Tender Value
Refer Docs
EMD Value
₹20,000
Closing Date
26 Sept 2026, 3:00 pm4d left
General Manager
Sarjoo Sahkari Chini Mills ltd, Belrayan Kheri
BELRAYAN Making a partition wall in equalization tank for ETP
2026_SSCML_1187799_1
560/GM/2026-27
Open Tender
Miscellaneous Works
Item Rate
45 days
Sarjoo Sahkari Chini Mills ltd, Belrayan Kheri
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Sarjoo Sahkari Chini Mills ltd, Belrayan Kheri
₹20,000
19 Sept 2026
19 Sept 2026
26 Sept 2026
19 Sept 2026
26 Sept 2026
19 Sept 2026
19 Sept 2026 - 26 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic) excavator)/manual means foundation trenches or drains (not exceeding 1.5 m in wisth or 10 sqm on plan), excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. including dressing of sides and ramming of bottoms, for all lift up to 1.5 m. including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. (DSR No. 2.8.1) | 30.24 | M3 | 195.07 | ₹5,898.92 |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering – All work up to plinth level.
1:5:10 with stone aggregate (1 cement : 5 coarse sand (zone-III) : 10 graded stone aggregate 40mm (nominal size) (DSR No. 4.1.10) | 4.32 | M3 | 4,885.23 | ₹21,104.19 |
| 3 | Rainforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings balconles, shelves, chajjas, lintals bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level. Excluding the cost of centering shuttering finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) 3 graded stone aggregate 20mm nominal size) (DSR No. 5.3) | 45.37 | M3 | 8,622.56 | ₹3,91,205.55 |
| 4 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.
Cold twisted bars. (D.S.R. No. 5.22.3) | 35.61 | Qtls | 8,082 | ₹2,87,800.02 |
| 5 | Centering and shuttering including strutting, propping etc and removal of form for
Foundations. Footings, bases of columns, etc. for mass concrete. (D.S.R. No. 5.9.2) | 235.2 | M2 | 631.39 | ₹1,48,502.93 |
| 6 | Steel rebaring work for existing R.C.C. slab using chemical anchering including drilling, cleaning fixing of reinforcement bars, cutting, bending and txing complete. | 80 | Nos | 500 | ₹40,000 |
| 7 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in.
Cement mortar 1:6 (1 cement : 6 coarse sand) (D.S.R. No. 6.1.2) | 4.83 | M3 | 6,824.27 | ₹32,961.22 |
| 8 | 12 mm cement plaster of mix :
1.6 ( 1 cement: 6 coarse sand) (D.S.R. No. 13.4.2) | 9.27 | M2 | 257.53 | ₹2,387.3 |
| 9 | Supply and filling in plinth with sand under floors including watering, ramming consoliding and dressing complete. (D.S.R. No. 2.27) | 11.4 | M3 | 1,591.6 | ₹18,144.24 |
| 10 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and reinforcement all work upto plinth level.
1:2:4 (1 cement, 2 coarse sand & 4 graded stone aggregate 20mm (nominal size) (D.S.R. No. 5.1.3) | 2.16 | M3 | 6,432.65 | ₹13,894.52 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.57 MB
BID.pdf
Tender Documents • 2.42 MB
BOQ_2236953.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .