Tender Value
₹7.7 L
EMD Value
₹8,000
Closing Date
30 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Executive Engineer, Panchayat (R&B) Division, Tapi
Nucleus Budget 2025-26. Construction of Compound Wall in Sarkari Uchchtar madhyamik shala at Village Lakhali Ta.Vyara Dist.Tapi.
298614
31 OF 2025-26
Open
Civil Works - Buildings
Tapi
6 documents required · 6 mandatory
₹900
Executive Engineer, Panchayat (R&B) Division, Tapi-Vyara
₹8,000
23 Apr 2026
23 Apr 2026
23 Apr 2026
30 Apr 2026
23 Apr 2026
Name of Work:- Nucleus Budget 2025-26. Construction of Compound Wall in Sarkari Uchchtar
madhyamik shala at Village Lakhali Ta.Vyara Dist.Tapi.
: : BILL OF QUANTITY.' : :
Percentage Rate Tender
It. Description of Item (with brief Specification Rate In
Quantity Unit Amount
No. and reference to book of specifications) Figures
1 Excavation for foundation upto 1.5 m depth 78.30 Cum. 262.52
including sorting out and stacking of useful
materials and disposing off the excavated stuff
upto 50 Meter lead.(C) Hard Murrum
2 Filling available excavated earth (excluding rock 39.15 Cum. 133.66
in trenches plinth, slides of foundations etc. in
layers not exceeding 20 cm in depth
consolidating each deposited layer by ramming
3 Providing and laying cement concrete 1:2:4 (1- 6.53 Cum. 3786.47
Cement : 2- Coarse sand : 4- graded stone
aggregates 20 mm nominal size) and curing
complete excluding cost of formwork in (A)
Foundation and Plinth (more than 10 ton)
4 Providing and laying controlled cement concrete 15.88 Cum. 4333.91
M.200 and curing complete excluding the cost of
formwork and reinforcement for reinforced
concrete work in (A) Foundations, footings, Base
of columns and Mass concrete. (more than
5 Providing and laying controlled cement concrete 1.00 Cum. 10222.21
M-200 and curing complete including the cost of
form work but excluding cost of reinforcement
for reinforced concrete work for Column upto
6 Providing and laying controlled cement concrete 5.26 Cum. 6377.14
M.200 and curing complete excluding the cost of
formwork and reinforcement for reinforced
concrete work in (D) Columns, Pillars posts and
struts, upto floor two level. (more than 10 ton
7 Brick work using common burnt clay building 5.26 Cum. 4121.55
brick having crushing strength not less than
kg/sq. cm. in foundation and plinth in cement
mortar 1:6 ( 1 Cement: 6 fine sand) (B)
8 Providng TMT bars renforcement of FE 500/500D 3296.00 kg 77.29
for R.C.C. work including bending binding and
placing in position complete for all floor.
9 Providing and laying controlled cement concrete 4.00 Cum. 6377.14
M.200 and curing complete excluding the cost of
formwork and reinforcement for reinforced
concrete work in (D) Columns, Pillars posts and
struts, upto floor two level. (more than 10 ton)
10 Brick work using common burnt clay building 35.10 Cum. 4403.40
brick having crushing strength not less than
kg/sq. cm. in super structure above plinth level up
to floor two level in cement mortar 1:6 (
Cement: 6 fine sand) (B) Convention for G.F
11 Providing 15mm thick cement plaster in single 170.00 Sqmt 172.84
coat on Rough (Similar)side of single or half brick
walls for interior plastering upto floor two level
and finished even and smooth in (ii) Cement
mortar 1:4 (1-cement :4-sand)
12 20 mm thick sand faced cement plaster with on 246.50 Sqmt 337.53
wall upto all height above ground level consisting
12 mm thick backing coat of c.m. 1:3 (1 cement :
3 sand ) and 8 mm thick finishing coat of cm 1:1
(1 cement : 1 sand) etc. complete.all height etc.
13 Finishing wall with water proofing cement paint of 170.00 Sqmt 117.41
on wall surface ( Two coats) to give an approved
brand manufacture and of requred shape even
shade after throughtly brushing of loose powered
14 Wall painting (two coats) with plastic emulsion 246.50 Sqmt 86.93
paint of approved brand and manufacture with on
undecorated wall surface to give an even shade
including throughly brushing the surface free from
mortar droppings and other foreign matter and
sand papered smooth along ceilings and sloping
I / Weam / are willing to carryout the work at…………………. % above/ below percent (Should Be written in
figures and words) of the estimated rate mentioned above Amount of my / our tender works out as under.
*Estimated amount put to tender *Estimated amount put to tender
Deduct ……. % below Rs…………………… Add ………........% Above
*( please strike out whichever is not applicable)
1 The Contractor shall exhibition board with detailed specification and details of works directed
by the Engineer – In – Charge for which no extra payment shall bemade.
2 The labourcess will be deducted as per prevailing rules i.e. 1% of the work done.
3 GST and Income tax TDS will be deducted at a source while making payments of bills.
4 In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per
Govt G.R.: PRC-10/2017 Cement Consumption/16/C Date: 11/05/2017 as stated in S.O.R.
therefore in R.C.C. items where the reisa change as per actual mix design the cost of
difference of cement consumption have been deducted from the rate of original item at the
rate of input rate mentioned in all the tender.
Executive Engineer
Signature of the contractor Panchayat (R & B) Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SBD Compoundwall Lakhali.pdf
BOQ Compoundwall Lakhali.pdf
Specification.pdf
building booklet.pdf
GRs - SBD with Index.pdf
Download all tender documents and submit your bid