| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.2 LAccepted-AOC | ₹3.2 L | L1 | Accepted-AOC first lowest |
| 2 | L2₹3.7 LAccepted-AOC | ₹3.7 L | L2 | Accepted-AOC secondlowest |
| Sl No | Description | Qty | Unit | VIPIN RAJ N I L1 | Suresh Kumar K C L2 |
|---|---|---|---|---|---|
| 1.00Estimation | |||||
| 1.00 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 60 | sqm | 16 ₹960 | 17.29 ₹1,037.40 |
| 1.00 | OD262632/2025-2026:Hire charges for Hydraulic Excavator for removing tree stump and cleaning the garbages dumped on the yard as directed by engineer in charge | 8 | hour | 1,150 ₹9,200 | 1,298.39 ₹10,387.12 |
| 1.00 | 15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar | 7.47 | cum | 1,850 ₹13,819.50 | 1,994.96 ₹14,902.35 |
| 1.00 | 5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources) | 2.77 | cum | 8,950 ₹24,836.25 | 10,146.2 ₹28,155.71 |
| 1.00 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | 471.75 | kilogram | 95 ₹44,816.25 | 112.2 ₹52,930.35 |
| 1.01 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | 11.1 | sqm | 650 ₹7,215 | 737.97 ₹8,191.47 |
| 1.01 | 5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 2.83 | cum | 11,900 ₹33,736.50 | 12,355.03 ₹35,026.51 |
| 1.01 | 5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more | 453.6 | kg | 100 ₹45,360 | 108.75 ₹49,329 |
| 1.01 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 37.8 | sqm | 858 ₹32,432.40 | 975.61 ₹36,878.06 |
Tender Value
₹9,742
EMD Value
₹9,742
Closing Date
5 Mar 2026, 5:00 pmClosed
Assistant Executive Engineer
Office of the Assistant Executive Engineer PWD Buildings Sub Division Nedumangad
GENERAL-Construction of compound wall in N G O Q u a r t e r s N e t t a N e d u m a n g a d - Construction of compound wall-General Civil Work
2026_PWD_841325_1
PWD/BLDG/TR/23919/2025_5_1_1/1
Open Tender
Civil Works - Buildings
180 days
Nedumangad
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,015
Yes
₹9,742
Yes
18 May 2026
27 Feb 2026
7 Mar 2026
27 Feb 2026
5 Mar 2026
27 Feb 2026
Estimation
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
OD262632/2025-2026:Hire charges for Hydraulic Excavator for removing tree stump and cleaning the garbages dumped on the yard as directed by engineer in charge
15.7.4:Demolishing brick work manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-Charge.In cement mortar
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.2.2:Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size derived from natural sources)
5.22A.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
50.6.1.8:Solid block masonry using pre cast solid blocks (Factory made) of size 40x20x15cm or nearest available size confirming to IS 2185 part I of 1979 for super structure up to floor two level with thickness 15cm in: CM 1:6 ( 1 cement : 6 coarse sand etc complete
13.1.1:12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.46.1:Finishing walls with Acrylic Smooth exterior paint of required shade:New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm)
2.33.3:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyond 120 cm girth up to and including 240 cm girth
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.04 MB
Declaration.pdf
Other Document • 0.04 MB
viewsbd.pdf
Tender Documents • 1.63 MB
epayment.pdf
Other Document • 0.01 MB
AffidavitForm.pdf
Other Document • 0.26 MB
PreliminaryAgreementcom.pdf
Other Document • 0.28 MB
BOQ_1418725.xls
BOQ • 0.31 MB
Integritypact.pdf
Other Document • 0.09 MB
Download all tender documents and submit your bid