| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹35.9 LAccepted-AOC | ₹35.9 L | L1 | Accepted-AOC agreement executed |
| 2 | L2₹37.5 L+₹1.6 L (4.44%)Rejected-Finance | ₹37.5 L+₹1.6 L (4.44%) | L2 | Rejected-Finance reject |
| 3 | Rejected-Technical KOLATH NILAPOLA P O | KERALA | - | - | Rejected-Technical reject |
| 4 | Rejected-Technical | - | - | Rejected-Technical reject |
| Sl No | Description | Qty | Unit | Simon P.J. L1 | JACOB GEORGE L4 | REJI THOMAS JOSEPH L3 | Xavier Oommen L2 |
|---|---|---|---|---|---|---|---|
| 1.00AMRUT-2.0 Poovakattuchira | |||||||
| 1.00 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | 108 | sqm | 347.16 ₹37,493.28 Lowest | 386 ₹41,688 | 386 ₹41,688 | 362.6 ₹39,160.8 |
| 1.00 | 2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil | 25.92 | sqm | 120.64 ₹3,126.99 Lowest | 134 ₹3,473.28 | 134 ₹3,473.28 | 126 ₹3,265.92 |
| 1.00 | 4.1.6:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded
stone aggregate 40 mm nominal size derived from natural sources) | 6.48 | cum | 7,519.75 ₹48,727.98 Lowest | 8,364 ₹54,198.72 | 8,364 ₹54,198.72 | 7,853 ₹50,887.44 |
| 1.00 | 4.4.1:Providing and laying cement concrete in kerbs, steps and the like at or near ground level excluding the cost of centering, shuttering and finishing.1:1½:3 (1 Cement: 1½ coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 19.44 | cum | 8,774.98 ₹1,70,585.61 Lowest | 9,760 ₹1,89,734.4 | 9,760 ₹1,89,734.4 | 9,164 ₹1,78,148.16 |
| 1.00 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 60.48 | cum | 8,303.14 ₹5,02,173.91 Lowest | 9,235 ₹5,58,532.8 | 8,500 ₹5,14,080 | 8,671 ₹5,24,422.08 |
| 1.01 | 11.20.1:Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard, jointed with neat cement slurry mixed with pigment to match the shade of tiles, including rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar 1:4 ( 1 cement : 4 coarse sand).Light shade pigment using white cement | 520.5 | sqm | 1,390.1 ₹7,23,547.05 Lowest | 1,546 ₹8,04,693 | 1,450 ₹7,54,725 | 1,451.91 ₹7,55,719.16 |
| 1.01 | 10.28:Providing and fixing stainless steel (Grade 304) railing made of Hollow tubes, channels, plates etc., including welding, grinding, buffing, polishing and making curvature (wherever required) and fitting the same with necessary stainless steel nuts and bolts complete, i/c fixing the railing with necessary accessories & stainless steel dash fasteners, stainless steel bolts etc., of required size on the top of the floor or the side of waist slab with suitable arrangement as per approval of Engineer-in-charge, (for payment purpose only weight of stainless steel members shall be considered excluding fixing accessories such as nuts, bolts, fasteners etc.) | 2,000 | kg | 690.23 ₹13,80,460 Lowest | 767 ₹15,34,000 | 767 ₹15,34,000 | 720.94 ₹14,41,880 |
| 1.01 | 30.2.10.1:Grassing with selection No. 1 grass including watering and maintenance of the lawn for 60 days or more till the grass forms a thick lawn, free from weeds and fit for mowing including supplying good earth, if needed (the grass and good earth shall be paid for separately).In rows 5 cm apart in both directions | 1,200 | sqm | 23.57 ₹28,284 Lowest | 26 ₹31,200 | 26 ₹31,200 | 25 ₹30,000 |
| 1.01 | 30.2.13:Preparation of beds for hedging and shrubbery by excavating 60 cm deep and trenching the excavated base to a further depth of 30 cm, refilling the excavated earth after breaking clods and mixing with sludge or manure in the ratio of 8:1 (8 parts of stacked volume of earth after reduction by 20% : one part of stacked volume of sludge or manure after reduction by 8%), flooding with water, filling with earth if necessary, watering and finally fine dressing, leveling etc. including stacking and disposal of materials declared unserviceable and surplus earth by spreading and leveling as directed, within a lead of 50 m, lift up to 1.5 m complete (cost of sludge, manure or extra earth to be paid for separately). | 250 | cum | 296.74 ₹74,185 Lowest | 330 ₹82,500 | 330 ₹82,500 | 309 ₹77,250 |
Tender Value
₹39.9 L
EMD Value
₹50,000
Closing Date
10 Sept 2025, 5:00 pmClosed
Krishnakumar
The Assistant Engineer, LIDEW Section,Changanassery Municipality
AMRUT-2.0 Poovakattuchira Municipal park-in changanassery muncipality
2025_LSGD_792979_10
1/2025-26/EE/LIDEW/CMC
Open Tender
Civil Works - Others
Item Rate
180 days
Changanassery Municipality
Please refer Tender documents.
9 documents required · 9 mandatory
₹2,760
Yes
₹50,000
Yes
31 Oct 2025
30 Aug 2025
12 Sept 2025
30 Aug 2025
10 Sept 2025
30 Aug 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1309247.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .