| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAdmitted-Finance | ₹1.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹2.0 Cr+₹24.9 L (13.9%)Admitted-Finance NA | ₹2.0 Cr+₹24.9 L (13.9%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | Rejected-Technical Not Technically Qualified |
| Sl No | Description | Qty | Unit | M/S VIR BAHADUR YADAV L1 | Wood Stone Constructions L2 |
|---|---|---|---|---|---|
| 1.00 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. All kinds of soil | 28.32 | Cum | 200 ₹5,664 Lowest | 205.16 ₹5,810.13 |
| 2.00 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | 2.83 | Cum | 150 ₹424.5 Lowest | 154.47 ₹437.15 |
| 3.00 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | 1.16 | Cum | 4,000 ₹4,640 Lowest | 5,368.47 ₹6,227.43 |
| 4.00 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: All works above plinth level upto floor V level. | 269.82 | Cum. | 8,000 ₹21,58,560 | 7,770.88 ₹20,96,738.84 Lowest |
| 5.00 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars | 36,964.63 | Kg | 80 ₹29,57,170.4 Lowest | 84.99 ₹31,41,623.9 |
| 6.00 | Centring and shuttering including strutting,ropping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | 2.56 | Sqm | 200 ₹512 Lowest | 309.05 ₹791.17 |
| 7.00 | Centring and shuttering including strutting,ropping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | 35.26 | Sqm | 600 ₹21,156 Lowest | 663.96 ₹23,411.23 |
| 8.00 | Centring and shuttering including strutting,ropping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts | 334.08 | Sqm. | 600 ₹2,00,448 Lowest | 757.59 ₹2,53,095.67 |
| 9.00 | Centring and shuttering including strutting,ropping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers | 993.74 | Sqm. | 600 ₹5,96,244 | 580.35 ₹5,76,717.01 Lowest |
| 10.00 | Centring and shuttering including strutting,ropping etc. and removal of form for Suspended floors, roofs, landings, balconies and access | 675.16 | Sqm. | 600 ₹4,05,096 Lowest | 730.76 ₹4,93,379.92 |
Tender Value
₹2.3 Cr
EMD Value
₹4.6 L
Closing Date
27 Apr 2026, 5:00 pmClosed
General Manager
Office of Chief General Manager, Construction Wing, Uttarakhand Peyjal Nigam, Kamla Nagar(Opp. ONGC Hospital), Dehradun
CONSTRUCTION OF PROPOSED TYPE II AND TYPE-III RESIDENTIAL QUARTER ABOVE EXISTING BUILDING AT INDIA RESERVE BATTALION-II DEHRADUN EAST HOPE TOWN (PLOT- 2), UTTARAKHAND
2026_MDPEY_93945_1
1266/Nivida(Garh)D.Dun/31 Dt 06/04/2026
Open Tender
Civil Works
Item Rate
365 days
DEHRADUN EAST HOPE TOWN (PLOT- 2)
Please refer tender document
3 documents required · 3 mandatory
₹5,900
PM, Const.Unit, UKPJN, Dehradun
₹4.6 L
Dehradun
18 May 2026
8 Apr 2026
28 Apr 2026
8 Apr 2026
27 Apr 2026
14 Apr 2026
9 Apr 2026 - 10 Apr 2026
13 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. All kinds of soil | - | Cum | - | - |
| 2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. | - | Cum | - | - |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) | - | Cum | - | - |
| 4 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: All works above plinth level upto floor V level. | - | Cum. | - | - |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars | - | Kg | - | - |
| 6 | Centring and shuttering including strutting,ropping etc. and removal of form for Foundations, footings, bases of columns, etc. for mass concrete | - | Sqm | - | - |
| 7 | Centring and shuttering including strutting,ropping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. | - | Sqm | - | - |
| 8 | Centring and shuttering including strutting,ropping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts | - | Sqm. | - | - |
| 9 | Centring and shuttering including strutting,ropping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers | - | Sqm. | - | - |
| 10 | Centring and shuttering including strutting,ropping etc. and removal of form for Suspended floors, roofs, landings, balconies and access | - | Sqm. | - | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.44 MB
BOQ_111189.xls
BOQ • 0.47 MB
Tendoc_1266.pdf
Tender Documents • 3.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .