16,034.60 1358.86 13588.64
EARTHING COIL 8SWG GI WIRE 50MM DIA 450M 10 NO 143.69 1,436.90 121.77 1217.71
INCIDENTIAL CHARGES 0.075 9027.60
TOTAL 129395.55
S.NO SERVICES UNIT QTY GST+RATE TOTAL Ex.RATE TOTAL
2 Tree cutting Km.
3 Approach Clearance Km.
5 Shifting of materials to pole pits No. 10 70.01 700.10 59.33 593.31
6 Stay pit digging No. 0 324.64 0.00 275.12 0.00
7 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 10 345.57 3,455.70 292.86 2928.56
8 Fixing of LT 5 Pin cross arm with insulator No. 0 81.54 0.00 69.10 0.00
9 Pole erection complete with earthing No. 10 894.18 8,941.80 757.78 7577.80
11 Stay erection complete No. 0 223.89 0.00 189.74 0.00
12 Painting of cross arm, pole and numbering of poles No. 10 460.76 4,607.60 390.47 3904.75
13 Diamond guarding Pair 0 68.04 0.00 57.66 0.00
15 Stringing of line 3 Ph. 5 Wire Km. 0 17911.10 0.00 15,178.90 0.00
16 Transporation charges LS 1 2800.00 2,800.00 2,372.88 2372.88
TENDER AMOUNT 150677.59
Materials for RETURN Estimate for replacement of 10 nos. detoriated PCC pole by RS joist LT pole at various location under basant vihar zone of City Dn.-1 CSPDCL Bilaspur.
S.NO B43028260492 QTY UNIT GST+RATE TOTAL
MATERIAL RETURNED TO BOARD
1 CAST IRON SCRAP 1,559.560- KG 39.11 -60,994.39
Materials for LT POLE Estimate for replacement of 0.24 KM burn AB LT cable at sheela vihar R K NAGAR under basant vihar zone of City Dn.-1 CSPDCL Bilaspur.
1735/17.08.2026 92492.58 WITH GST WITHOUT GST
S.NO B43028260413 QTY UNIT GST+RATE TOTAL Ex.RATE TOTAL
1 M S NUTS AND BOLTS: - 16x40mm 0.25 KG 86.95 21.74 73.69 18.42
2 M S NUTS AND BOLTS: - 16x65mm 0.25 KG 85.5 21.38 72.46 18.11
3 INSULATING PIERCING CONNECTOR FOR ABC TO 12 NO 178.94 2,147.28 151.64 1819.73
4 INSULATING PIERCING CONNECTOR FOR AB CAB 36 NO 128.38 4,621.68 108.80 3916.68
5 INSULATING PIERCING CONNECTOR AB CABLE(S 12 NO 98.54 1,182.48 83.51 1002.10
6 DISTRIBUTION BOX 3 PH 4 CONNECTOR 0 EA 1,603.46 0 1358.86 0.00
INCIDENTIAL CHARGES 0.075 4357.40
S.NO SERVICES UNIT QTY GST+RATE TOTAL Ex.RATE TOTAL
16 Transporation charges LS 1 2800.00 2,800.00 2,372.88 2372.88
17 Dismentaling charges ls 1 1000.00 1,000.00 847.46 847.46
TENDER AMOUNT 69319.32
Materials for RETURN Estimate for replacement of 0.24 KM burn AB LT cable at sheela vihar R K NAGAR under basant vihar zone of City Dn.-1 CSPDCL Bilaspur.
S.NO B43028260414 QTY UNIT GST+RATE TOTAL
MATERIAL RETURNED TO BOARD
1 ALUMINIUM SCRAP Cable -30 KG 102 -3060
Materials for LT POLE Estimate for replacement of 02 nos detoriated 11 kv pole LT pole 2 span AB Cable at bajarnag chouk R K nagar under basant vihar zone of City Dn.-1 CSPDCL Bilaspur.
1750/17.08.2026 72450.92 WITH GST WITHOUT GST
S.NO B43028260461 QTY UNIT GST+RATE TOTAL Ex.RATE TOTAL
2 11KV V cross arm cleat type 1 NO 1,152.42 1,152.42 976.63 976.63
3 Stay clamp for 'H' Beam 1 NO 362.75 362.75 307.42 307.42
5 EARTHING COIL 8SWG GI WIRE 50MM DIA 450M 1 NO 143.69 143.69 121.77 121.77
6 11KV 5KN PIN INSULATOR (POLYMER) 3 NO 139.71 419.13 118.40 355.19
8 G.I. WIRES: - Barbed wire. 2 KG 84.31 168.62 71.45 142.90
9 Danger boards 33KV & 11 KV. 1 NO 101.61 101.61 86.11 86.11
11 M S NUTS AND BOLTS: - 16x65mm 0.6 KG 85.5 51.3 72.46 43.47
13 LT FIVE PIN CROSS ARM 1 NO 939.1 939.1 795.85 795.85
14 SHACKEL INSULATORS 90 x 75 mm. 4 NO 16.99 67.96 14.40 57.59
15 HARDWARE FOR 75X90MM LTSHACKLE INSULATOR 4 NO 54.62 218.48 46.29 185.15
16 Aluminium Bobbin. 1 NO 50.75 50.75 43.01 43.01
18 STAY SET WITHOUT STAY WIRE16mm Paint11KV 1 NO 592.97 592.97 502.52 502.52
20 Stay clamp LT/Pair 2 NO 326.97 653.94 277.09 554.19
INCIDENTIAL CHARGES 0.075 3311.41
S.NO SERVICES UNIT QTY GST+RATE TOTAL Ex.RATE TOTAL
2 Tree cutting Km.
3 Approach Clearance Km.
5 Shifting of materials to pole pits No. 1 68.04 68.04 57.66 57.66
6 Stay pit digging No. 1 324.64 324.64 275.12 275.12
7 Transportation of pole from road side to pole pit for a lead of 1 Km. No. 1 335.83 335.83 284.60 284.60
8 Fixing of LT 5 Pin cross arm with insulator No. 3 81.54 244.62 69.10 207.30
9 Pole erection complete with earthing No. 1 868.97 868.97 736.42 736.42
11 Stay erection complete No. 1 223.89 223.89 189.74 189.74
12 Painting of cross arm, pole and numbering of poles No. 1 447.78 447.78 379.47 379.47
13 Diamond guarding Pair 0 68.04 0.00 57.66 0.00
16 Transporation charges LS 1 1000.00 1,000.00 847.46 847.46
17 Dismentaling charges ls 1 1000.00 1,000.00 847.46 847.46
TENDER AMOUNT 51868.00
Materials for RETURN Estimate for replacement of 02 nos detoriated 11 kv pole LT pole 2 span AB Cable at bajarnag chouk R K nagar under basant vihar zone of City Dn.-1 CSPDCL Bilaspur.
S.NO B43028260491 QTY UNIT GST+RATE TOTAL
MATERIAL RETURNED TO BOARD
1 CAST IRON SCRAP 593.600- KG 39.11 -23215.7
2 ALUMINIUM SCRAP 25.000- KG 102 -2550
TOTAL BILL OF QUANTITY FOR MATERIAL TO BE PROVIDED BY THE CONTRACTOR
S.No Name of Work Estimate No. Work Order & Date Estimate Amount Tender Amount Diff Amount (E-H)
Material Services Total (F+G)
A B C D E F G H I
1 Estimate for replacement of 10 nos. detoriated PCC pole by RS joist LT pole at various location under basant vihar zone of City Dn.-1 CSPDCL Bilaspur. B43028260459 1913/27.08.2026 199,290.50 129,395.55 21,282.03 150678 48,612.91
Estimate for replacement of 0.24 KM burn AB LT cable at sheela vihar R K NAGAR under basant vihar zone of City Dn.-1 CSPDCL Bilaspur. B43028260413 1735/17.08.2026 92,492.58 62,456.05 6,863.27 69319 23,173.26
4 Estimate for replacement of 02 nos detoriated 11 kv pole LT pole 2 span AB Cable at bajarnag chouk R K nagar under basant vihar zone of City Dn.-1 CSPDCL Bilaspur. B43028260461 1750/17.08.2026 72,450.92 47,463.59 4,404.41 51868 20,582.92
MATERIAL RETURNED TO BOARD
S.NO MATERIALS QTY UNIT GST+RATE TOTAL
1 ALUMINIUM SCRAP Cable 30.000- KG 102 -3060
2 CAST IRON SCRAP RSJ 1559.56- KG 39.11 -60994
3 ALUMINIUM SCRAP Cable 25- KG 102 -2550
5 CAST IRON SCRAP 593- KG 39.11 -23215.7
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
source.json
RAW_JSON • 0.01 MB
260740-NIT_TD108603.pdf
pdf • 0.32 MB
260741-BOQ_TD108603.xlsx
xlsx • 0.03 MB
260742-TENDER_DOC_TD108603.pdf
pdf • 0.85 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .