Tender Value
₹6.9 Cr
EMD Value
₹6.9 L
Closing Date
30 Jul 2026, 5:00 pm
Executive Engineer, Gir Somnath Irrigation Division, Veraval Ishvar Complex, 3rd Floor, A-Wing, Opp. Reliance Mall, Veraval-Junagadh Road, Veraval-362265
Construction of Coastal Protection Work At Village Saiyad Rajpara In Una Taluka Of Gir Somnath District.
319623
Tender Notice No-10 2026-27
Open
Civil - All
Gir Somnath
8 documents required · 8 mandatory
₹12,000
Executive Engineer, Gir Somnath Irrigation Division,Veraval
₹6.9 L
1 Jul 2026
1 Jul 2026
1 Jul 2026
30 Jul 2026
1 Jul 2026
(Bill of Quantities)
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr. )
Item Description of Item (with brief Quant Unit Rate In Amount
No specification and reference to book of ity figures
specifications)
Supplying & Laying trap rubble stone 50 to100
Kg .in weight for toe and core filling including
conveying and stacking to required line level
Slopes section including all leads and lifts.
Conveying material from stacks and laying etc.
Supplying & Laying trap rubble stone 20 to100
Kg .in weight for toe and core filling including
conveying and stacking to required line level
Slopes section including all leads and lifts.
Conveying material from stacks and laying etc.
Supplying & Laying trap rubble stone 500 to
1000Kg. In weight for toe and core filling
including conveying and stacking to required
line level Slopes section including all leads and
lifts.Conveying material from stacks and laying
etc. complete. Rate analysis for 1 cum.
Supplying & Laying trap Rubble Stone 2.0 to
3.0 tone in weight for toe&core filling including
conveying and stacking to required line, level,
slope section including all leads & lifts
conveying materials from stacks and laying
etc. completely.
5 Casting design mix M30 grade PCC 3269.00 Cum 8625.63
tetrapods/dollose weighing upto 25 tonne
using minimum cement 405 kg/cum and
graded crushed stone aggregates 40mm
nominalmaximum size for laying in section of
breakwater or such other structure including
cost of formwork, admixture (superplasticizer)
@ 0.4 % of weight of cement, vibrating, curing,
finishing etc. Complete.
Labour charges for placing of CC
Tetrapods/Dollose/blocks weighing upto
tonne in the section of breakwater or such
other structure, laying in position as shown in
the drawing or as directed includingloading at
casting yard, transporting, unloading at work
site and all labour, machinery such as cranes,
dumpers, trucks, trailers etc. Complete.
Provision for Mobilization and Demobilization
of All Required Construction Machinery,
Equipment, and Ancillary Facilities for harbour
project works such as jetty, wharf, breakwater
etc. (5% of total estimated cost)
Excavation in all sort of strata and formations
including depositing the unuseful excavated
stuff as and where directed including sorting
and stacking useful materials as directed up to
200 Mt. lead and all lift etc. complete including
dewatering. (a) In overburden including Hard
Providing & Laying in position 'NOMINAL MIX'
cement concrete using cement sand and
crushed aggregate by machine mix incl.
necessary formworks, centering, scaffolding
compaction by mechanical vibrator curing as
directed with all lead & lift etc D) Concrete
grade 1:2:4 and MSA-40mm(Graded)
Drilling 25mm dia holes at distance as
specified and depth upto 3.0mt for check dam
foundation & fixing anchor bars of specified
diameter with cement grout incl cleaning holes
as directed etc, (excluding cost of bars.)
Providing, cutting, bending, binding and fixing
in position as per drawing. TMT BAR,
reinforcement for R.C.C. works and anchor
bars including cost of black annealed 16 to
BWG M.S. Wire etc. complete with all lead and
Back filling with appropriate excavated
material behind the structures or refilling the
trenches with excavated useful material
including watering ramming, consolidation etc
complete with all lead and lift.
Providing and fixing in position 100/110 mm
dia PVC Pipe weep holes in the retaining
walls./side wall/abt etc
I/We am/are willing to carry out the work at ......................% above/below percent(Should
be written in figures and words) of the estimated rate mentioned above. Amount of
my /our tender works out as under.
Estimated amount put totender Estimated amount put totender
Deduct………% below Add ........ % Above
In words In words
(B) For Item Rate Tender (For above INR 50 Cr.):
Item Description of Item Quantity Unit Rate Amount
No (with brief specification
and reference to book of In In
specifications) figures Words
(A) Total Tendered Amount
(B) Rebate on above tendered amount (if any) % (in figure)
(C) Net Tendered Amount (A-B) (in figure) ………………………………
1 #The Contractor shall exhibit a board with brief details of work as directed by the
Engineer-In-Charge for which no extra payment shall be made.
2 The labour cess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore i n
R.C.C. items where there is a change as per actual mix design the cost of difference of
cement consumption have been deducted from the rate of original item at the rate of
input rate mentioned in all the tender.
Signature of Contractor Executive Engineer
Gir Somnath Irrigation Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1a.SBD Saiyad Rajpara - Part-1.pdf
1b.Technical Specification - Part-2.pdf
1c.Itemwise Detailed Specification - Part-3.pdf
BOQ.pdf
Drawing.pdf
Tender Notice No 10 of 2026-27.pdf
Download all tender documents and submit your bid