| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹87.1 LAccepted-AOC | ₹87.1 L | L1 | Accepted-AOC Below Estimate rate |
| 2 | L2₹88.6 L+₹1.5 L (1.70%)Rejected-AOC | ₹88.6 L+₹1.5 L (1.70%) | L2 | Rejected-AOC Above Estimate rate |
| 3 | L3₹89.7 L+₹2.6 L (3.02%)Rejected-AOC | ₹89.7 L+₹2.6 L (3.02%) | L3 | Rejected-AOC Above Estimate rate |
Tender Value
₹88.0 L
EMD Value
₹1.8 L
Closing Date
3 Jan 2024, 3:00 pmClosed
District Collector/Chairman
202, 2nd Floor, DRDA, Collectorate, Karur
Retender - Karur District - Periodic Renewal with Five Years Maintenance of PMGSY roads - 2022-23 - Package No.TN0746R - 2 Nos
2023_RDTN_126717_9
DIPR/3802/Tender/2023
Open Tender
Civil Works - Roads
Item Rate
90 days
202, 2nd Floor, DRDA
Please refer Tender documents.
8 documents required · 8 mandatory
₹0
₹1.8 L
202, 2nd Floor, DRDA, Karur
22 May 2024
25 Dec 2023
3 Jan 2024
25 Dec 2023
3 Jan 2024
25 Dec 2023
26 Dec 2023
Amount
1.Renewal to the road from Thennilai kumaravalasu to Velliyan kattur road Km 0/0-1//920
Clearing and Light Jungle including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm in thickness as per Technical Specification clause 201.
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 A
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Advance patch work for making up the undulation in the existing in the existing BT surface to an average thickness of 25mm using 13.20mm HBG metal
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.2 to 0.25 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
Providing and laying bituminoua concrete with 100-120 TPH batch type HMP producing an average output of 75 tonne per hour using crushed aggregates of specified grading,premixed with bituminous binder @5.4 to 5.6 percent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment,rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT & H speciications clause 507 complete in all respects
Road Making with Hot Applied Thermoplastic Compound with reflectorising Glass Beads on Bitumen Surface
Painting Citizen Information board
Painting Name Board
Road studs with lens
Towards Cautionary Sign board
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
2.Renewal to the road from Thennali Kumaravalasu road to Avithupalayam Km 0/0-2//910
Clearing and Light Jungle including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm in thickness as per Technical Specification clause 201.
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 A
Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc, complete.
Advance patch work for making up the undulation in the existing in the existing BT surface to an average thickness of 25mm using 13.20mm HBG metal
Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.2 to 0.25 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
Providing and laying bituminoua concrete with 100-120 TPH batch type HMP producing an average output of 75 tonne per hour using crushed aggregates of specified grading,premixed with bituminous binder @5.4 to 5.6 percent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment,rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT & H speciications clause 507 complete in all respects
Road Making with Hot Applied Thermoplastic Compound with reflectorising Glass Beads on Bitumen Surface
Painting Citizen Information board
Painting Name Board
Road studs with lens
Towards Cautionary Sign board
Towards Km stone
Towards Hm stone
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
APPU CONSTRUCTION
Sri Ranganathar Constructions (P) Ltd
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .