Extension of HT LT line with installation of Transformer for providing service connection at different area under the jurisdiction of ESD Jubarajnagar
2024_POWER_45625_1
NIT/DGM/ED-DMR/23-24/08
Open Tender
Electrical Works
Turn-key
90 days
O/O DGM ED Dharmanagar
As per NIT
3 documents required · 3 mandatory
₹2,000
₹14,818
O/O DGM ED Dharmanagar
24 Jan 2024
6 Jan 2024
17 Jan 2024
6 Jan 2024
16 Jan 2024
6 Jan 2024
6 Jan 2024 - 9 Jan 2024
10 Jan 2024
Amount
SCHEDULE-A Supply
8 mtr Long PCC pole
9 mtr Long PCC pole
Stay set Complete
Stay wire 7/2.5mm
Stay insulator(LT)
Stay insulator(HT)
M.S. CHANNEL(100x50x50x6) mm Channel
M.S. CHANNEL (75x40x40x6) mm Channel
M.S. ANGLE (65x65x6) mm Angle
MS Angle 50X50X6 mm
ACSR (6/1/2.59mm)
8 SWG GI wire
LT Shackle insulator
Straps with Nuts & Bolts
LT spacer
Febricated clamps of assorted size of MS flat (50 x 6 mm) with double coat of red oxide primercoating
M.S.Nuts & Bolt i/c Washer of assortedsize ISI Marked machine made(ISI marked machine made)
25 KVA, 11KV/0433KV Distribution Transformer
PVC CABLES (SINGLE CORE) 16 mm2
PVC CABLES (SINGLE CORE) 70 mm2
Rewireable Porcelain Cut out 63 Amp
Rewireable Porcelain Cut out 100 Amp
11KV Polymer composite 45 KN Disc Insulator
11KV Disc fittings Up to 7/3.8mm, 2-U Bolt type
11KV Polymer Pin Insulator
LIGHTINING ARRESTOR 9 KV, 5KA Polymeric L/A
11 KV, 200 Amps GOS 3-phase.
11 KV DOF Set, 3-phase
2.5mtr. Long , 40mm dia G.I.Pipe Make: TATA/ JINDAL)
60Kg Salt & 55Kg Charcoal ( For 1 Pit).
Danger plate (HT)
SCHEDULE-B Erection
Erection of 9.00 mtrs length of PCC pole at any kind of soil upto a depth of 1/6th of pole height , i/c excavation of earth , refilling the pit with soil upto the ground level, ramming and making complete in all respect .
Erection of 8.00 mtrs length of PCC pole at any kind of soil upto a depth of 1/6th of pole height , i/c excavation of earth , refilling the pit with soil upto the ground level, ramming and making complete in all respect .
Erection of stay set direct in earth complete with 19mm X 1800mm long stay rod , anchor plate of size 300X300x8 mm , thimble, turn buckle, 7/2.5mm dia GI stranded stay wire and stay insulator etc.with supply of MS clamp, nuts 7 bolts etc as required and making complete in all respect .
Laying and Stringing of ACSR 6/1/2.59 mm dia WEASEL including hoisting and binding etc. Complete as required.
Laying & strining of 8SWG GI wire including hoisting & binding etc. Complete as required
Spaceing of conductor of single/two/three phase for 2 wire LT line with the help of spacer
MS Angle cross arm bracket of 4 wire upto 1.1 mtr long by 50 x50X6 mm MS Angle
Erection of M.S.Angle Cross-Arm,1.0 to 2.5 Mtr.Long 65 x65 x 6 mm
Erection of M.S.Channel Cross-Arm,0.3 to 1.2 Mtr.Long75 x40 x 40 x 6 mm
Erection of M.S.Channel Cross-Arm,1.3 to 2.8 Mtr.Long75 x40 x 40 x 6 mm
Erection of M.S.Channel Cross-Arm,0.6 to 2.8 Mtr.Long100 x50 x 50 x 6 mm
Erection of M.S.Channel Cross-Arm exceeding 2.8Mtr. Long 100 x50 x 50 x 6 mm
Erection of 11KV Pin insulator along with Pin.
Erection of Disc insulator Set for 11KV line along with necessary fittings
Erection of 9KV,5KA single pole metal oxide gapless type LA , including necessary connection complete as per technical specification
Erection of 11KV DOF unit set of three nos. including necessary connection complete as per technical specification.(Excluding the cost of back clamp, Nuts & Bolts)
Erection of 11KV 200 Amp. GOS unit set of Two nos. including necessary connection complete as per technical specification.(Excluding the cost of back cIamp,Nuts & Bolts)
Installation/Positioning of 11/0.430KV,3-Phase 25KVA of Distribution Transformer on Pole with necessary connections & fitting fixing of all allied accessories components as required for making complete in all respect for energizing.
Providing Three Phase Service Connection with laying PVC cable from nearby Electrical pole to Premises upto 35mtr. in length supported by G.I.Wire,Reel Insulator i/c fitting fixing of Energy Meter as required
Providing protective Sub-Station fencing of approve quality as per technical specification i/c supply of all materials.
LT Shackle insulator with straps nuts & bolts
Earthing with G.I pipe 2.5mtr. Long and 40mm dia, including excavation, refilling with alternate layer of salt & Charcoal as per drawing (excluding supply of G.I.Pipe, Salt & Charcoal, Gi wire, nuts &boIts, etc. as required)
Maintaining adequate clearance from overhead live conductors by Trimming of tree branches/jungle cutting/bamboo for Way Leaves
Febrication of MS Channel/angle
Re-Stringing of ACSR conductors
Re-Stringing of 8 SWG GI Wire
Re-adjustment of stay set complete
Numbering of errected poles & DT by Black japan paint on yellow background
Erection of Danger plate on OH lines (11KV/415 volts)
SCHEDULE-C Carriage of 11/0.430, 3-Phase 25KVA by Mechanical Transport from the Site /Store/Worshop to working site Vis-a-vis including loading, unloading and placing on base, as required,a) Upto the lead range 25KM From Sub Division Store to site
a) Upto the lead range 25km
SCHEDULE-D Carriage of 9.0mtr. Length of PCC poles by Mechanical Transport from the factory / Sub-divisional store to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM For maximum 04(four) poles
SCHEDULE-E Carriage of 8.00 mtr. Length of PCC poles by Mechanical Transport from the factory / Sub-divisional store to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM (for max. 5nos. Poles)
b) Beyond 05(five) poles
SCHEDULE-F Carriage of G.O.S., D.O.F. L. A. etc. by Mechanical Transport from factory /the Sub-Divisional store yard to working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM
SCHEDULE-G Carriage of materials such as cable, AAC, AAAc, ACSR, GI wire, cross-arm, stay set, insulators etc. by Mechanical Transport from factory / the Sub-Divisional store yard to working site Vis-à-vis i/c. loading, unloading and stacking as required :-PCC poles by Mechanical Transport from the Sub-Divisional store yard working site Vis-à-vis i/c. loading, unloading and stacking as required :-
a) Upto the lead range 25 KM
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .