Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Chief General Manager (Thermal)
Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing / Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations. and (B) Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous works at GIPCL - SLPP
355264
SLPP/AHS/BRC/DOZER/2027-29
Open
Power/Energy Projects/Products/Services
Works
Surat
₹2,950
Nani Naroli Surat
₹48,000
16 Oct 2026
16 Oct 2026
16 Oct 2026
5 Nov 2026
16 Oct 2026
documents for Technical Bid in Office of Surat Lignite Power Plant (SLPP)
E-Reverse Auction Will be informed by GIPCL to all qualified Bidders
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
1. Amendment / corrigendum of the Tender Document, forms, schedules, etc. may be
done any time by the GIPCL during the period of publication of Tender on the
website. The Bidders are required to visit the website regularly till the last date &
time of Bid submission.
2. GIPCL reserves the right to reject any or all the tenders without assigning any
reason thereof.
3. The Bidders are required to quote the rate strictly as per the terms and conditions
mentioned in the tender document, adhering to technical specifications as well.
4. The Bidders are required to submit their Bids online only through (n)Procure portal
(https://tender.nprocure.com)
5. The EMD, Tender fee & other supporting documents are to be submitted in physical
form only at the following address:-
Gujarat Industries Power Company Limited,
Surat Lignite Power Plant,
At Village: Nani Naroli,
Taluka: Mangrol, Dist.: Surat - 394 112, Gujarat.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
INSTRUCTIONS TO BIDDERS
1. PLANT SYNOPSIS
Gujarat Industries Power Company Limited (GIPCL) (henceforth be named
Company/GIPCL), is a Premier Power Utility in the State of Gujarat with an installed
capacity of 1859.40 MW comprising of various conventional and renewable projects.
GIPCL commissioned its first power project: a 145 MW gas based combined cycle power
plant in 1992 at Vadodara. It expanded its capacity by 165 MW Neptha and Gas based
Combine Cycle Power Plant at Vadodara in
Surat Lignite Power Plant (SLPP) with four units of 125 MW capacities each is located at
Village: Nani Naroli, Taluka: Mangrol, District: Surat in Gujarat. GIPCL has also operating
its own captive Lignite and Lime Stone Mines close to the Power Plant. The Power Plant is
based on Circulating Fluidized Bed Combustion (CFBC) technology for the Boilers, where
Lignite is burnt along with Lime Stone in the Combustor of the Boiler.
It commissioned 5 MW Solar Power Plant on the Vastan Mine dump top adjacent to Surat
Lignite Power Plant in January 2012. Also, GIPCL has commissioned 1MWp Distributed
Solar Power Projects at two locations in Gujarat viz. at Village: Amrol, Dist.: Anand in April,
2016 and at Village Vastan, Taluka Mangrol, and Dist.: 2016. Surat in May 2016. GIPCL
has successfully commissioned a 2 X 40 MW Solar Project in September 2017 as well as
a 75 MW Solar Power Project in June 2019 at Gujarat Solar Park, Village Charanka, Dist.:
Patan. GIPCL has also successfully commissioned 112.4 MW wind farms at different
location of Gujarat. The Company has commissioned the 100 MW Solar Project at the
Raghanesda Solar Park, Banaskantha, Gujarat on August 2021. The Company has also
commissioned 75 MW Solar project at Vastan Lignite Mine, Tal. Mangrol, Dist. Surat,
Gujarat in June 2025. The Company has also developed 2375 MW Renewable Energy
Park at Khavda in the Kutch district of Gujarat in Dec
Surat Lignite Power Plant (SLPP) is accessible by road from Kim and Kosamba, which are
on Mumbai-Ahmadabad highway. From Kosamba, SLPP is around 32 km, out of which
km is part of the National & State Highway and balance 5 km is District Road. From Kim,
SLPP is around 18 km, out of which 13 km is the State Highway and balance 5 km is District
Road. The nearest Broad Gauge Railway Line is at Kim, which is around 21 km from the
SLPP. Surat is approximately 50 km from the SLPP. Location Map for SLPP is as under:
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
The Company intends to award Biennial Rate Contract (BRC) for (A) Disposal of Ash at pre-
designated locations of Mines pit / any other locations and (B) Cleaning of Areas underneath and
surrounding Fly Ash & Bed Ash Silos (Contract Period: 2027-29) at GIPCL-SLPP: 4 x 125 MW
Power Plant and is therefore inviting e-Tenders online on (n)Procure portal
(https://tender.nprocure.com)from experienced & resourceful Contractors.
2. SCOPE OF WORK
2.1 The Scope of Work covers Hiring of Dozer D-80 on Metric Tonne basis for following:
During the monsoon period, festival periods and any other lean periods, Fly Ash / Bed Ash will
be transported to Lignite mines / any other locations for utilization / dumping purpose. As soon
as ash is unloaded at site, it is to be dozed & leveled immediately. The delay in Dozing of
ash will block the approach area for further transportation & unloading at designated
point. So, it is very much essential to keep the dozer in running condition for quick action.
It may be noted that, the Contract will operate as & when required basis which shall mainly
depend upon volume & frequency of rainfall, sale of ash or any other requirement. By any
reason, if Contract is not executed or partly operated, GIPCL shall not be responsible for
any type of idle charges.
2.2 The Scope of Work covers Hiring of Dozer D-80 on Running Hour basis for following:
2.2.1 The compaction of Lignite and Limestone at in-plant, out plant and ELHS stockpile layer
2.2.2 Pushing of Limestone and Lignite at in-plant stockpile, out plant stockpile, ELHS
stockpile and at feeder breaker end.
2.2.3 For lying of conveyor belt and lifting of take up counter weights in Maintenance work
and any other jobs as per the requirement.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
2.3 The Bid submitted by the Bidder not covering the total scope of work and services as
detailed out in the tender document shall be liable for rejection.
2.4 Quantum of job mentioned against all items in the Price bid are indicative only & may vary
as per site requirement & not to be construed as maximum or guaranteed quantity.
The quantities shown in the price bid are approximate quantities for the contract period and
they may vary as per job requirements.
2.5 All the miscellaneous activities pertaining to specific work to be executed for satisfactory
performance is in the scope of Contractor in his quoted rates.
3. GENERAL INSTRUCTIONS
3.1 The Bidders who are interested in participating in the Tender must read and comply with
the instructions and the Terms & Conditions contained in the Tender Document.
3.2 The Bids shall be filled in by the Bidders clearly, neatly and accurately. Any alteration,
erasures or overwriting shall be liable to make the tender invalid unless the same is neatly
carried out and attested over the full signature of Bidder. The decision of the Company
to interpret the information and rates filled in by the Bidder shall be final and binding on
3.3 The Bidders are requested to make themselves fully conversant with the General
Conditions of Contract, Special Conditions of Contract, Technical Specifications, Site
conditions, Safety & Health Aspects and Norms to be observed etc. before submitting
their bids so that no ambiguity arises in these respects subsequent to submission of the
3.4 Before quoting the rates, the Bidder should go through the specifications, scope of work
etc. and get himself fully conversant with them. The Bid should include cost of
mobilization and cost to adhere to all Safety Norms as described in the Tender. No
relaxation or request for revision of quoted / accepted rates shall be entertained
subsequent to the opening of Bid on account of mobilization or Safety costs.
3.5 Splitting of work is not advisable as the purpose of SoR method will not be fulfilled.
3.6 Bidder has to submit all the information as per required Bid document. Failure to furnish
all the information as per required Bid documents or submission of a Bid containing
deviations from the contractual terms and conditions, specifications and requirements,
shall be rejected.
3.7 The Bids shall be submitted within the time frames set out in the Notice Inviting Tender
(‘NIT’) and Bids submitted thereafter shall not be accepted and considered.
3.8 The Tender Document shall not be transferable.
3.9 The Bidders are expected to examine all instructions, forms, terms & specifications in the
Bid documents and to get fully acquainted themselves with all the conditions and matters
which may affect the subject matter of the work/tender or the cost thereof. If any Bidder
finds any discrepancies or omissions in the specifications and documents or any doubt
in true meaning or interpretation of any part, he shall seek necessary clarifications in
writing if required.
3.10 Conditional offers shall not be considered and liable to be rejected.
3.11 The Company reserves the right to extend the deadlines for submission of the Bids by
giving amendments.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
3.12 Bidders may visit site for detailed understanding regarding the “Scope of Work” as per
the Tender document, with due prior intimation in writing pertaining to the said Site visit.
3.13 During evaluation of Bids the Company may, at its discretion ask the Bidder(s) for
clarification of their Bid. The request for clarification and the response shall be in writing
and no change in prices or substance of the Bid shall be sought, offered or permitted.
3.14 The Company reserves the right to amend / modify the Bidding documents at any time
prior to the deadline for submission of Bids, either at its own discretion or in response to
the clarification requested by a prospective Bidder. In such case, the Company may in its
discretion extend the deadline for submission of Bids in order to facilitate the prospective
Bidders for incorporating the effect of the amendment in their Bids.
3.15 The Bidders shall bear all costs and expenses associated with the preparation and
submission of their respective Bids, to attend meetings or conferences, if any, including
any pre award discussion with the successful Bidder, technical and other presentations
etc. and the Company shall not be liable for any expense thereof.
3.16 If the successful Bidder is a joint venture, formed of two or more companies, the Bidder
along with the partners shall accept joint and several responsibilities and liabilities for all
obligations under the Contract.
3.17 Timely and satisfactory completion of the work and strict adherence to the allotted time
frames for jobs shall be the essence of the contract.
3.18 The Company reserves the right to qualify/disqualify any applicant without assigning any
3.19 The Bidder shall be disqualified if any untrue statement or misrepresentation is made in
the Bid forms, attachments and other supporting documents submitted by the Bidder.
It is perquisite and necessary for all interested Bidders to visit the site/plant after downloading
the Tender copy to understand the actual working conditions, compliance related to labour, safety
etc. before submitting their offer. Failing which, any consequential liabilities arising will be to
Bidder’s account. The Bidders shall examine the site of works and its surroundings at his own
responsibility. The Bidders shall collect information that may be necessary for preparing the Bid
and entering into a Contract. All costs and liabilities arising out of the site visit shall be at Bidder’s
The Bidder is deemed to have examined and understood the Tender document, obtained his
own information in all matters whatsoever that might affect the carrying out the works expressly
mentioned or works which may have to be carried out to fulfill his contractual obligations within
the scheduled rates and to have satisfied himself to the sufficiency for his offer.
The submission of Tender by a Contractor implies that he has read these instructions, conditions
of the contract etc. and has himself aware of the Scope, nature of works & specifications of the
works to be done. GIPCL will not, therefore after acceptance of Contractor’s rate, pay any extra
charges for any other reason in case the Contractor is found later on to have misjudged the site
Any error in description or quantity or omission in the contract document shall not vitiate the
contract or release the Contractor from executing the work comprised in the contract according
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
to scope of works, magnitude of the works, requirement of materials, equipment, tools & tackles,
labour, etc. Contractor has to complete the work in accordance with the contract documents
irrespective of any defects, omissions or errors that may be found in the contract documents.
BIDDER shall inspect the site, examine and obtain all information required and satisfy himself
regarding matters such as access to site, communication, transport, working condition including
constraint of work place, confined area, quantum of dusting, running equipment, importance of
work, round the clock working conditions, safety requirements, right of way, high flood level in
River, flow of water during monsoon/dry season in the River/Nullah, the type and number of
equipment and facilities required for the satisfactory completion of work, the quantity of various
items of the work, the availability of local labour, availability and rates of material, local working
conditions, uncertainties of weather, obstructions and hindrances that may arise, etc which may
affect the work or cost thereof, before submission of his Bid. Ignorance of site conditions shall
not be accepted by the GIPCL as basis for any claim for compensation. The submission of a Bid
by the BIDDER will be construed as evidence that such an examination was made. Any later
claims / disputes in regard to rates quoted shall not be entertained or considered by the GIPCL.
The rates quoted by BIDDER shall be based on his own knowledge and judgment of the
conditions and hazards/risk involved and shall not be based on any representations of the
5. ELIGIBILITY CRITERIA
The following criteria shall be adopted for qualifying the Bidders for further proceeding:
5.1 Bidder should possess minimum Three years of experience out of last five years ending
last day of the month previous to the one in which tender is invited in similar nature of
mechanized jobs involving the equipment / machinery such as Dozer of Model: D-80 or
equivalent dozing capacity, and/ or other similar types of HMVs / HCVs and Earth mover
equipments. Bidder shall enclose the proof of the same. Bidder shall submit necessary
evidence for the same like attested copies of work orders along with work completion
certificates from clients. The work completion certificate shall comprise of Order value &
Executed value. Bidders should have executed the work directly. The work executed as
a sub-contractor or subletting agency shall not be taken in to consideration.
Note: For evaluation of the bid, the executed value mentioned in the work completion certificate
will be considered.
5.2 Bidder must Own / Possess minimum One (1) No. Dozer of Model: D - 80 or equivalent
dozing capacity. The relevant copies showing the Ownership / Possession of the said
Dozer shall be submitted along with the Bid.
5.3 Bidder should produce evidence of having experience of successfully completed
similar works as defined hereunder during last five years ending last day of the
month previous to the one in which tender is invited, satisfactory progress of ongoing
works etc. secured from clients along with certified copies of documentary evidence
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
preferably photo copies of work experience. The experience should be either of the
a. One similar completed work each costing not less than the amount equal to
Rs. 16.75 Lac with GST.
b. Two similar completed works each costing not less than the amount equal to
Rs. 11.17 Lac with GST.
c. Three similar completed works each costing not less than the amount equal
to Rs. 8.38 Lac with GST.
Bidder should specifically mention fulfilling of above criteria in his offer along with details of work
orders & work completion certificates issued by clients.
5.4 Tender Fee: The Tender Fee shall be accompanied in form of Demand Draft / RTGS
5.5 EMD: The EMD shall be accompanied in the form of DD/RTGS or Bank Guarantee given
by Bank as described in detail in Clause No. 7 of this Section of Tender Document.
5.6 Bidder should have separate Employees Provident Fund code number towards
registration of firm with RPF commissioner.
5.7 Attested copies of relevant documents duly signed & sealed on each & every page shall
be submitted. The above documents will be analyzed and if found satisfactory, the Price
Bid will be open. GIPCL may verify the documents, experience certificates issued by
concerned authority. After opening of Technical Bid, if any required attested documents
found missing in the Technical Bid submitted by the Bidder, the tender inviting authority
may inform to that Bidder only once by e-mail to submit the missing required documents
within stipulated time limit. If Bidder/Bidders fail to submit within stipulated time, their Bid
will be declared technically disqualified and no further correspondence will be
5.8 Bidder should have average annual turnover of Rs. 8.38 lac with GST during last
three financial years i.e. FY: 2023-24, FY: 2024-25 and FY: 2025-26. Bidder shall
furnish annual audited financial statement duly certified by Chartered Accountant for the
aforesaid three financial years to demonstrate the financial healthiness of the company.
The Balance sheet must be in the name of the company. Any type of MOU for this
purpose will not be entertained.
Note: In case, the annual turnover is less than the statutory guidelines which does not require
audit, the Bidder shall submit the turnover certificate from Chartered Accountant.
5.9 The Bidder has to submit Income Tax Permanent Account Number (PAN) & GST
registration number. Copy of the same shall be submitted.
5.10 The Net worth at the end of the financial year 2025-26 should be positive (+) as per
audited accounts audited by a qualified Chartered Accountant, being a member of the
Institute of Chartered Accountants of India.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
5.11 In case Bidder is a Consortium / joint deed of undertaking of company, the above
requirements/credential of consortium leader / bidder shall be considered unless
otherwise specifically mentioned in the tender.
5.12 If Bidder or its Partner(s) or Director(s) is /are/was in any Litigation(s), Court Case(s) or
Arbitration(s), either completed or under progress during last five (5) years or Black Listed
/ Deregistered / Stopped or banned from dealing in the past by any Govt. of Gujarat
Undertakings / Depts. / Authorities and Govt. of Gujarat supported companies /
undertakings / organizations, Bid of that party will be liable to be rejected. Bidder agrees
and undertakes to accept decision of GIPCL in this regards as final and binding on the
Bidder without any demur and that no further correspondence shall be done in this regard
at any stage. Bidder shall have to submit the “Declaration for Contractual Disputes/
Litigations” as appended in Annexure – G (SECTION – F)
5.13 Bidder shall have to submit the “Declaration-cum-Undertaking for Compliance of Safety
Laws and Regulations” on his company letter head as amended in Annexure-F in Section-
F / Form attached.
• If any Major Violation of any safety law(s) / Rule(s) is / are found during the preceding
Three (3) years, Bid of that party will be liable to be rejected. Bidder agrees and
undertakes to accept decision of GIPCL in this regards as final and binding on the Bidder
without any demur and that no further correspondence shall be done in this regard at any
• If any of the details submitted in the prescribed Annexure / Form to the Bid is/are found
to be false, incorrect at any time in future, then the Contract awarded to that Bidder /
Contractor shall be liable to be terminated forthwith without any notice / correspondence
and Bidder agrees and undertakes to accept decision of GIPCL in this regards as final
and binding on the Bidder without any demur and that no further correspondence shall
be done in this regard at any stage. Further, Performance / Security Deposit will also be
liable to be forfeited. Any dues to GIPCL from the Bidder / Contractor shall be recovered
from the pending bills or any other dues payable to the Bidder / Contractor, if any or
otherwise through any other recourse available under the Laws.
The Bidder shall submit all the evidences, documents, attested copies of Work Orders &
Work completion certificates etc. as a proof with EMD & Tender Fee and also provide the
requisite details ‘Online’ for meeting the pre-qualification requirements. GIPCL will verify
the experience, performance, capability & strength of Bidders, independently for
executing the job. GIPCL may visit the site & consult the owner of the industry/property
where similar job is executed by the Bidder. GIPCL reserves the right to accept / cancel
/ reject any / all Bids without assigning any reason thereof. The Tenders of qualified
Bidder/Bidders shall only be considered for further evaluation.
5.14 Site Visit is mandatory prior to submission of bid to understand the scope of work,
working conditions, site conditions, equipments, tools & tackles, labor deployment,
associated risk, surrounding etc.
6. LANGUAGE OF BID
The Bid prepared by the Bidder, and all correspondence and documents relating to the Bid
exchanged by the Bidder and the Company, shall be written in the English language. Any printed
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
literature furnished by the Bidder, written in another language shall be accompanied by an
English translation for the purpose of interpretation of the Bid.
7. EARNEST MONEY DEPOSIT (EMD) and TENDER FEE
7.1 An EMD of Rs. 48,000/- and Non-refundable Tender fee Rs. 2,950/- inclusive of
applicable GST shall accompany with Bid. Tender fee shall be submitted through
RTGS / online mode of payment only.
7.2 The EMD shall be submitted in the form of DD/irrevocable Bank Guarantee in favor of
“Gujarat Industries Power Company Limited” from all Nationalized Banks or Axis Bank,
ICICI Bank, HDFC Bank, Kotak Mahindra Bank, IndusInd Bank, Federal Bank, Bandhan
Bank, IDBI Bank and Karur Vysya Bank as per Performa of BG enclosed with this tender
document under Section-F (Annexure-C).
Bank for EMD DD Payable at :
1. Bank of Baroda Mosali, Dist: Surat
2. State Bank of India Nani Naroli, Branch Code:
3. Any Nationalized banks Surat
Alternatively, EMD & Tender Fee may also be submitted through RTGS mode of
payment by the bidders as per the details given below:-
1. BANK NAME:- State Bank of India
2. BRANCH:- Nani Naroli
3. IFSC CODE:- SBIN0013423
4. BENEFICIARY NAME: Gujarat Industries Power Company Limited
Also, EMD & Tender fee may be submitted through online payment gateway of company’s
website: www.gipcl.com (online Payment Form) as per detail provided in Section-F
(Annexure-I) herein under.
7.3 In case EMD is paid in the form of BG, the same shall be valid for a period of 180 days
after the due date for submission of the Bid.
7.4 The EMD of the successful Bidder will be returned after payment of Security Deposit
within 21 days from the date of award of contract by successful Bidder.
7.5 The Earnest Money Deposit will be refunded to the unsuccessful BIDDER as soon as the
Tender is finalized and after award of LOI/WO.
7.6 Any bid not accompanied with EMD and Tender fee will be rejected. Tender Fees and
EMD should be submitted in physical form directly to GIPCL as per Clause 7.9.
7.7 No interest shall be payable on EMD.
7.8 The EMD will be forfeited if the BIDDER (i) withdraws his Tender after acceptance or (ii)
withdraws his Tender before the validity date of the tender.
7.9 SCHEDULE OF EMD & TENDER FEES:
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
Details/receipts of EMD & Tender fee Address for Submission:
paid by RTGS/online or EMD in
physical form by way of DD/BG (as CGM (THERMAL),
GUJARAT INDUSTRIES POWER CO. LTD.,
applicable) with other documents duly (Surat Lignite Power Plant)
self-attested are to be submitted in Village – Nani Naroli, Taluka – Mangrol
physical form in sealed cover as per District – Surat 394 112, Gujarat
details mentioned in NIT. Bid No. Phone : 02629-261063
shall be mentioned at the top of Fax : (02629) 261073 /
cover/envelope.
8. SUBMISSION OF BIDS
A: MODE OF SUBMISSION
The Bids shall be submitted online on (n)Procure portal (https://tender.nprocure.com) within
the dates specified in the NIT along with the details of Tender Fees, EMD in two parts as under:
(a) Pre-qualification and Techno-commercial Bid without price.
(a) Pre qualification and Techno-commercial Bid without price:
The Tender document duly signed in all pages without price bid along with techno-commercial
deviations, if any, shall accompany the Bid. The following Information shall be provided in the
techno commercial bid:
1. Schedule of deviation (SECTION – F: Annexure E) Technical as well as commercial, if
The following supporting documents shall also be submitted along with EMD & Tender Fee in
1. The Tender Document duly signed in all pages without price bid along with Techno-
commercial deviations, if any.
2. Proof of experience meeting the minimum ‘Eligibility Criteria’ (Clause No. 5 above).
3. Performance certificate issued by clients.
4. Previous Work Order copies.
5. Details of present Work Order (if any).
6. Average Annual Turnover for the last three financial years i.e. FY: 2023-24, FY: 2024-25
and FY: 2025-26, audited annual accounts / financial statements i.e. Profit and Loss
account and Balance Sheet duly certified by a practicing CA will be required.
7. P.F Number and Allotment Letter.
9. GST registration number/certificate copy.
10. Copies of RC Books / Certificate showing Ownership Dozer Model D – 80 or equivalent
as mentioned in ‘Eligibility Criteria’ (Clause No. 5 above).
• To participate in e-Reverse Auction, Bidders have to create e-Auction user Id on https://e-
auction.nprocure.com and it is mandatory to submit the same along with physical
Techno-commercial Bid; so that the Bidder shall be allowed to participate in the e-
Reverse Auction.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
1. Price Bid shall be
submitted online only through (n)Procure portal
(https://tender.nprocure.com) .
Note: Estimate includes cost of all equipment / machinery, manpower, vehicles,
consumables, fuel, tools & tackles, transportation, Safety statutory compliance,
mobilization etc.
2. GST shall be paid extra at actual as per prevailing rates as declared by Central
Government on submission of documentary evidence.
3. Bidder shall have to fill the respective item rate excluding GST.
4. The quantities shown in the Section – E: Schedule of Quantities and Price are
approximate for the Contract Period and may vary as per job requirement.
5. The Bidder shall fill the Bid documents with utmost care in consonance with the
instructions contained in the Bid documents.
B: METHOD OF TENDERING / SIGNATURE ON BIDS
(i) The Bid must contain the postal address like name, residence and place of business of
the person or persons submitting the Bid and must be signed and sealed by the Bidder
with his usual signature. The name of all persons signing the documents shall also be
typed or printed below the signature on each page.
(ii) Bid by a joint venture/partnership firm must be furnished with full names of all partners
and be signed with the partnership name, followed by the signature and designation of
one of the authorized partners or other authorized representative(s). A certified copy of
the power of attorney authorizing such partner or representative shall also be submitted.
(iii) Bids by a Corporation/Company must be signed with the legal name of the
Corporation/Company i.e. by the President/Managing Director/Secretary or other
person or persons authorized to Bid on behalf of such Corporation/Company. A certified
copy of the board resolution/power of attorney authorizing such partner or
representative shall also be submitted.
(iv) The Bidder's name stated on the proposal shall be the exact legal name of the firm.
(v) Erasures or other changes in the Bid Documents shall be initialed by the person signing
(vi) Bids not conforming to the above requirements of signing shall be disqualified.
9. MODIFICATION AND WITHDRAWAL OF BIDS
a. The Bidder may modify or withdraw the bid prior to the deadline prescribed for submission
b. No Bid shall be modified subsequent to the deadline for submission of Bids.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
c. No Bid shall be withdrawn in the interval between the deadline for submission of Bids and
the expiration of the period of bid validity.
10. POLICY FOR BIDS UNDER CONSIDERATION
a. Bid shall be deemed to be under consideration immediately after opening of the Bid and till
official intimation of award / rejection made by the Company to the Bidders.
b. While the Bids are under consideration, Bidders and / or their representative or other
interested parties are advised to refrain from contacting by any means, the Company. The
Engineer, if necessary, will obtain clarifications on the Bids by requesting for such
information from any or all the Bidders, in writing as may be necessary. The Bidder will not
be permitted to change the price or substance of the Bid after the Bid has been opened.
11. EFFECT AND VALIDITY OF THE BID
a. The Bid should be kept valid for acceptance for a period of one hundred and eighty (180)
calendar days from the last date of submission of Bids.
b. The submission of any Bid along with the required documents and specifications shall
constitute an agreement that the Bidder shall have no cause of action or claim, against the
Company for rejection of his Bid. The Company shall always be at liberty to reject or accept
any Bid or Bids at his sole discretion and any action will not be called into question and the
Bidder shall have no claim in that regard against the GIPCL.
12. OPENING OF BIDS
12.1 GIPCL will open the Pre-qualification / Technical Bid / Price Bid, as the case may be,
in presence of Bidder's representatives whenever such a procedure has been specified.
Otherwise the tender will be opened by the authorized officers of GIPCL.
12.2 Preliminary Examination:
12.2.1 The Company will examine the Bids for any computational errors, for sureties
furnished by Bidder, for authentication of documents submitted and completeness of
12.2.2 Arithmetical errors will be rectified on the following basis:
(a) If there is a discrepancy between the unit price and the total price that is obtained by
multiplying the unit price and quantity, the unit price shall prevail and the total price will
be corrected & will be binding to the Bidders.
(b) If there is a discrepancy between the Total Bid Amount and the sum of total prices, the
sum of total prices shall prevail and the Total Bid Amount will be corrected & will be
binding to the Bidders.
13. EVALUATION & COMPARISON OF BIDS
13.1 GIPCL shall evaluate the Bids received and accepted by it to ascertain the lowest
evaluated Bid in conformity with the specifications of the Tender Document.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
13.2 The Technical Bids will be examined for minor matters regarding qualification of bids.
Subsequent to correspondence with the respective bidders, the decision of Tender
Committee will be final.
13.3 All responses to requests for clarifications shall be in writing and shall be presented to
the Company through e-mail or in a sealed envelope on or before the given date
requested by the Company. If the Technical clarifications sought by the Company do not
reach the Company on or before due date, the Bid will be rejected.
13.4 The comparison of all the Bids shall be carried out with reference to the scope of work as
per the technical specification. Any deviation / omission shall be evaluated at highest
quoted price of the deviation / omission quoted by any of the Bidder. In case a separate
price (for omission) is not given by any other Bidder, a reasonable price of the same shall
be taken & the same shall be binding to the Bidders.
13.5 The commercial deviation, if any, shall be loaded to bring all the Bids at par. The loading
shall be carried out at an interest rate of 2% above PLR of SBI.
13.6 A Bid to be substantially responsive shall be one which on evaluation confirms to all the
terms, conditions and specifications of the Bid documents without any material deviation
or reservation.
13.7 For the above referred purpose, a ‘material deviation’ shall be one which:
(a) Affects in any substantial way the Scope, Quality or performance of the
(b) Limits in any substantial way and in a manner inconsistent with the Bid documents,
GIPCL’s right or the Bidder’s obligations, under the contract, or
(c) Rectification of it would affect unfairly the competitive position of other Bidders presenting
substantially responsive Bids.
14. RIGHT OF REJECTION OF TENDERS
14.1 GIPCL reserves the right to accept or reject any Bid or to cancel the Bidding process and
reject all Bids at any time prior to award of Contract, without thereby incurring any liability
to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders
regarding the same.
14.2 Any Tender without EMD and Tender Fee will be treated as non responsive and shall be
rejected at the outset & no further correspondence shall be entertained regarding this.
14.3 GIPCL reserves the right to debar any Bidder from participation in future Bids if such
Bidder has quoted an abnormally low rate in the Bid document/price Bid.
15. AWARD OF CONTRACT
15.1 GIPCL will award the Contract to that Bidder whose quotation has been determined to be
substantially responsive and evaluated as the lowest quotation in conformity with the
requirements of the specifications and documents contained herein, provided further that
the bidder is determined and evaluated to be qualified to perform the contract
satisfactorily.
15.2 The successful bidder shall be intimated of his selection through the Letter of Intent or
Letter of Award/ Work Order which shall be sent to him through e-mail, courier, fax or
registered mail.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
15.3 GIPCL reserves the right to cancel/short close the contract during the contract period by
giving prior notice of one month without assigning any reason.
15.4 GIPCL reserves the right to split the contract quantity between vendors.
16. CONTRACT PERIOD
16.1 The Contract will be for a period of two (2) years and shall commence from the date as
mentioned in the Letter of Intent (LoI) / Work Order which shall be awarded to the
successful Bidder.
16.2 GIPCL reserves the right to extend the Contract Period up to 3 months on the same rates
and terms and conditions without any price escalation and entering into any new contract.
16.3 The said Contract Period can be extended if mutually agreed upon by both the parties up
to one year and in such a case a revised Work Order shall be issued at the same rates
and terms & condition or at negotiated rates acceptable by both parties i.e. the Company
& the Contractor.
17. ASSIGNMENT AND SUB-LETTING:
The contractor shall not directly or indirectly assign or sub-let total / any part of contract to
any other party or agency.
18. CONTRACTOR’S OBLIGATIONS
• DEPLOYMENT OF EQUIPMENT / MACHINERY
(i) The Contractor shall Own / Possess the following Equipments / Machinery for deployment
at site for timely & satisfactorily execution of the works under the Contract:
• Minimum 1 No. Dozer D-80 (Model: D-80 or equivalent)
(ii) The Contractor shall deploy sufficiently skilled Dozer Operators having a valid Driving
License of respective Earth Mover category and HMV / HCV category and along with mobile
(iii) At the time of deploying manpower, the Contractor shall strictly comply all the applicable
labor laws/Acts norms including but not restricted to the age of the workers, women workers
and shall also ensure that a police verification and security check for all the workmen /
labour engaged at the GIPCL site is done and necessary documents regarding the same
shall be submitted to the GIPCL’s authorized representative/officer-in-charge. Any default
in complying with the same or any misrepresentation regarding compliance of the same
shall compel GIPCL to initiate appropriate civil or criminal proceedings regarding the same.
(iv) The Contractor shall also comply with the safety requirements and provide his
workmen/labour with safety equipment like safety shoes, safety helmets, safety shoes
masks, gum boots, a uniform and other necessary PPEs for properly undertaking the
operations involved under this contract. Following are also to be issued:
(v) Contractor shall nominate / authorize person in writing to co-ordinate with GIPCL’s
Engineer and who shall bear overall responsibility for performance of the Contract. Such
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
person shall remain always available at SLPP site. Contractor has to submit the authority
letter and documentary proof for the same.
(vi) The Contractor shall appoint a person who shall co-ordinate with GIPCL’s Engineer In-
charge for daily entrusted job. They have to maintain daily records duly signed for the works
carried out and duly certified by Engineer-In-Charge. The Contractor in co-ordination with
the Engineer-In-Charge shall ensure the availability of adequate manpower / machinery /
equipment to carry out the job satisfactorily on a daily basis. As per the instruction of
Engineer In-Charge they have to allot the work and execute the same in specified time limit.
(vii) During execution of the works, one or more jobs may be required to be done simultaneously
and the Contractor shall mobilize additional resources accordingly.
(viii) During emergency or similar situations the Contractor shall be required to mobilize
resources as per need within the period of four (4) hours as directed by GIPCL. If the
Contractor fails to mobilize sufficient resources to complete the job in time, GIPCL will
execute the job through other agency at the risk and cost of the Contractor with 10%
supervision charges plus applicable GST as per extant GST Laws & the same will be
recovered from the Contractor’s bill.
19. CLARIFICATION OF BIDDING DOCUMENTS
If any Bidder requires any further information or clarification in the Bidding Documents, may
notify the Company before one week of last date of submission of online Bid, in writing or by E-
mail at the GIPCL's mailing address [email protected] as indicated in the 'Invitation to Bids'.
The GIPCL's response (including an explanation of the query) will be sent in writing or by E-mail
to all prospective Bidders who have received the Bidding Documents.
20. TIME SCHEDULE
The basic considerations and the essence of the 'Contract' shall be the strict adherence to the
time schedule for performing the specified 'Works'.
21. UNDERSTANDING AND CLARIFICATION ON DOCUMENTS AND
The Bidder is required to carefully examine the specifications and documents, all the conditions
and matters work wise & cost wise. If any Bidder finds any discrepancies or omissions in the
specifications and documents or is in doubt for any meaning of any part, he shall request in
writing for an interpretation/ clarification to the GIPCL or during Pre-Bid meeting.
All such interpretations and clarifications shall form a part of the Bid documents.
All the payments against the Work Order shall be in Indian currency and payable through cheque
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
23. POINTS TO BE CONSIDERED DURING QUOTING ONLINE PRICE BID
a. The Schedule of Rates (SoR) shall be read in conjunction with Instructions to Bidders,
General Conditions of Contract, Special Conditions of Contract and Technical
specifications.
b. The quantities given in the Schedule of Rates (SoR) are estimated and will be made as per
actual work carried out as per the rates of Work Order.
c. The method of measurement of completed work for payment shall be in accordance with
the method of measurement specified in the Tender document.
d. No separate amount shall be payable for use of auxiliary equipment incidental to or in day
to day operation in the course of fulfillment of contractual obligation of the supplier.
Note: Interested Bidders are requested to submit the online tender at least two days in
advance from the due date set for Online submission of Bid in order to avoid non-
participation in e-Tender due to probable technical problem in (n)Procure portal.
The quantities specified are estimated and for tendering purpose only. Payment will be
made, based on actual work done as certified by Engineer In-charge of GIPCL.
Quantities of individual items may be revised during the course of Contract period based on site
requirement. Contractor shall not be entitled for any compensation on ground of such alteration
in scope of work. GIPCL reserves the right to operate or increase / decrease quantities in each
item or omit any item included in Schedule of Quantity at his discretion. Contractor shall have no
claim, whatsoever, on grounds of loss of anticipated profit etc. on account of the same.
After commencement of the work, GIPCL, for any reason may not require to be carried out the
whole/part of the work as specified in the tender, the Engineer In-charge shall inform the fact for
thereof to the Contractor and the Contractor shall have no claim for any payment or
compensation whatsoever on account of any profit or advantage which he might have derived
from the execution of the work in full but which he did not derive in consequence of the full amount
of the work not having been carried out nor shall he have any claim for compensation by reason
of any change having been made in the original specifications and instructions which shall involve
any curtailment of the work as originally contemplated.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
INSTRUCTIONS TO BIDDERS FOR ONLINE TENDERING &
E-REVERSE AUCTION
SR. DESCRIPTION
Tender documents are available only in electronic format and same can be
01. downloaded from the website https://tender.nprocure.com and It can also be
viewed from Company’s website www.gipcl.com
Price bid should be submitted online through the website
02. https://tender.nprocure.com only. No physical submission of price bid will be
entertained as it should be furnished on-line only
Bidders who wish to participate in online tenders will have to procure / should
have legally valid Digital Certificate (Class III) as per Information Technology
Act-2000, using which they can sign their electronic bids. Bidders can procure
the same from any of the license certifying Authority of India or can contact
(n)code solutions- a division of GNFC Limited, who are licensed Certifying
Authority by Government of India
All bids should be digitally signed. The bidders are required to contact at the
below mentioned address for detailed training on on-line tendering and also for
(n) Code Solutions - A division of GNFC Ltd.
04. 403, GNFC Infotower, S.G Road,
Bodakdev, Ahmedabad – 380054 (Gujarat, India).
E-mail: [email protected], website: https://tender.nprocure.com
Interested bidders are requested to submit the online tender at least two days in advance
from the due date set for on line submission of bid in order to avoid non participation.
E-REVERSE AUCTION:
1 GIPCL reserves the right to conduct E-Reverse auction through (n) Procure platform.
2 E-Reverse auction shall be conducted amongst (a) the lowest 50% eligible bidders
(rounded to the next higher whole number) from the total bids received OR (b) Minimum
three (03) lowest bidders, whichever is higher, shall be invited for participation in e-Reverse
Auction through n-procure platform.
3 Opening Price, Detrimental value and duration for the e-Reverse Auction shall be informed
to the qualified bidders before start of e-Reverse Auction.
4 After e-Reverse Auction process, L1 bidder shall be decided on Lowest Total Contract
Price. i.e. gross total quoted amount with GST.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
5 After e-Reverse Auction process, the original % rate quoted by the final L1 bidder shall be
reduced proportionately on SoR of individual items/packages by total % reduction after e-
reverse auction, keeping GST % rate same as originally quoted by final L1 bidder.
6 To participate in e-Reverse Auction, Bidders have to create e-Auction USER ID on
https://e-auction.nprocure.com and it is mandatory to submit the same along with
physical Techno-commercial Bid; so that the Bidder shall be allowed to participate
in the e-Reverse Auction.
7 In case of any further information regarding online bidding or if a Bidder needs any
assistance in accessing/ submission of online bid/ clarification or if training is required for
participating in online e-reverse bidding, then the Bidder can contact the following office for
assistance or training:
(n) Procure Cell, (n) code solutions-A division of GNFC Ltd.,
403, GNFC Info tower, S.G. Road,
Bodakdev Ahmedabad – 380054 (Gujarat)
Fax: 079-26857321 / 40007533, Email: [email protected]
Bidder may visit https://tender.nprocure.com for information regarding e-tendering
registration process.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
GENERAL CONDITIONS OF CONTRACT
1. CONTRACT SECURITY DEPOSIT/ PERFORMANCE BANK GUARANTEE
As a Contract Security, the successful Bidder, to whom the work is awarded, shall be required to
furnish a Performance Bank Guarantee (PBG) / Contract Security Deposit in favour of Gujarat
Industries Power Company Limited for guarantee amount at Ten percent (10%) of the “Annual
Contract Price excluding GST” from any Nationalized Bank, Axis Bank, ICICI Bank, HDFC
Bank, Kotak Mahindra Bank, IndusInd Bank, RBL Bank, DCB Bank, Federal Bank, Bandhan
Bank, Standard Chartered Bank in the format attached in SECTION-F, and it shall guarantee the
faithful performance of the 'Contract' in accordance with the terms and conditions specified in these
documents and specifications. Contract security deposit shall be submitted strictly within twenty
one days from the date of LoI or work order, whichever is earlier. The guarantee shall be valid up
to retention period of four months from the contract completion date. The Guarantee amount
shall be payable to the Company in Bidder's home currency without any condition whatsoever.
The Performance Bank Guarantee (Security deposit) shall be returned to the Vendor / Contractor
without any interest at the end of the Retention Period after the completion of Contract and on
fulfilling contractual obligations throughout the retention period. However, any delay in
submission of initial SD will result in equivalent late release of entire SD after guarantee period.
2. PENALTY AND RECOVERY:
(i) In case of any damage of equipment/machinery due to negligence of Contractor or any
other reasons attributed to Contractor the decision of Engineer In-charge regarding the
amount of recovery shall be final and binding subject to a maximum of 10% of Contract
value. Recovery will be affected from the monthly bills and security deposit.
(ii) If the Contractor fails to execute the work as per directions of Engineer In-charge within the
time frame given in work order and / or day to day instructions given by Engineer In-charge,
GIPCL shall get the work done by third party at the risk & cost of the Contractor with 10%
additional overhead charges plus applicable GST as per extant GST Laws.
(iii) The ascertainment of the cause of the damage shall be done by Plant head - SLPP and his
decision in this regard shall be final.
(iv) The aforesaid amounts of Penalty and Damages shall be recoverable from the monthly
invoices of the Contractor or the Security deposit. If the amount of damages recoverable
from the Contractor exceeds the total of invoices and/or Security deposit amount, then the
Contractor shall become liable to pay the same to GIPCL and GIPCL shall be entitled to
initiate appropriate proceedings against the Contractor for the same.
(v) Tentative Penalty shall be imposed to Contractor for various instances as follows:
• Non availability of the following equipments / machinery although due intimation in
▪ Dozer D-80 / Un-Satisfactory work: Rs. 5,000 per Day in case of non-availability
• Absence of Dozer operator without approval from Engineer In-charge: Rs. 1000 / day
• Un-safe work execution: Rs. 750 per day per Instance
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
• In-spite of repeated instruction, if found without safety appliances like Safety shoe, Safety
helmet or any other Safety gear which he has to wear considering his job location,
Necessary action shall be taken against that particular workmen like not allowing him in to
plant premises etc. Also, a token amount of Rs. 100/- per day would be deducted as per
the discretion of Engineer In-charge / Safety Officer.
(vi) The maximum total Penalty which shall be deductible considering all above instances shall
be limited to 10% of the Total Contract Value.
3. DEDUCTIONS FROM CONTRACT PRICE
All costs, charges or expenses that GIPCL may have paid, for which, under the Contract the
Contractor is liable, shall be recovered by the GIPCL. The Contractor shall pay all such claims
within 15 days of claim failing which the same shall be deducted from the bills of Contractor.
4. TERMINATION OF CONTRACT BY GIPCL
Contractor shall be responsible to complete the jobs within agreed time schedule and in case
Contractor fail to complete the job, GIPCL shall recover from his bill, Security Deposit and / or
whatsoever for expenses incurred to complete the job with additional 10% overhead charges
plus applicable GST as per extant GST Laws.
In case if contractor’s services are not found satisfactory with respect to mobilization, time bound
completion of work, workmanship & safety (OHSAS policy of GIPCL) then GIPCL has right to
terminate the contract at any time by giving him 15 days advance notice without assigning any
reason and will make the alternate arrangement at the risk & cost of contractor.
GIPCL may terminate the contract after due recoveries of pending jobs / damages after giving
15 days advance notice to the Contractor if any of the following events occur:
i. Contractor is adjudged as insolvent.
ii. Contractor has abandoned the contract.
iii. Contractor fails to proceed with the work with due diligence as per requirements of the
iv. Contractor has neglected or failed persistently to observe or perform any of the acts,
matters or things, which as per the contract are to be observed and performed by the
v. Contractor repetitively violating the safety norms for more than three incidents.
vi. Any major contradiction of applicable labour laws.
vii. Any major deviations from contractual terms and conditions including quality of job.
viii. GIPCL reserves the right to terminate the contract without giving any reason
whatsoever and forfeit the PBG.
5. FAILURE & TERMINATION
If the Contractor after receipt of written notice from the GIPCL / Engineer In-charge requiring
compliance, with such further drawings and/or the GIPCL / Engineer In-charge’s instructions fails
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
within seven days to comply with the same, the GIPCL / Engineer In-charge may employ and
pay other agencies to execute any such work whatsoever as may be necessary to give effect
thereto and all costs incurred in connection therewith shall be recoverable from the Contractor
by the GIPCL on a certificate by the GIPCL / Engineer In-charge as a debt or may be deducted
by him from any money due or to become due to the Contractor.
If the Contractor fails to execute the work or fails to mobilize the resources and equipments as
per directions of GIPCL / Engineer In-charge within the time frame given and/or violating the
GIPCL’s safety rules & regulations, GIPCL / Engineer In-charge shall get the work done by third
party at the risk & cost of the Contractor with additional 10% overhead charges plus applicable
GST as per extant GST Laws and all costs incurred in connection therewith shall be recoverable
from the Contractor by the GIPCL / Engineer In-charge as a debt or may be deducted by him
from any money due or to become due to the CONTRACTOR.
6. SETTLEMENT OF DISPUTES
a. Any disputes or difference of opinion between parties arising out of the contract to the extent
possible shall be settled amicably between the parties. If amicable settlement cannot be
reached all the disputed issues shall be resolved through arbitration before a Sole Arbitrator
appointed by Managing Director, GIPCL according to the provisions of The Arbitration &
Conciliation (Amendment) Act, 2019, as amended from time to time. The place of arbitration
shall be at Vadodara/ Surat or any other place within state of Gujarat.
b. Work under the contract shall be continued by the contractor during arbitration proceedings
unless GIPCL shall order suspension thereof or any part thereof in writing or unless the
matter in such work cannot possibly be continued unless the decision of the Arbitration
proceedings is obtained.
7. INTERPRETATION OF CLAUSE
In case of disputes as regards interpretation of any of the clauses or specification, the decision
of CGM (THERMAL) - GIPCL will be final and binding on the Contractor.
8. EMPLOYEE’S COMPENSATION INSURANCE
Contractor shall take all risk Insurance Policy to cover all his workmen/employees, staff
applicable under the Employee Compensation Act 1923 or any amendment thereof as also
insurance cover for third party liability. The Contractor shall keep the GIPCL indemnified from all
liabilities arising out of his action in pursuance of this contract. The E.C. Policy should be obtained
from Surat Jurisdiction and shall be assigned to GIPCL. E.C. Policy should cover the specified
contract period.
Contractor shall also obtain additional Off-duty coverage insurance policy for all his workers.
9. STATUTORY REQUIREMENTS
A. COMPLIANCE OF LABOUR LAWS
The Contractor shall at his own cost comply with the provision of labour laws, rules, orders and
notifications whether central or state or local as applicable to him or to this contract from time to
time. These Acts/Rules include without limitation of the followings.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
1. Contractor shall be solely responsible and shall fully comply with all the provisions of
all the labor laws applicable such as the Minimum Wages Act, 1948, Contract Labor
(Regulation & Abolition) Act 1970, Factories Act, 1948, Payment of Bonus Act
Employees Provident Fund and Miscellaneous Provision Act 1952, Industrial Dispute
Act 1947, Workmen Compensation Act 1923, Payment of Gratuity 1972, Interstate
Migrant Workmen Act 1979, Equal Remuneration Act with Rules, Order and
Notifications issued/made there under from time to time.
2. All other Acts, Rules/Bye-Laws, Orders, Notifications etc. present of future applicable
to the Contractor from time to time for performing the contract job.
2.1 The Contractor shall provide and be responsible for payment of Wages, Salaries,
Bonus, Social charges, Insurance, Food, Accommodation, Transport, Medical and
Canteen facilities and other statutory privileges and facilities to his personnel as per
law / rules / regulations and orders of the Central Government, State Government,
Local Authorities or other authorities as are in force from time to time. All employees
of the Contractor shall be employee of the Contractor.
2.2 The Contractor shall have a valid license obtained from Licensing Authority under
the Contract Labor (Regulation & Abolition) Act, 1970 at the time of execution of the
contract covering all his employees working at SLPP site and furnish the same
failing which GIPCL may terminate the contract at its sole discretion.
2.3 The Contractor shall at the time of execution of the contract have a EPF Code
Number obtained from the Authorities concerned under the Employees Provident &
Miscellaneous Provisions Act, 1972 and remit contributions in respect of the
employees employed by him at SLPP Site to the P.F office concerned every month
failing which GIPCL will recover from the outstanding payment to the Contractor
from GIPCL.PF code of Gujarat region should be taken.
2.4 The Contractor shall maintain all records/registers required to be maintained by him
under various labor laws mentioned above and produce the same before the
Statutory Authorities whenever required.
2.5 The Contractor shall also submit periodical reports / returns to the various statutory
authorities such as the Contract Labour (Regulation & Abolition) Act-1970,
Employees Provident Fund Act etc. Under intimation to HR&A dept.
2.6 The Contractor shall not pay less than the Minimum Wages notified by the
Government from time to time to his employees of corresponding categories.
2.7 The Contractor shall be responsible for payment of overtime wages to his workmen,
if any, in case they are required to work beyond the prescribed hours under law as
per applicable rates.
2.8 The Contractor shall take Workmen Compensation Insurance Policy for all his
employees working at SLPP. The Contractor shall indemnify the company against
any liability due to any work injury or accident to any of its employees.
2.9 The Contractor shall in the event any of his workmen / employee sustains any injury
or disablement due to an accident arising out of and in the course of his
employment, provide necessary medical treatment and pay compensation as
applicable, required under the Workmen’s Compensation Act,
2.10 If any of the persons engaged by the Contractor misbehave with any of the officials
or the Company or commit any misconduct with regard to the property of the
Company or suffer from any serious communicable disease, the Contractor shall
replace them immediately.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
2.11 The Contractor shall not engage / employ persons below the age of 18 years.
Employment of women shall be strictly according to applicable laws.
2.12 GIPCL will have right to deduct and disburse the claims of the individual / parties
being a principal employer on any account whatsoever in relation to their
employment with the Contractor. The Security deposit will be released to the
Contractor at the end of the contractual tenure subject to an undertaking by the
Contractor that in the event any of his workmen or the heirs of workmen puts up a
claim for recovery of money due to him from the Contractor before the appropriate
authority under the I.D.Act 1947 or under any other labor laws or for compensation
under the Workmen’s Compensation Act, 1923 and the appropriate authority has
given a direction for making payment the Contractor will meet the same or indemnify
GIPCL if in the event GIPCL pays it as Principal Employer.
2.13 The Contractor shall make payment of wages to his employees on fixed date within
the period specified under the applicable Law, in presence of representative of the
company. He will submit a true copy of wage sheet, attendance register and P.F.
remitted challan on monthly basis to HR&A dept. for verification and record.
2.14 The Contractor shall provide Safety items / kits to his employees such as safety
shoes, goggles, ear plugs, hand gloves, safety belts etc., if any, required under the
2.15 The Contractor shall conduct pre-induction and periodic medical checkup of his
workmen as per applicable laws.
2.16 The Contractor shall be solely responsible for any accident caused to his workers
and should adhere to all rules / regulations as per labor laws of Government and
other statutory laws as applicable.
2.17 The Contractor should register himself under the Contract Labour Act, Employee
Compensation Act and PF Act (Code no. to be mentioned) and submit the copy of
registration certificate and should possess the same from the date of
commencement of work, failing which the contract is liable to be cancelled. The
E.C. Policy copy should be submitted to the GIPCL before commencement of the
work and Labor License should be obtained within one week from the date of issue
of form-V. Contractor should apply for Form-V immediately after receipt of LoI. A
copy of Labour License shall be submitted to GIPCL, HR&A Department.
2.18 Contractor shall have to insure his workmen /supervisors etc. under Group
Insurance scheme.
2.19 The Contractor shall be responsible for compliance of all statutory rules, regulation,
act enforced from time framed by the government such as Factory Act, Employee
Compensation Act, payment of ‘Wages Act’, Minimum Wages Act’, Provident Fund
Act, All Labor Laws Act in respect of employees engaged by him for the work
and shall have to maintain necessary records. In case any amount becomes due
to be payable by him to his employees or to the Government under the above rules,
regulation, Acts, GIPCL reserves the right to recover the same from the running bill
of the contract.
2.20 Documentary evidence of deposit of PF paid shall have to be produced by the
Contractor along with the next bill.
2.21 Records as per the provisions of various statutory Acts will have to be maintained
by the Contractor and submitted as and when required.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
2.22 All employees of Contractor should maintain due discipline and respect local
sentiments. GIPCL reserves the right to direct the Contractor to remove any such
person who does not comply with it.
2.23 The list is indicative in nature and not an exhaustive one. Any
amendment/alteration/Notifications or addition to the existing Law or a new statute
shall automatically and immediately become applicable.
2.24 Annual Health Check up- As per Statutory requirement, Contractor has to inform
workmen deployed at site for annual health check up as per schedule prepared by
HR&A department.
B. LEGAL ASPECTS
1. Contractor shall maintain all register required under the Labour Laws and make the
payment as per the Minimum Wages Act to the workers employed by him.
2. Contractor shall obtain requisite license to carry out this contract under the provisions of
Contract Labour Act, 1970 and maintain necessary records and registers under the said
3. Contractor shall submit a copy of each of the registration certificates with respect to
Employees Provident Fund and Employee Compensation Act within one week time, from
the date of award of this contract.
4. Contractor’s employees, agent or sub-agent shall not smoke or light anything within the
premises of the GIPCL and carry match box / lighter or any other explosive and /or
inflammable material inside the plant.
5. Contractor shall abide by all the statutory rules and regulations like P.F., Labour Laws
6. Contractor shall issue an appointment order to each casual workman stating therein the
nature of job to be performed by him and fix time for which the concerned workmen are
likely to be deployed. Contractor shall also issue a temporary identity card specifying the
period for which the workmen has been deployed.
7. Contractor is fully liable for the persons engaged by him for above work; however, GIPCL
reserves the right to deduct any amount legally justified towards any liability not fulfilled.
8. Contractor shall indemnify GIPCL from any liabilities arising out of the employment of the
9. If the Contractor fails to complete the allocated job within specified time frame, GIPCL
shall get the work done by third party at the risk and cost of Contractor.
10. PAYMENT OF WAGES
Contractor shall be responsible for compliance of all statutory rules, regulation, act enforced from
time framed by the government such as Factory Act, Employee Compensation Act, payment of
‘Wages Act’, Minimum Wages Act’, Provident Fund Act, Payment of Bonus Act, Labour Law Act,
maternity benefit act in respect of employees engaged by him for the work and shall have to
maintain necessary records. In case any amount becomes due to be payable by him to his
employees or to the Government under the above rules, regulation, Acts.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
11. ACCIDENT TO WORKMEN
Contractor shall be fully responsible for injury or death of any of your or third party workmen due
to any act omission / indiscretion on your part while undertaking the work and Contractor shall
fully abide by the statutory requirements of the employee's compensation act. GIPCL shall not
be liable for any compensation due to accident, death or injury to any of Contractor’s workmen
or any third party due to negligence, act or omission on your part.
General area lighting will be provided by GIPCL. However work area specific lighting should be
arranged by contractor.
13. NIGHT/SUNDAY/HOLIDAY SHIFT
The Contractor shall depute qualified and adequate resources in Night shift / Sunday / holidays
for any emergency job, which may come up at Night / Sunday / holiday.
14. SAFETY ASPECT
Contractor shall observe all the safety and security rules and regulation of the GIPCL which are
at present in force and which may come into force during the pendency of the contract. Any
violation of any rules and regulations will entail immediate termination of the contract.
When contractor moves his/her lifting tools and tackles to the plant area, required test certificates
as per the Factories Act 1948, as amended from time to time and the state factories rules has to
be submitted to safety Dept. Safety Dept. will check the certificates and if found okay, then only
materials will be allowed to enter inside the plant. Material inward gate pass will be made only
after certification from Safety Dept. Security Dept. will inform to Safety Dept., as & when such
tools and tackles brought at the gate for making entry in the maintenance site.
The contractor has to submit the list of required safety gears along with safety equipments
available with him/her to safety Dept. Safety Dept. will check for quantity and quality of the safety
gears and then allowed permission of work. Poor quality material will not be allowed to take
inside the Plant. If quantity of required safety equipments is not satisfactory, contractor will not
be allowed to carry out the work using such safety gears inside the Plant for the work.
15. GENERAL SAFETY CLAUSES:
1. The Contractor shall observe and comply, with regard to his workmen working at the SLPP
site, the safety norms as per the safety operating standards.
2. The Contractor shall ensure that his workmen are informed and trained regarding the safety
standards to be adopted while operating within the SLPP Plant & Mines premises and the
Contractor shall brief them regarding the same and use of the Personal Protective Equipment
3. The Contractor shall issue safety shoes and safety helmet of IS standard to all his workmen
immediately on execution of the work and the contractor shall ensure that his workmen wears
the protective equipments at all times during the work operation. Following brand of the safety
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
shoes and helmet shall be issued to contract workmen. Contractor shall issue safety shoes
Sr No. Model Company Specifications
01. Tough Hat, HP-TH Sure Safety
02. V-Gard MSA IS : 2925 – 1984, ANSI / ISEA
03. PN 521 –Shelmet Karam
Sr No. Model Company Specificatio
SSTEELE (Strom) – Double
01. Acme Fabrikplast Co.
TRIMAX(Adjacent) – Double
02. Acme Fabrikplast Co.
03. Worktoes Warren Worktoes - Warren Plus
4. Other safety gears like ear plug, dust mask, hand gloves, safety goggles, gum boots, full
body safety uniform and belts, safety net etc. shall be issued and used as per the job
requirements. Safety helmet shall be of YELLOW COLOUR ONLY. Contractor will procure
safety shoes & safety helmet from a reputed company with at least 12 months’ guarantee
and shall produce the guarantee certificate and IS standard certificate to the safety
department. Contractor should purchase safety shoes of reputed brands. Safety shoes will
be issued every year. IS certificate and guarantee certificate must be obtained from the
vendor and submitted to the Safety department. Safety shoes should be heat, water, oil and
chemical resistant, having an anti-slippery sole of 15298- 2002 make.
5. It is the duty of Contractor to ensure that his workmen are wearing required PPEs as per
work requirement. Contractor should ensure that their workers are wearing Safety helmet,
safety shoes, dust mask, goggles, ear plug etc. at all times when they are at work throughout
the contract period. The Contractor has to maintain the PPE issue registers with signature of
6. Contractor will reissue these PPEs in case of damage or misplacement of the same.
Replacement shall be made immediately.
7. The Contractor shall be responsible for providing first aid or emergency medical help and
treatment to his workmen in the event of any accident or injury.
8. If it is observed that Contractor is not issuing required PPEs timely and that of required
quality, GIPCL will issue the required PPEs to contract workers and back charge the same
with 25% overhead charges plus applicable GST as per extant GST Laws incurred by GIPCL.
9. All lifting tools and tackles shall be duly certified by competent person in conformity with the
statutory requirements and certificate in form no. 10 as per rule 60 of Gujarat Factories Rules,
1963 and section 29 of the Factories Act, 1948 shall be submitted every year before using
such tools and tackles. In case of purchase of new lifting tools and tackles, form no. 10 as
per the said rules shall be submitted before they are taken into use. All lifting tools and tackles
shall be of reputed make having International manufacturing standard and shall be
maintained in proper and workable condition.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
10. The Contractor shall nominate one Safety Officer with required qualification for supervising
the daily job/ shutdown jobs for observing and maintaining the safety aspects at site. He is
solely responsible for any safety measures during maintenance work. He has to ensure that
all the workmen working at site are equipped with essential PPE’s and proper safety
arrangement is made at the SLPP site.
11. After mobilization of any tools & tackles to site, which includes chain pulley blocks, D-
shackles, wire ropes, winch machines, Mobile crane, Hydra etc. shall be offered for
inspection with all above statutory test certificate before using at site for any work. They
should use all tools and tackles only after certification by GIPCL representative/safety officer.
12. When working at height, working on ceiling or roof covered with fragile materials, full body
harness safety belt, ladders and crawling boards shall be used to prevent accident. Further,
during working on height, Contractor should arrange proper scaffolding of still pipes, safety
net, full body safety belt, fall arrestor system etc. Advice and instructions of engineer in
charge/ safety in charge shall be strictly complied with in this regard. All necessary safety
precautions shall be taken by the Contractor to prevent accident and personnel injuries while
working on height.
13. Flash back arrestors made of reputed manufacturer shall be provided on cutting torch, on DA
cylinders and on O2 cylinder. Cylinder caps also required for handling the cylinders at the
work at height area. Gas cylinders shall be transferred through gas cylinder trolley only with
cylinder cap and stored up right (vertical) position only. All gas cylinders shall be hydro tested
/ certified as per gas cylinder rules 2004. Gas cylinders shall be stored, handled as per gas
14. All vehicles shall be operated by licensed drivers only. All vehicles’ PUC to be tested as per
Government approved RTO guidelines. All Vehicles must be parked in Parking space
designated by GIPCL. If any vehicle is found inside the plant premises other than the parking
area such vehicles shall be handed over to Security dept. and their entry shall be cancelled
for movement inside the plant premises with immediate effect.
15. All electrical equipment shall be in good condition and free from any defect. Electrical tools
& equipments i.e. welding machine, grinding and drill machine etc. may be checked by the
electrical engineer of the Contractors regularly, every six month at least and report to be
submitted to concerned HOD and safety dept.
16. During hot work, Contractor will use fire curtains like asbestos sheets or fire blankets to
prevent falling and spreading of sparks and hot material on and around the work area.
Contractor will procure and use such items. ELCB / RCCB shall be provided with rating of 9-
30 milli-amperes on welding machine and all portable power tools.
17. The Contractor shall fill – up Incident notification form (S-I), Incident Investigation form (S-II)
and near miss report within time limit as specified in forms, if any accident, Incident, near
miss occurred while working at SLPP site.
18. Major AMC / ARC Contractor (Where the man power strength is more than 50 and above)
should appoint / nominate one qualified safety officer and he shall be responsible for
addressing all the safety related aspects of execution of contract jobs and he will in close co
ordination with safety officer of SLPP and attend all safety related meeting such as safety
committee, on job safety training etc. Where the Contractual man power is less than 50, the
Site In-charge of the Contractor will act as a Safety Officer and he will perform all the duties
of safety officer as mentioned above.
19. No loose connection / joints allowed in electrical cables during performance of any kind of
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
20. Safety shoes to be issued to female employees also.
21. All the vehicles shall be fit as per RTO guidelines and valid fitness certificate is required as
per RTO guidelines.
22. The Contractor’s nominated safety officer shall be imparted regular on-job safety training like
tool-box talk etc. and submit a record of such training in safety dept, respective dept and
23. The Contractor shall comply all the new requirements related with safety as informed by the
HOD / Safety department from time to time.
24. Penalty to be imposed for Violation of safety norms is proposed as follows:-
The Contractor & Contract workmen shall strictly adhere to Safety standards / Guidelines as per
practices. The list provided below is an indicative list to explain the principles behind safety
practice. If the contract workmen fail to comply with safety standards as per category A, B & C
below, penalty shall be levied on the Contractor as per the table mentioned below:
Category Examples / Cases Penalty
PPEs Working without shoes, dust mask,
A Rs. 100 /- per instant.
Related gloves, safety goggles etc.
Failure to adhere to HSE
guidelines/plans, careless attitude in
material handling,
Machine being used with damaged
machine guard, unsafe electrical
work - workout plug top/improper
electrical joints/cables lying on
ground, electrical equipment working • Rs. 500 /- per instant.
without proper earthing, machine
being used without machine guard, • After three incidence, per
Welding machine without ELCB / incidence Rs. 2,500/-
WI RCCB of proper rating, Gas cylinder
Related without test certificate, Cylinder cap, • Continuous unsafe acts will
NRV / Flash back arrester, Cylinder disqualify the Contractor
trolley etc. from further participation in
Unsafe working practices at height tender of/contract with
more than 3 meters. GIPCL.
Working without permit or non-
compliance with permit conditions
like hot work, height work etc. as
applicable, lifting tools and tackles
being used without third party
inspection certificates in form no.
9/10 as per Factory Act – 1948 etc.
• Suspend the entry gate
Breach of safe practices by a pass for one week.
C particular person repeatedly for three
times • After two suspensions his
gate pass will be cancelled.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
Penalty so levied against the Contractors and company employees will be used during the
observation of National Safety Day.
The Contractor, workmen following good safety practices in their work area continuously
will be rewarded / honored on National safety day.
16. REJECTION OF WORK:
If, as a result of inspection, examination or testing, the GIPCL’s Representative / Engineer
decides that any materials, work or workmanship is defective or otherwise not in
accordance with the Contract, the GIPCL / Engineer / GIPCL’s Representative may reject
such plant, materials, work or workmanship and shall notify the CONTRACTOR promptly,
stating his reasons. The CONTRACTOR shall then promptly make good the defect and
ensure that the rejected item complies with the Contract. If Contractor failed to rectify the
rejected work or workmanship, GIPCL / Engineer reserves the right to deduct or withhold
amount against rejected work or Workmanship. CONTRACTOR shall not entitle for any
claim or release of hold payment until rectify the defect up to satisfactory of GIPCL. If
Contractor failed to rectify any such defective work or workmanship, GIPCL reserve the
right to rectify at risk and cost of the CONTRACTOR and deducted by the GIPCL from any
amount due, or to become due, to the CONTRACTOR’s dues.
If the GIPCL / Engineer / GIPCL’s Representative requires such materials, work or
workmanship to be retested, the tests shall be repeated under the same terms and
conditions. If such rejection and retesting cause the GIPCL additional costs for the
traveling and lodging costs of GIPCL / Engineer’s personal for attending the retest, such
costs shall be recoverable from the CONTRACTOR by the GIPCL and may be deducted
by the GIPCL from any amount due, or to become due, to the CONTRACTOR.
17. GENERAL TERMS AND CONDITIONS:
a. All tools & tackles, labours, equipments, vehicles, tractors, etc., to execute the
contract are in the scope of the contractor. The contractor should ensure that tools
&equipments are in healthy condition.
b. The decision of the Engineer-in-charge shall be final and binding on the contractor
for defining the terms and condition included in this contract.
c. If the work is not found satisfactory, Engineer-in-charge reserves the right to take
suitable action.
d. Contractor shall depute full time independent experienced site-in-charge /
independent site supervisor / s at site. They shall co-ordinate with GIPCL engineer
and shall bear overall responsibility of contract including joint certification, billing etc.
Such person shall function from site office of contractor at SLPP.
e. Contractor shall also nominate one safety supervisor at site and shall submit
nomination of safety supervisor in writing before commencement of contract. Safety
supervisor shall arrange small safety talk on every day morning or whenever required
with all workers working under this contract. He shall coordinate with concern
department’s Engineer-in-charge on daily basis and report daily observations, tool-
box talk records etc. The work shall not be allowed without deploying safety
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
supervisor and a penalty equal to Rs.1,000/- per day absent of safety supervisor shall
be levied from Contractor.
f. Contractor shall strictly follow the existing work permit system of the GIPCL and any
future revisions.
g. The contractor has to take EC insurance policy for their workmen. The contractor has
to submit labour license (if applicable) and PF account number to the Engineer-in-
charge before start the work.
h. The contractor has to do the job timely. GIPCL shall not compromise in delay. In case
of delay of work without any valid reason, the GIPCL reserves the rights to carry out
the work by deploying other agencies at the risk & cost of contractor with additional
10% overhead charges plus applicable GST as per extant GST Laws.
i. Contractor shall mobilize the resources as per need within the period of twenty four
hours. If the contractor fails to mobilize sufficient resources to complete the job in
time, GIPCL will execute the job through other agency at the risk and cost of the
contractor with additional 10% overhead charges plus applicable GST as per extant
j. Contractor should mobilize all resources for efficient & smooth execution of contract
within seven to fifteen days from the date of issue of Letter of Intent/Work Order.
k. The prices / item rates quoted (based on quoted % above/equal or below SoR) shall
remain firm till completion of the contract and any agreed extensions thereafter and
shall not be subject to any price escalation including idle charges for labour,
machinery, overhead expenses etc… due to any reason whatsoever. However
Diesel price variation will be applicable as mentioned in the clause no 2 of Section
D. No price escalation / idle charges shall be entertained due to delay in work on
unavailability of work front, non-issue of work permit, holding of work permit for any
reason, unavailability of contractor’s supervisor, unavailability of contractor’s safety
supervisor, violation of safety rules, unsafe act by any of contractor’s worker,
negligence & ignorance of safety & quality instructions of GIPCL Engineer-in-charge
or any other reason whatsoever.
l. Contractor must fulfill all the safety regulations and to take safety measures to avoid
hazards. Contractor shall arrange all standard adequate healthy safety PPEs like but
not limited to approved quality safety shoes & safety helmets, standard dust masks,
safety goggles, safety hand gloves, etc… as required and shall use exclusively under
this contract for all the time during working at specified locations failing which, the
Engineer-in-charge may hold the work and will take necessary action including
penalty as decided. If the contractor repeatedly violates safety rules / regulations
(more than three successive incidents), Engineer-in-charge may take necessary
action against the contractor, including appropriate financial penalty and / or
termination of contract.
m. One or more jobs may be required to be done simultaneously and contractor shall
mobilize additional resources accordingly.
n. Timely completion of all jobs and works shall be the essence of this Contract.
Contractor should closely monitor each activities and complete the jobs as per the
time given by and under the supervision of the Engineer-In-charge and shall ensure
that sufficient manpower is deployed for the same.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
o. The contractor has to complete the works as per the planning schedule and their
respective supervisor has to interact with Engineer-In-Charge for PTW (Permit to
work), work instruction, Return of permit.
p. The contractor has to submit daily reports showing work carried out with details of
available manpower, equipments / vehicles (tractors) etc.
q. Any job other than the listed jobs in work order shall be executed by the contractor
on instruction from GIPCL and payment shall be made to the contractor on respective
item rate only.
r. The Government of India has enacted the Micro, Small and Medium Enterprises
Development Act, 2006 (the “Act”) and the Act has come into force from October
2006. The Bidder shall confirm whether your organization is registered under the
Micro, Small and Medium Enterprises Development Act, 2006, as amended from
time to time. If your organization is registered under the Act, please specify the
category i.e., Micro Enterprise, Small Enterprise or Medium Enterprise under which
it is registered and kindly attach a copy of your registration certificate.
s. The Bidder shall provide details of registration along with copy of the registration
certificate issued by the District Industries Centre/Department of Industries, etc of the
respective State Government. It is to be noted that large scale industries and trading
firms have been excluded from the purview of the Act.
t. GIPCL is an ISO 9001, ISO 14001, ISO 45001 & ISO 50001 (EnMS) certified
company and GIPCL gives extreme importance to maintain these global standards.
Contractor shall be required to fulfill the requirements of above standards while
working with GIPCL especially for controlling fugitive emission of ash (fly and Bed)
during dozing / leveling / compacting of Ash / Lignite / Limestone activities. Contractor
should ensure that his workmen/labour work in accordance with them.
u. GIPCL shall impart safety training to the Dozer operator/s in phased manner,
considering their working in mines area, and relevant safety aspects / use of safety
PPEs pertaining to it. Contractor shall instruct the operator/s for attending these
training sessions, as and when informed by GIPCL’s Engineer In-charge.
18. CONTRACTOR’S SUPERVISION
The Contractor shall, during the whole time the work is in progress, employ a qualified manpower
/ operator with adequate experience in handing of jobs of this nature and with the prior approval
of the GIPCL / Engineer In-charge. Such manpower / operator shall be constantly in attendance
at the site during working hours. During Contractor’s Supervisor’s absence during working hours,
if unavoidable, and also beyond working hours, when it may be necessary to give directions,
orders may be given by the GIPCL’s Engineer In-charge and shall be received and obeyed by
the Contractor’s superintendent who may have charge of the particular part of the work in
reference to which orders are given. If requested to do so, the Engineer / GIPCL shall confirm
such orders in writing. Any directions, instructions or notices given by the Engineer / GIPCL to
him, shall be deemed to have been given to the Contractor. The representative of the Contractor
shall have all necessary powers to receive materials from the GIPCL, issue valid receipts for the
same, engage labour or purchase materials and proceed with the work as required for speedy
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
None of the Contractor’s Superintendents, Supervisors or labour should be withdrawn from the
work without due notice being given to the GIPCL’s Engineer In-charge; further no such
withdrawals shall be made if in the opinion of the GIPCL’s Engineer In-charge such withdrawals
will jeopardize the required pace of progress / successful completion of the work.
The Contractor shall employ in or about execution of the work only such persons as area careful,
skilled and experienced in their respective trades, and the GIPCL shall be at liberty to object to
and require the Contractor to remove any person employed by the Contractor in or about
execution of works who in the opinion of the Engineer misconducts himself or is incompetent or
negligent in the proper performance of his duties and all such persons shall not again be
employed upon the works without the prior permission of the GIPCL.
Neither the Contractor nor the Engineer shall hire or employ any employee of any other party
except by mutual consent.
19. CONTRACTOR TO REMOVE ALL OFFENSIVE MATTER IMMEDIATELY AND CLEAN-
All loose materials, wastage, packing materials, empty paint drums, cut pieces or other
matter of an offensive nature shall not be deposited on the surface, but shall at once be
carted away by the CONTRACTOR to some pit or place provided by him away from the
site of work and approved by local authorities.
As a part of the work included in this contract, the CONTRACTOR shall completely
remove and satisfactorily dispose of all temporary works & remove scaffolding materials
to the extent directed. He shall tear down and dispose of all temporary works, shall
remove or grade, to the extent directed, all plant and equipment, shall satisfactorily
dispose off all rubbish resulting from the operations under this contract and shall do all
work necessary to restore the territory embraced within the site of his operations to at
least as good order and conditions as at the beginning of the work under this contract.
20. FACILITIES TO BE PROVIDED BY GIPCL
A. The Company shall provide the following facilities to the Contractor at the site:
a. Electricity & water at nearest available one point. Further distribution to be done by
contractor at their cost.
b. Quarter / room & food for supervisors / engineers on chargeable basis in GIPCL’s
township at discretion of GIPCL if available. Food on chargeable basis at GIPCL’s
Industrial Canteen as available. If not available, contractor to make his own
arrangement for lodging and boarding locally or as appropriate at his cost.
c. Workshop facility as available at site only. However contractor may visit the workshop
to ensure the existing facility. For the facilities other than available, contractor has to
carry out the job outside at their own cost.
d. First aid facilities as available on chargeable basis. If not available contractor to make
his own arrangement for the same locally or as appropriate at his cost.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
Apart from the above, no other facilities shall be provided by GIPCL.
B. GIPCL shall also conduct an orientation program appraising the workmen regarding the
safety norms and measures to be observed during work operations at the plant site.
21. WORK MEASUREMENT / CERTIFICATION
On daily basis, the Contractor shall take the certification form GIPCL Engineer In-charge
regarding daily work carried out in line with the tender and as per GIPCL engineer instructions.
This daily certification of measurement of work shall be the basis of processing your monthly bill.
For Package (A) of Tender, the weighment of the Ash disposed / dumped at specified locations
of Mines pit on day to day basis shall be the basis for the Operation of Dozer. The Contractor
shall have to doze / level / compact the dumped Ash on day to day basis. The certification for
Dozer operation shall be based on the complete dozing of the previously dumped Ash at location
directed by Engineer in-charg (Ash dump-yard) after physical verification for proper leveling /
compacting before the said certification. The weighment at AHS Weigh Bridge shall be treated
as actual quantity of Ash disposed / dumped. If Weigh-bridge is out of order, the average weight
derived by previous record or the decision taken by the Engineer In-charge in this regard, shall
be considered as the quantity of Ash dumped in the mines pit for dozing and
dozing/compacting/Leveling of the same shall be considered for work certification. For Package
(B), the actual measured (and certified by Engineer In-charge) Dozer Run Hours shall be
considered for work measurement / certification.
22. PUBLIC HOLIDAYS
The Contractor shall be responsible for giving benefit to all his employees, employed in
whatsoever capacity, Nine (9) Public / Paid holidays and the same shall be notified in advance
and due communication thereof shall be made to the Management.
23. FORCE MAJEURE
The performance of the obligations herein contemplated may be suspended without incurring the
penalty in the event of the subsistence of Force Majeure conditions.
If a Force Majeure situation arises, the affected Party shall promptly notify the other Party in
writing of such conditions and the performance shall be suspended as per mutual agreement.
For the purposes of this clause, ‘Force Majeure’ means an event beyond the control of the Party
and not foreseeable by the Party and shall include events of floods, explosions, riots, wars,
hurricane, epidemics, any other Act of God, quarantine restrictions, terrorism, government
actions and provided always that such acts result in the impossibility of the further performance
of the contract.
The Contractor shall indemnify and keep harmless GIPCL from and against all actions,
proceedings, claims, demands, losses, costs, damages and expenses whatsoever which may
be brought against or suffered by GIPCL which it may sustain, pay or incur as a result of or in
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
connection with the performance/ purported performance / non-performance of the contract by
the Contractor.
In case, in any litigation pertaining to labour employed through Contractor if any direction or order
is issued by court at any point of time the Contractor shall comply with and implement such
direction or order whether passed at the time of award of contract or during the pendency of
contract. Further, the Contractor shall indemnify the GIPCL against all consequences arising and
affecting GIPCL owing to the compliance of the orders by the Contractor.
25. GOVERNING LAW AND JURISDICTION
This tender document and contract shall be governed by the laws of India and the Courts at Surat
shall have jurisdiction regarding the same.
26. Where any portion of the General Condition of Contract is repugnant to or at variance with
any provisions of the Special Condition of Contract, then unless a different intention
appears, the provision of the Special Conditions of Contract shall prevail to the extent of
such repugnancy of variance.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
SPECIAL CONDITIONS OF CONTRACT
1. DETAILED SCOPE OF WORK:
(1A) Package - A: Dozing / Compacting / Leveling of Ash and other works at pre-
designated locations of Mines pit:
GIPCL Power plant generates Fly Ash & Bed Ash which is suitable for manufacturing bricks,
paving blocks, hollow blocks, etc. The nearby local land losers / brick manufacturers lift entire
quantity of ash from power plant for their use. These local customers do not lift ash completely /
partially When there is less demand of ash based product in the market or heavy rainfall or during
festival times such as Diwali, Holi etc. So it is disposed at pre-designated locations of mines
area. The Scope of Work here shall be to Doze / Compact and Level the disposed quantity of
Ash at pre-designated locations of Lignite mines pit on day to day basis, as and when required.
The estimated quantity of Ash which may be required to be disposed and hence subsequently
dozed/compacted/leveled at mines during the proposed Contract period shall be as per the
Section E – Schedule of Quantities and Price. This quantity may increase or decrease, which
shall depend upon the frequency & volume of rainfall. If there is intermittent rain fall & volume of
rain is less, the estimated disposal quantity may be very less.
The Scope of Work shall cover Hiring of Dozer D-80 or of equivalent capacity on Metric Tonne
(MT) basis for following:
▪ During the monsoon period and any other lean period during the Contract period at any time,
Fly Ash / Bed Ash will be transported to Lignite mines for dumping purpose. As soon as Ash
is unloaded at site, it is to be dozed & leveled immediately.
▪ Arrangement of water hose and spraying of water for compacting the dozed ash, as and
when required or as instructed by Engineer-in-charge.
▪ The delay in Dozing of ash will block the approach area for further Transportation & Unloading
at designated point. So, it is very much essential to keep the dozer in running condition for
▪ It may be noted that, the Contract will operate as & when required basis. However
Contractor has to ensure 365 days availability of Dozer along with operator.
1. The weighment for the actual Ash disposed / dumped at the below specified locations of
Mines pit shall be done at GIPCL’s AHS Weigh-bridge.
2. If at any point, the Weigh Bridge is found in-operative or out of order, average weight
transported of previous one month will be considered for billing purpose.
3. Followings are the pre-designated locations of Lignite Mines pit / any other locations where
Contractor shall have to execute the work :
(i) at a one way distance of 0 km to < 3 km from Fly Ash Silos – 3 & 4;
(ii) at a one way distance of > 3 km to < 6 km from Fly Ash Silos – 3 & 4;
(iii) at a one way distance of > 6 km to < 9 km from Fly Ash Silos – 3 & 4;
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
(iv) at a one way distance of > 9 km to < 12 km from Fly Ash Silos – 3 &
4. The total estimated quantity of Ash to be dozed/compacted/leveled, during the Contract, shall
be as specified in Section – E. The quantity of ash may vary depending on the performance
of the plant, volume of Rain fall, the off take of Ash by the local land losers / brick
manufacturers etc. Company shall allow brick manufacturers to lift the ash, as much quantity
as they can lift. So in case if Contract is not executed or partly operated, GIPCL shall
not be responsible for any type of idle charge.
(1B) Package-B: Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction
at in-plant and ELHS stock pile area & other miscellaneous works:
The Scope of Work shall cover Hiring of Dozer D-80 or equivalent capacity on Running Hour
basis for following:
➢ The compaction of lignite / limestone at in-plant, out plant and ELHS stockpile layer wise.
➢ Pushing of Lignite and Limestone at in-plant stockpile, out plant stockpile, ELHS stockpile
and at feeder breaker end.
➢ For lying of conveyor belt and lifting of take up counter weights in Maintenance work and any
other jobs as per the requirement.
Note: Considering the case of Dozer break-down and parallel work requirement for
Package A and Package B, and parallel work to be carried out at different locations of
Mines pit, Contractor may have to arrange additional Dozer (model D-80 or equivalent
dozing capacity), at GIPCL–SLPP site, without any cost implication to GIPCL.
Followings shall form the part of Scope of Work for both Package - A and Package – B for
the Contractor:
1. The Dozer of model D-80 / equivalent equipment deployed at Site shall be equipped with an
Hour Meter for measurement of the Running Hours for the Operation of Dozer. Further, the
Dozers shall be retained at Site till the completion of work assigned by Engineer In-charge,
on day to day basis.
2. In normal day, Contractor shall keep Dozer from 8:30 am to 5:30 pm. However in case of
urgency, Contractor shall make the Dozer available in one hour notice other than above time,
if required so.
3. Contractor shall mobilize the replacement for all the vehicles deployed by him at site,
immediately on any breakdown of the respective equipment / machinery.
4. The mobilization of Dozer between intermediate locations of Mines, where the Dozing of Ash
shall have to be carried out as per the Scope of Work of Contract, or the mobilization of Dozer
from any AHS locations to LLHS locations and vice versa shall not be payable to the
Contractor and shall be in Contractors’ scope. The Contractor may consider tentatively
12 Nos. of such mobilization of Dozer per Annum (approx. 4 hours of Dozer running
per to & fro mobilization) for execution of inter-departmental scope of work (between
Package – A and Package – B)
5. While executing the contract, if any legal situation, local litigations, etc. arises, it will be the
responsibility of Contractor to manage amicably without any financial burden to GIPCL.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
6. During execution of contract, Contractor shall follow all the safety norms, legal / statutory
compliances, etc. as applicable time to time.
7. Contractor has to designate a person as a supervisor to look after and coordinate the daily
activities. The supervisor shall report to concerned Engineer In-charge of GIPCL and get the
job certified on daily basis. The daily reports duly certified by GIPCL Engineer In-charge shall
be submitted along with the monthly bill and the payment shall be made on the basis of the
8. Mobilization period: Initial mobilization period from the Date of Award of Contract shall
seven (7) days. If the Contractor fails to mobilize sufficient resources to complete the job in
time, GIPCL may execute the job through other agency at the risk and cost of the contractor.
9. All statutory requirements applicable for working in Power Plant and Mines area shall be
adhered to and followed.
10. On completion of work, the Contractor shall promptly demobilize from the site and leave the
place in a manner as directed by the OWNER / Engineer In-charge, including cleaning of the
11. Contractor shall report to Ash Handling department for Package-A. pertaining to any issue
regarding the Dozing of Ash at pre-designated locations of Mines pit and LLHS department
for Package-B pertaining to any issue regarding the Dozing of Lignite/Coal and other works
12. No damages to GIPCL property or any public property shall be admissible.
13. All tools and plants and consumables shall be in the scope of contractor.
14. Contactor has to provide mobile phone to its dozer operator for ease of communication while
working in mines area.
1.1 SPECIFIC REQUIREMENT
Contractor shall submit copies of the following documents immediately on Award of Contract:
❖ Suitable / Valid Driving licenses for Dozer Operators (suitable Earth mover category).
❖ R.C. book of Vehicles deployed at site.
❖ Valid Insurance coverage of Vehicles deployed at site.
❖ Valid Fitness certificates, if applicable, of Dozer(s)
❖ Valid P.U.C, if applicable, of Dozer(s).
❖ Vocational Training certificate issued under VT rule
❖ Medical of Driver/ Dumper Operator - as per Mine Rule
• Under - performance of work:
The daily operating hours may be from 07.00 am to 09:00 pm in critical times. Contractor shall
have to doze / compact / level the dumped Ash or push / lift / compact Lignite, as and when
required, as directed by Engineer In-charge, by 9:00 pm of the respective day. If the Contractor
shall not be able to achieve the above, as per requirement, by 9.00 pm of the particular day, and
especially for Package – (A), if Ash dumping shall be hampered, it will be considered as Under
performance and GIPCL shall be free to deploy any other party to get the work done at the risk
and cost of Contractor. In case of such urgency, Contractor shall be prepared with the
required resources for the Dozing / compacting / leveling of up to 1,500 to 2,000 MT of Ash
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
If Contractor Under performs as above for more than five (5) times in a Fortnight period,
GIPCL reserves the authority to terminate the Contract immediately and forfeit the
Security deposit of the Contractor.
1.2 FAILURE DURING EMERGENCY
During any emergencies, Contractor shall have to carry out the work by deploying additional
required resources within four (4) hours of intimation, failing to which GIPCL reserves the right
to carry out this work by engaging any other party at the risk and cost of Contractor. The
expenditure occurred due to such situations, the Contractor will be held responsible & the same
will be recovered from the Contractor’s monthly bill / any other pending bills along with 10%
Overhead charges plus applicable GST as per extant GST Laws. For repetitive failure of such
work for more than two incidents, GIPCL reserve the right to terminate the entire contract by
forfeiting all pending dues, Security Deposit, after giving 15 days notice to the Contractor & this
will be binding to the Contractor.
1.3 TO REMEDY DEFECTIVE WORK
If the work or any portion thereof shall be damaged in any way excepting by the acts of the
GIPCL, or if defects not readily detected by proper inspection shall develop before the final
completion and acceptance of the whole work, the Contractor shall forthwith make good, without
compensation, such damage or defects in a manner satisfactory to the Engineer In-charge /
GIPCL. In no case shall defective or imperfect work be retained even if Contractor followed all
technical specifications. GIPCL will not compromise for quality of materials, works &
The Contractor shall remain liable under the provisions of this clause notwithstanding the passing
by the GIPCL of any certificate, final or otherwise or the passing of any accounts.
2. DIESEL PRICE VARIATION
Diesel price variation will be applicable only if diesel price increase or decrease more than 5%
over the base price of diesel.
i) Base price will be the average of last 30 days diesel price at nearest PSU outlet (Nani
Naroli) from plant from the date of publication of tender.
ii) For calculation of diesel price variation, Monthly average diesel price for the claimed
billing period ( generally 21st to 20th ) will be considered.
iii) Diesel price variation will be applicable only on 60% component of respective items
mentioned in the Section-E of tender.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
Effect of change in diesel price on SoR will be calculated as shown in below table. Diesel rate
considered here for calculation is indicative only.
Calculation for increase of Diesel price for item as mentioned in Sr. No. A
1 SoR rate Rs / Ton
2 Base Price of Diesel Rs/Lit
3 Monthly Average Price of Diesel Rs/Lit
4 Difference in Diesel Price (3-2) Rs/Lit
5 Change in Diesel Price (4/2*100) %
Change in Diesel Price which is not applicable as per tender
7 Change in Diesel Price which is applicable (5-6) %
8 Variable Component Specified in Tender %
9 Rise in SoR (1*7*8/10000) Rs / Ton
10 New SoR Rate after increase of diesel price (1+9) Rs / Ton
Calculation for decrease of Diesel price for Fly Ash Dozing item Sr. No. A of
1 SoR rate Rs / Ton
2 Base Price of Diesel Rs/Lit
3 Monthly Average Price of Diesel Rs/Lit
4 Difference in Diesel Price (3-2) Rs/Lit -10
5 Change in Diesel Price (4/2*100) % -10.20
Change in Diesel Price which is not applicable as per tender
7 Change in Diesel Price which is applicable (5-6) % -5.20
8 Variable Component Specified in Tender %
9 Rise in SoR (1*7*8/10000) Rs / Ton -0.50
10 New SoR Rate after decrease of diesel price (1+9) Rs / Ton
Calculation for increase of Diesel price for item as mentioned in Sr. No. B
1 SoR rate Rs / Hr
2 Base Price of Diesel Rs/Lit
3 Monthly Average Price of Diesel Rs/Lit
4 Difference in Diesel Price (3-2) Rs/Lit
5 Change in Diesel Price (4/2*100) %
Change in Diesel Price which is not applicable as per tender
7 Change in Diesel Price which is applicable (5-6) %
8 Variable Component Specified in Tender %
9 Rise in SoR (1*7*8/10000) Rs / Hr
10 New SoR Rate after increase of diesel price (1+9) Rs / Hr
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
Calculation for decrease of Diesel price for item as mentioned in Sr. No. B
1 SoR rate Rs / Hr
2 Base Price of Diesel Rs/Lit
3 Monthly Average Price of Diesel Rs/Lit
4 Difference in Diesel Price (3-2) Rs/Lit -10
5 Change in Diesel Price (4/2*100) % -10.20
Change in Diesel Price which is not applicable as per tender
7 Change in Diesel Price which is applicable (5-6) % -5.20
8 Variable Component Specified in Tender %
9 Rise in SoR (1*7*8/10000) Rs / Hr -56.20
10 New SoR Rate after decrease of diesel price (1+9) Rs / Hr
3. PRICE & RATES
The rates quoted by the Bidder in the online Price Bid shall be inclusive of cost of all labour,
supervision, cost of safety supervisor, shifting, transportation, loading, unloading, fuel
,equipment, all tools & tackles, safety equipments & PPEs, Royalties, Rents, GST, Stamp Duties,
Central or State Government or Local body or Municipal Taxes or Duties, Turn over Tax, Work
Contract Tax and / or any other duty / tax levied by the Central, State Government or other Public
bodies etc... and such other costs that are not specifically mentioned herein but will be incurred
by the Contractor for the satisfactory and timely completion of the work. The quoted rates shall
be deemed to include for everything mentioned in the specification, all leads & lifts, Contractor’s
overheads & profits for due performance of the work under this contract and such other costs
that are not specifically mentioned herein but will be incurred by the Contractor for the satisfactory
and timely completion of the work. The rates shall also include cost for mobilization /
demobilization of manpower, equipments, materials, etc.
The quoted rates by the Contractor shall be firm throughout the Contract period and also during
extension, if required and shall not be subject to any escalation in prices, idle charges for
equipment / machinery, labour, overhead expenses etc. However Diesel price variation will be
applicable as mentioned in the clause no 2 of Section D. No idle charges shall be paid due to
any reason whatsoever and due to delay in work by Contractor or due to non-availability of work
front by GIPCL or any reason whatsoever.
The price / rate quoted by Contractor shall be considering mobilization of all required manpower,
tools & tackles, materials, equipment for timely and satisfactory completion of all Scope of work.
The value and/or quantum of work may be increased or decreased depending upon day to day
requirement. However, item rates remains unchanged (except change due to Diesel price
variation) and the payment shall be made as per the actual quantity executed as informed &
certified by GIPCL representatives.
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
3.1 TERMS OF PAYMENT
A. Conditions of Payment:
The Contractor shall raise the running Invoices in duplicate every month in respect of the work
performed or completed during the month along with the documents as hereinafter provided. On
receipt of the invoice complete in all respects and with all the said documents, the payment in
respect of the same shall be made within 21 days of such receipt of a complete invoice as per
the following terms of payment:
(i) 100% of monthly RA bill along with 100% taxes shall be released against the work
executed duly certified by GIPCL, Income Tax (IT) will be deducted at source from
monthly RA bills as per the rules in force.
(ii) Security deposit at 10% of Annual Contract value excluding GST shall be submitted as
per Clause no.: 1 of SECTION - C. Security deposit will be returned to the Contractor
without any interest after retention period of three months from actual contract completion
date as certified by Engineer-in-charge as per Clause no.: 1 of SECTION - C.
(iii) GST shall be paid along with bills after fulfillment of following terms:
(a) Submission of copy of registration certificate issued by GST Authority (to be
furnished only once).
(b) Citing the GST Registration no. And the date of Issue of Registration certificate on
(c) Claim of GST amount with percentage (%) separately shown on the invoices.
(d) The Contractor shall be required to submit the proof of payment of GST in previous
month/quarter, as may be applicable as & when demanded by
GIPCL/Owner/company.
(e) The Bidder shall inform the Owner in the event of its registration certificate is
cancelled or discontinued for whatsoever reason.
(f) The vendor shall also mention on their invoice the HSN/SAC code as applicable
under the GST laws under which GST is levied and a self certified authentic third
party evidence (www.cbic-gst.gov.in) shall be adduced, one time, to that effect by
(iv) At the time of submission of the first monthly RA Bill, the Contractor shall submit a
certificate from Engineer In-charge regarding availability of required equipments
machineries with due healthiness, other required vehicles etc at site. The Contractor shall
also furnish the checklist as per Annexure enclosed with the SECTION - F of tender
document along with the RA Bill of respective month.
(v) The Contractor shall submit his Final Bill within a period of four months of the expiration
or earlier termination of the contract or any extensions that may be granted by GIPCL to
the Contractor. GIPCL shall not entertain any bill for any work item after expiration of
period of four months.
(vi) The Contractor shall include all his claims in the Final Bill submitted by him and
accordingly the final bill submitted by the Contractor shall be deemed to be inclusive of
all and whatsoever the claims that the Contractor may have from GIPCL. The Contractor
shall not be entitled to claim any amounts which are not mentioned in the Final Bill and
the Contractor shall be deemed to have waived any claims not mentioned in the Final Bill
and shall not be entitled to recover the same from GIPCL subsequent to the submission
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
of the Final Bill on any account and GIPCL shall stand absolved of all its liabilities in
respect of any such claims not raised by the Contractor in his Final Bill.
B. Validity and Uniformity of Rates
The rates shall be firm and valid for the period of two years of the Contract Period and shall
remain unaltered during Contract Period. However Diesel price variation will be applicable as
mentioned in the clause no 2 of Section D.
3.2 SUBMISSION OF TECHNICAL DOCUMENTS TO THE ENGINEER IN-CHARGE:
Contractor shall submit following documents to the Engineer In-charge for verification purpose
• Measurement sheets along with record duly signed by authorized representative of
Contractor and GIPCL Engineer.
The bill will not be entertained without submission of relevant documents.
3.3 SUBMISSION OF STATUTORY COMPLIANCES WITH PERIODICAL /
MONTHLY RA BILL(S)/FINAL RA BILL:
Contractor shall submit one time or regularly, as applicable, the following documents alongwith
the periodical/monthly RA bill/Final RA bill.:
(i) Notarized Indemnity Bond as per standard Performa, in case of Final bill.
(ii) No claim - No arbitration certificate as per Performa at Annexure-C in Section-F,, after the
final bill amount is certified by GIPCL for payment and the same is made known to the
contractor by GIPCL & accepted by the contractor.
Bill submitted without any of the above documents shall not be processed for payment.
3.4 MOBILIZATION DURING EXECUTION OF WORK
a. Initial mobilization: After issue of LOI/ Work order, contractor has to mobilize all resources
within 7 days at site. Subsequently the contractor shall mobilize resources at site as per
need within period of four (4) hours as directed by GIPCL.
b. Contractor shall provide required separate & independent site supervisors who will be
responsible for supervision and execution of job in specified time with respect to quality,
specifications, site preparations, safety, co ordination with GIPCL, joint measurements, etc.
The supervisors shall coordinate with the Engineer In-charge of GIPCL for proper execution
c. The resources required for execution of above jobs will vary from time to time, hence
Contractor shall mobilize the resources accordingly.
d. Contractor shall provide accommodation for the persons deployed by him for the work at his
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
3.5 QUANTITY OF WORK
The estimated quantities of work required to be carried out by the Contractor are as given in the
Section - E (Schedule of Quantities and Price). Estimated Quantities shall vary according to the
exigencies of work at site. However, the rates quoted by Bidder shall remain firm irrespective of
any variation in estimated quantities. Contractors shall engage required nos. of workmen /
machinery / equipment along with required tools & tackles as per work load and emergency
situations throughout the contract period to perform his contractual duties.
In case, contract quantity / amount exhausted before completion of contract period, GIPCL
reserve the rights to increase the quantities or contract amount for successful completion of entire
contract period. Contractor shall responsible to complete the particular job up to entire
satisfaction of Engineer In-charge. The item rates remain firm & unchanged (except change due
to Diesel price variation) till completion of the contract and any agreed extensions thereafter and
shall not be subject to any escalation, idle charges for labour, machinery, overhead expenses
etc. for any reason whatsoever. However Diesel price variation will be applicable as mentioned
in the clause no 2 of Section D. The quantum of work of individual item may be up to any extent
depending upon requirement. Under this contract, Contractor has to execute all work as per the
Plant requirement.
3.6 GENERAL CONDITIONS OF CONTRACT
General Conditions of Contract (Section-C) and detail specification prepared by the company will
be applicable for this contract. The same is enclosed herewith. Bidders are advised to go through
Where any portion of the General Conditions of Contract is repugnant to or at variance with any
provisions of the Special Conditions of Contract, then unless a different intention appears, the
provision of the Special Conditions of Contract shall prevail to the extent of such repugnancy of
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
SCHEDULE OF QUANTITIES AND PRICE
Biennial Rate Contract (BRC) for Hiring of Dozer (model D-80 or equivalent) for
(A) Dozing / Compacting / Leveling of Ash at pre-designated locations of Mines
pit / any other locations, and (B) Pushing / Lifting of Lignite, Limestone, Lignite
stock pile compaction at In-plant and ELHS stock pile area & other miscellaneous
works at Surat Lignite Power Plant – 4 x 125 MW, Unit # 1 to 4 (Contract Period:
Brief Total Biennial SoR
Scope of UoM Biennial amount (G)
No. Description (g)
Work Qty (excl. GST)
A. Hiring of Dozer of model D-80 or equivalent capacity for dozing / compacting /
leveling of Ash and other works at pre-designated locations of Mines pit / any
(model D-80 Rate
or excluding Will be derived
1 equivalent) MT 1,00,000 GST to be after filling of
for dozing / quoted by rate by bidder
leveling / bidder
B. Hiring of Dozer of model D-80 or equivalent capacity for Pushing / Lifting of
Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile
area & other miscellaneous works
excluding Will be derived
equivalent) detailed in Running
2 1,000 GST to be after filling of
for pushing / section - Hours
quoted by rate by bidder
lifting / D above.
Will be derived
Total Contract Value for two (2) years
after filling of
(excluding GST)
Will be derived
Total Contract Value for two (2) years
after filling of
(including GST)
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
LIST OF ANNEXURES & FORMS
CHECKLIST FOR PASSING THE BILLS
For the month of :
1) Work Order / P.O. No. & :
2) Nature of work :
3) Duration of Work Order : From to
4) Maxi. No. of manpower per day : M F Total
deployed in the month.
5) Details of Labour License : Valid up to for
6) Details of E.C Policy : Valid up to for
7) Documents attached for verification : Wage & Attendance Sheets.
for the previous month. Yes/No
P.F Challan Yes/No
8) Documents attached for verification : Bonus Payment Register
(in case of Final Bill) Yes/No
: Leave wage register Yes/No
9) Security Deposit / Retention Money : Yes / No if yes, Rs.
Date: Signature of Contractor
with official stamp
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
PROFORMA FOR CONTRACT SECURITY-CUM-PERFORMANCE GUARANTEE BY
SELLER / CONTRACTOR
(To be executed on non-judicial stamped paper of approximate value)
1. WHEREAS Gujarat Industries Power Company Limited having its office at PO: RANOLI, Dist.
Vadodara – 391 350, Gujarat State, India (hereinafter referred to as “The Company/Owner”
w h i c h expressions shall unless repugnant to the subject or context includes its legal
representatives, successors and assigns) has entered into a contract with M/s.
………………………………../ has placed a purchase order on
M/s………………………….(hereinafter referred to as “Contractor(s)/ Seller(s)” which
expression shall unless repugnant to the subject or context includes their legal
representatives, successors and assigns ) for …………………………….on the terms and
conditions as set out inter alia, in the Company‟s contract No./ P.O.No.…………..date
…………and various documents forming part thereof hereinafter referred to as the “said
contract” which expression include all amendments, modifications and/ or variations thereto
and where as the Contractor(s)/ Seller(s) has agreed for due execution of the entire contract
and guarantees its performance including any parts executed through any other agencies/
subcontractors AND WHEREAS one of the conditions of the “said contract” is that
“contractor(s)/seller(s) shall furnish to the owner a Bank Guarantee from a bank for ….%
(……….percent) of the total value of the “said contract” against due and faithful performance
of the “said contract” including performance guarantee obligations of the
contractor(s)/seller(s) for execution/ supplies made under the “said contract.”
2. We …………………………….Bank having its branch office at ……….……..do hereby agree
and undertake to pay the amount due and payable under this guarantee without any demur
merely on a demand from the Company stating that in the opinion of the Company, which is
final & binding, the amount claimed is due by reason of default made by the Contractor(s)/
Seller(s) in performing any of the terms & conditions of the said Contract including defect
liability obligations, in fulfilling the performance guarantee obligation or loss or damage
caused to or would be caused to or suffered by the Company by reason of any breach by the
said Contractor (s)/ Seller(s) of any of the terms & conditions of the contract. Any such
demand made on the Bank by the owner shall be conclusive as regards the amount due and
payable by the Bank under this guarantee. However our liability under this guarantee shall be
restricted to Rs. ……(Rupees………………………only).
3. We undertake to pay to the Company any money so demanded not withstanding any dispute
or disputes raised by the contractor(s)/ Seller(s) in any suit or proceeding pending before any
office, court or tribunal relating thereto our liability under this present guarantee being absolute
and unequivocal. The payment so made by us under this bond shall be a valid discharge of
our liability for payment there under. Our liability to pay is not dependent or conditional on the
owner proceeding against the Contractor(s)/ Seller(s).
4. The guarantee herein contained shall not be determined or affected or suspended by the
liquidation or winding up, dissolution or change of constitution or insolvency of the said
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit / any other locations and (B)
Pushing / Lifting of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other
miscellaneous works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
Contractor(s)/ Seller(s) but shall in all respect and for all purposes be binding and operative
until payment of all money due or liabilities under the said contract(s)/ Order(s) are fulfilled.
5. The Bank further unconditionally agrees with Gujarat Industries Power Company Limited
(GIPCL) that Gujarat Industries Power Company Limited (GIPCL) shall be at liberty, without
the Bank’s consent and without affecting in any manner the Bank’s obligation under this
Guarantee, from time to time, to:
a. Vary and / or modify any of the terms and conditions of the Agreement.
b. Extend and / or postpone the time for performance of the obligations of the Contractor
under the Agreement.
c. Forbear or enforce any of the rights exercisable by Gujarat Industries Power Company
Limited (GIPCL) against the Contractor under the terms and conditions of the Agreement.
6. This guarantee shall be in addition to and not in substitution or in derogation of any other
security held by Gujarat Industries Power Company Limited (GIPCL) to secure the
performance of the obligations of the Contractor under the Agreement.
7. No action, event or condition, which by any Applicable Law should operate to discharge the
Bank from liability hereunder, shall have any effect and the Bank hereby waives any right it
may have to apply such law, so that in all respects its liability hereunder shall be irrevocable
and, except as stated herein, unconditional in all respects.
8. This guarantee will remain valid up ____________________ days or ______________
whichever is earlier. The Bank undertakes not to revoke this guarantee during its currency
without previous consent of the OWNER/PURCHASER and further agrees that if this
guarantee is extended for a period as mutually agreed between bidder & owner/purchaser,
the guarantee shall be valid for a period so extended provided that a written request for such
extension is received before the expiry of validity of guarantee.
9. We ……………Bank further agree with the Company that the company shall have the fullest
liberty without our consent and without affecting in any manner our obligations hereunder to
vary any of the terms and conditions of the said Contract(s)/ Order(s) or to extend the time of
performance by the said Contractor(s) Seller(s) from time to time or to postpone for any time
or from time to time any of the powers exercisable by the Company against the said
Contractor(s)/ Seller(s) and to forbear or enforce any of the terms and conditions relating to
the said Contract(s)/ Order(s) and we shall not be relieved from our liability by reason of any
such variation, or extension being granted to the said Contractor (s) / Seller(s) or for any
forbearance, act or omission on the part of the Company or any indulgence by the Company
to the said Contractor(s)/ Seller(s) or by any such matter or thing whatsoever which under the
law relating to sureties would, but for this provision, have affect of so relieving us.
10. Notwithstanding anything contained herein before, our liability shall not exceed
Rs…………….(Rupees…………only) and shall remain in force till..……..Unless a demand or
claim under this Guarantee is made on us within three months from the date of expiry we shall
be discharged from all the liabilities under this guarantee.
Corporate Seal of the Bank Signature of duly Authorized person
By its constitutional Attorney On behalf of the Bank
With Seal & Signature code
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY DEPOSIT
(To be executed on non-judicial stamped paper of appropriate value)
1. WHEREAS M/s.Gujarat Industries Power Company Limited having its
Corporate Office at PO: R A N O L I , Dist.Vadodara – 391 350, Gujarat State,
India (hereinafter called “The Company Owner” which expression shall
unless repugnant to the subject or context includes its legal representatives,
successors and assigns) has issued tender paper vide its Tender
---------- (hereinafter called “the said tender”) to M/s.
……………………………(hereinafter called the said Tenderer(s)” which
expression shall unless repugnant to the subject or context includes their legal
representatives, successors and assigns and as per terms and conditions of
the said tender, the tenderer shall submit a Bank Guarantee for
Rs.………. (Rupees……………..only) towards earnest money in lieu of cash.
2. We ……………………………..Bank having its branch office at
……… do hereby undertake to pay the amount due and payable under this
guarantee without any demur, merely on a demand from the Company stating
that in the opinion of the company which is final and binding, the amount
claimed is due because of any withdrawal of the tender or any material
alteration to the tender after the opening of the tender by way of any loss or
damage caused to or would be caused or suffered by the Company by reason
of any breach by the said tenderer(s) of any of the terms and conditions
contained in the said tender or failure to accept the letter of Intent
Agreement or that the amount covered under this Guarantee is forfeited.
Any such demand made on the Bank by the owner shall be conclusive as regards
the amount due and payable by the Bank under this guarantee, However, our
liability under this guarantee shall be restricted to an amount not exceeding
Rs………………..(Rupees………………..only).
3. We undertake to pay to the Company any money so demanded
notwithstanding any dispute or disputes raised by the tenderer (s) in any
suit or proceeding pending before any office, court or tribunal relating thereto
our liability under this present guarantee being absolute and unequivocal. The
payment so made by us under this bond shall be a valid discharge of our liability
for payment there under. Our liability to pay is not dependent or conditional
on the owner proceeding against the tenderer.
4. The guarantee herein contained shall not be determined or affected or
suspended by the liquidation or winding up, dissolution or change of
constitution or insolvency of the said tenderer(s) but shall in all respect and for all
purposes be binding and operative until payment of all money due or liabilities
under the said contract(s)/ Order(s) are fulfilled.
5. The Bank further unconditionally agrees with Gujarat Industries Power Company
Limited (GIPCL) that Gujarat Industries Power Company Limited (GIPCL) shall be
at liberty, without the Bank’s consent and without affecting in any manner the Bank’s
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
obligation under this Guarantee, from time to time, to:
a. Vary and / or modify any of the terms and conditions of the Agreement.
b. Extend and / or postpone the time for performance of the obligations of the
Contractor under the Agreement.
c. Forbear or enforce any of the rights exercisable by Gujarat Industries Power
Company Limited (GIPCL) against the Contractor under the terms and conditions of
6. This guarantee shall be in addition to and not in substitution or in derogation of any
other security held by Gujarat Industries Power Company Limited (GIPCL) to secure
the performance of the obligations of the Contractor under the Agreement.
7. No action, event or condition, which by any Applicable Law should operate to
discharge the Bank from liability hereunder, shall have any effect and the Bank
hereby waives any right it may have to apply such law, so that in all respects its liability
hereunder shall be irrevocable and, except as stated herein, unconditional in all
8. We ……………..Bank Ltd. further agree that the guarantee herein contained shall
remain in full force and effect during the period that would be taken for the
finalization of the said tender and that it shall continue to be enforceable till the said
tender is finally decided and order placed on the successful tenderer(s) and
or till all the dues of the company under or by virtue of the said tender have been
fully paid and its claims satisfied or discharged or till a duly authorized officer of the
company certifies that the terms and conditions of the said tender have been fully
and properly carried out by the said tenderer (s) and accordingly discharges the
9. That t h e O wn e r Company will have full liberty without reference to us and without
affecting this guarantee to postpone for any time or from time to time the exercise
of any of the power of the owner under the tender.
10. Notwithstanding anything contained herein before, our liability shall not exceed
Rs…………………. (Rupees…………………………only) and shall remain in force
till…………….. (Date to be filled up shall be 180 days from the date of submission
Bank Corporate Seal of
the Bank By its
constitutional Attorney
Signature of duly Authorized person
On behalf of the Bank
W ith Seal & Signature code
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
4.0 ANNEXURE – D
PROFORMA CERTIFICATE
(No claim, No arbitration)
Chief General Manager (Thermal)
Gujarat Industries Power Company Limited,
Surat Lignite Power Plant,
Village: Nani Naroli, Ta. Mangrol,
Dist. Surat – 394112 (Gujarat).
We hereby confirm with free consent as under:-
1. The measurements certified in final bill are full and final. We accept all the certified
measurements and no claim related to the measurement is left.
2. The payment certified in that or above referred LoI / contract is full and final. We accept
this, and no claim related to payment is left.
3. The rates of the LoI / contract and its amendments are firm till completion of contract and
extension period. We shall not claim any escalation against these rates.
4. Along with the contract referred, the ARBITRATION CLAUSE also perishes i.e. we will not
resort to arbitration.
5. No extra items are left to be settled.
6. We do not have any claims against any item related to the LoI than those items certified
7. We are accepting the recoveries or hold amount from our bills, if any, made by GIPCL
against non compliance or as decided by GIPCL within terms & conditions of contract.
8. We have paid royalties, taxes for all the materials procured by us, for carrying out the
works for above LoI and we indemnify GIPCL from any liability arising thereof.
9. In case of any disputes arising in future related to payment of royalties, all liabilities of
settlement of dispute and its payment if any, will be borne by us.
10. We have paid wages to all the workmen who were deployed by us for carrying out above
referred work as per prevailing Minimum wages act. We have also fulfilled all requirements
of the P.F. Act. We have maintained all records necessary as per the statutory
requirements. We hereby indemnify GIPCL from any disputes arising in future related to
payment of labours, Provident Fund, etc. and confirm that all liabilities of settlements of
disputes and their payment is our responsibility.
The above confirmation will come into effect as soon as payment from final bill after due
recoveries will be received by us.
Signature, Stamp and date
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
5.0 ANNEXURE – E
Schedule of Deviation from Technical Specification and Commercial Terms and
All the deviations from the terms & conditions of contract shall be filled by BIDDER
clause by clause in this schedule.
Sr. No SECTION TENDER DEVIATION
The bidder here by certifies that the above mentioned are the only deviations from OWNER’s
Tender enquiry. The bidder further confirms that in the events any other data and information
presented in the BIDDER’s proposal and accompanying documents are at variance with
specific requirements laid out in the OWNER’s Tender Document, then the latter shall govern
and will be binding on the BIDDER for quoted price.
SIGNATURE …………………
DESIGNATION ……………..
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
6.0 ANNEXURE – F
Declaration cum Undertaking for Safety Laws and Regulations Compliance
(To be submitted on Company’s Letter Head)
I ______________________ on behalf of ………Name of Party/Company………..hereby
confirm, agree and undertake that all the Statutory and Safety Laws and Regulations of the
applicable Authority/ies shall be strictly followed for all types of works at the site during the period
of the Contract, if awarded to me.
Signed and Stamped by the
Authorized Signatory of the Bidder
Declaration for Contractual Litigations
(To be submitted on Company’s Letter Head)
Please Tick (√) whichever is correct option
I ______________________ on behalf of ………Name of Party/Company………..hereby confirm
that I /We have
a. Not invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings
/ Depts. / Authorities and Govt. of Gujarat supported companies / undertakings /
organizations for the last three ( 03) years. There are no ongoing/pending legal
matter(s) with any of the Govt. of Gujarat Undertakings / GoG supported
Companies, including GIPCL.
Please Tick ( )
b. Invoked legal recourse e.g. litigation against any Govt, of Gujarat Undertakings
/Depts. / Authorities and Govt. of Gujarat supported companies / undertakings
/organizations for the last three (03) years.
Please Tick ( )
If “b” is applicable, please submit the details for the same.
The above is true, as on date, to the best of my knowledge. Any breach/ false statement in this
regard shall amount to disqualification of the Bid being submitted herein.
Signed and Stamped by the
Authorized Signatory of the Bidder
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
PARTICULARS OF THE BIDDER
Sr. No. Particulars Please provide information here.
1. Name of Bidder
2. a. Registered Office Address:
b. Address for Correspondence:
3. Contact Details:
Contact Person Name
Telephone No. :
Year of establishment
COMPANY SEAL SIGNATURE …………………
DESIGNATION ……………..
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
PROCEDURE FOR MAKING ONLINE PAYMENT OF EMD/SD/TENDER FEE
1. For making online payment, first go to the website: www.gipcl.com
2. Then, click on the caption/link as can see like:
“Click here for Making Online Payment of EMD/SD, Advance for Ash, DM water
(The link is visible as horizontal highlighted below Tenders - News & Update Section. Can be
seen in below screenshot)
3. After clicking the link the new page will open. On this page, No need to enter User Name
and Password. Directly click on “Payment Form” given below the sign in option.
4. After clicking the “Payment Form”, the vendor has to enter the details asked which will be
self explanatory. It is desired that all the information may be filled correctly so that the
payment made can be tracked.
If the some required fields are not known/available, vendor may write “Not Available” and then
proceed. E.g. some information like Party code is not available to vendor or GST No. not
available with vendor.
Optional Note: Although mentioned as above can be proceeded with “Not available”, It will
be appreciated that regular vendors may obtain the party code from Materials Dept. or
Concerned Person, so that the vendor can be identified. The same party code may be used
for future transactions also.
After entering the details, click on SUBMIT Button.
5. The vendor/Party will be redirected to Payment Gateway. By selecting the desired payment
mode, payment can be made:
6. After making the payment, the receipt will be generated which has to be shared with
Concerned Person of GIPCL.
Important Note: Please note that for making online payment through the above gateway, the
charges* as below will be applicable, which has to be borne by Vendor/Party making the
Payment Mode Charges
Net Banking Rs.9 + GST
Credit Card 0.75% + GST
International 3.00% + GST
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
10.0 ANNEXURE-J
CERTIFICATE OF COMPLIANCE BY CONTRACTOR
(To be submitted with each monthly bill on letter head along with labour compliance records)
of.........................to.......................... at Gujarat Industries Power Company Limited –
Surat Lignite Power Plant, Nani Naroli. I undertake to be bound by all the provisions of
the Contract Labour (Regulation & Abolition) Act 1970 and the Contract Labour
(Regulation & Abolition) Rules 1972, The Employees’ Provident Funds and
Miscellaneous Provisions Act 1952, Minimum Wages Act 1948, Payment of Wages Act
1936 and Payment of Bonus Act 1965 and all other applicable labour laws in so far as
the provisions are applicable to me in respect of the employment of contract labour by
Authorized Signature with Stamp
Place: Nani Naroli
Tender Document for Biennial Rate Contract for Hiring of Dozer of D-80 Model or equivalent for: (A) Dozing /
Compacting / Leveling of Ash and other works at pre-designated locations of Mines pit and (B) Pushing / Lifting
of Lignite, Limestone, Lignite stock pile compaction at in-plant and ELHS stock pile area & other miscellaneous
works at GIPCL - SLPP [Tender Ref. No. SLPP/AHS/BRC/Dozer/2027-29]
11.0 ANNEXURE – K
GUJARAT INDUSTRIES POWER COMPANY LIMITED
PO : RANOLI, DIST : BARODA –
Reference PO No. Date:
Integrity Pact No.: Contract Period:
To create an environment where Business Confidence is built through best business practices
and is fostered in an atmosphere of trust and respect between providers of goods and services
and their users for the benefit of stakeholder, society and the nation.
GIPCL’S COMMITMENT PARTY’S COMMITMENT
Not to bring pressure / recommendation
To maintain the highest ethical standards in
from outside GIPCL to influence its
business and professions
Not to use intimidation, threat, inducement
To ensure maximum transparency to the
or pressure of any kind on GIPCL or any
satisfaction of all stakeholders.
of it's employees.
To fulfill the terms of agreement / contract To be prompt and reasonable in fulfilling
and to consider objectively the viewpoints of the contract, agreement and legal
other stakeholders. obligations.
To ensure regular and timely release of To provide goods and / or services timely
payments for works done/services provided as per agreed quality and specifications.
To ensure that no improper demand is made To maintain the general discipline in our
by employees or by anyone on our behalf. dealings and transactions.
To give maximum possible assistance to all
the Vendors / Suppliers / Service Provider To be truthful and honest in furnishing
and others to enable them to complete the information.
Not to divulge to others any information,
To provide all necessary information to
business details about GIPCL made
suppliers /contractors relating to contract /
available during the course of business
job to facilitate them to complete the
relationship without the written consent of
contract / job successfully in time.
To ensure that no hurdles are caused to Not to enter into cartel / understanding
vendors / suppliers / contractors in whether formal or informal so as to
execution of agreement / contract / work. influence the price.
Seal & Signature Seal & Signature
(GIPCL’s Authorized signatory) (Party’s Authorized signatory)
Designation : Designation:
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
EMDBG.pdf
Tender_BSC_Hiring of D-80 Dozer_2027-29 355264.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .