Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹14.6 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹15.2 L+₹64,362.94 (4.42%)Admitted-Finance | L2 | Admitted-Finance |
Tender Value
₹17.3 L
EMD Value
₹34,000
Closing Date
19 Nov 2026, 11:00 amClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
DGM (Civil)
Cochin Shipyard Ltd. Perumanoor (PO), Kochi 682015
Work involves dismantling of existing fencing, gate etc. and construction of a compound wall incl block work, plastering, painting, finishing, providing gate, fencing renewal repair, painting the top surface of tank incl pointing, painting, PCC etc.
2026_CSL_293782_1
Upkeep of No.2 fresh water tank, construction of compound wall and associated works.
Open Tender
Civil Works
Works
90 days
CSL, Kochi
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹34,000
26 Nov 2026
30 Oct 2026
20 Nov 2026
30 Oct 2026
19 Nov 2026
30 Oct 2026
90 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling and removing existing chain link fencing comprising GI chain link mesh , MS angles / GI pipe posts, struct, stay wires, nut, bolt clamp, and all other accessories around posts if necessary, dismantling PCC foundations, stacking the recovered material at a location within 50 m lead as directed by the Engineer-in-charge. | 280 | m2 | 79 | ₹22,120 |
| 2 | Demolishing cement concrete work manually or by mechanical means including disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | 3 | m3 | 2,547 | ₹7,641 |
| 3 | Demolishing R.C.C. work manually / by mechanical means including stacking of steel bar sand including disposal of dismantled or waste materials by mechanical means, including loading, transporting, unloading as per direction of Engineer-in-charge. | 2 | m3 | 3,720 | ₹7,440 |
| 4 | Dismantling of steel gate of any size including shutters, frames, holdfast, hinges, locking arrangement etc.complete including cutting of welded members stacking of serviceble materials and disposal of unserviceble materials as per the direction of Engineer-in Charge. | 650 | kg | 5 | ₹3,250 |
| 5 | Earthwork in excavation by manual means in foundation trench for compound wall in all kind of soil over areas exceeding 30 cm in depth and 1.5m in width as well as 10 sqm on plan including cutting and removal of tree roots of all size encountered during excavation and disposal of excavated earth lead upto 50 m and for all lift as directed by Engineer in charge. | 43 | m3 | 549 | ₹23,607 |
| 6 | Providing and laying in position plain cement concrete 1:4:8 (one cement, four quarry sand and eight 40 mm nominal size hard granite broken stone) including centering, shuttering mixing, laying, compacting, all labour charges, cost and conveyance and delivery, handling, unloading, storing of all materials complete as directed by Engineer-in-Charge. | 5 | m3 | 7,532 | ₹37,660 |
| 7 | Filling available excavated earth in trenches, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering including bailing out water, all labour charges, cost and conveyance of plants and transporting earth from CSL permises within a lead of 500 m complete as per the direction of the Engineer-in-charge. | 21 | m3 | 200 | ₹4,200 |
| 8 | Providing and laying in position reinforced cement concrete 1:1.5:3 (one cement, one and half quarry sand and three 20mm nominal size hard granite broken stone) including centering, shuttering, mixing, laying, compacting, all labour charges, cost and conveyance and delivery, handling, unloading, storing of all materials etc. complete as directed by Engineer-in-Charge. | 17 | m3 | 11,864 | ₹2,01,688 |
| 9 | Supplying, fabrication and fixing in position TMT reinforcement bars of grade Fe 500D of various diameters for RCC work including straightening, cutting, bending, binding with 22 SWG GI wires and providing concrete cover blocks, all complete . (Rate is inclusive of cost of 22g binding wire.) | 820 | kg | 92 | ₹75,440 |
| 10 | Provide Solid block masonry using pre cast solid blocks (Factory made) of size 30x20x15cm or nearest available size confirming to IS 2185 Part I of 1979 for super structure up to floor two level thickness 20cm and above in: CM 1:5 ( 1 cement : 5 coarse sand) including cost of all materials, labour, transportation, unloading and scaffolding etc complete (including costs of cement). | 34 | m3 | 9,465 | ₹3,21,810 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.11 MB
TenderDocs.pdf
Tender Documents • 3.33 MB
G-C-C.pdf
Other Document • 1.70 MB
BOQ_344681.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart shows the information on this page on a best-effort basis and does not guarantee that it is accurate, complete or current. Check it against the buyer's official notice and documents before you act on it; the official record prevails. TenderKart is not liable for any loss or claim arising from the use of this information. If you notice any error or omission, please let us know at .