Loading…
Loading…
Tender Value
₹61.4 L
EMD Value
₹61,437
Closing Date
20 Jul 2026, 4:30 pmClosed
Sri Lakshmi Narasimha swamy Temple, Balasinganapal
Sri Lakshmi Narasimha swamy Temple, Balasinganapalli(V), Chennuru(M), Kadapa District
Construction of Compound wall and Three Storied Rajagopuram to Sri Lakshmi Narasimha swamy Temple, Balasinganapalli(V), Chennuru(M), Kadapa District
958768
P/COE/1027/2026
OPEN - NCB
Civil Works
YSR
14 documents required · 13 mandatory · 1 optional
₹2,175
₹61,437
11 Jul 2026
6 Jul 2026
6 Jul 2026
Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wall in ordinary soils and depositing on bank with an initial lead of 10m and 1m additional lift charges over the initial depth up to 3m including all operatio Compoundwall
Filling with carted coarse sand in trenches,sides of foundations and basement with initial lead in layers not exceeding 15cm thick,watering and ramming including cost and conveyance of water to work site and all peraitonal,incidental ,labour charges,hire charges of T&P etc., and overheads & contractors profit complete for fnished item of work(APSS NO.309&310)
Supply of hard granite cut stone slabs for flooring form Perur quarry including cost and converyance etc., complete with the following specifications.a) The size of the stone slab should not be less than 0.61mx 0.45m(2'-0"x1'-6").b) The thickness of the stone slabs should not be less than 100mm ( 4") in all sides. c) The top of the slab should be dressed with the following dressings properly.d) All the sides of the slabs should be dressed with following dressing to a depth of 40mm (11/2") from top surface to suit proper alignment and jointing with side slabs.e) The slabs should be laid horizontally and jointed properly to alignment over sand bed (excluding cost of sand bed).cement mortar bed.f) The joint of the slab should not be more than 6mm (1/4" thick).g) The slabs should be jointed with C.M(1:3) and the mortar should not come over the slab for the above item the rate is including cost and conveyance of all materials to site of work including necessary labour charges, dressing, laying, jointing but excluding cost of sand for bedmortar the bed will be paid under relevent item .( Cement mortar of 0.005 Cum/ Sqm should be used for joints.) I) a)cost of hard granite stone steps
b) Three line dressing for hard granite stone not less than 12" x 24" uniform size and thick ness not less than 4"
c) Labour charges for jointing for hard granite and soft variety
Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and under flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, excluding seigniorage charges, sales & other taxes on all materials and including all charges for machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc., and overheads & contractors profit complete for finished item of work. (APSS No. 402)
R.R. Masonry in CM ( 1: 6 ) using rough stone approved quarry including cost, seigniorage, conveyance of all material like cement, sand, granite stone water etc to work site from approved source and all labour charges, curing, centering etc. complete for levelling Course Concrete. As per APSS 612
Brick masonry for superstructure in CM (1:6) mix using second class bricks having crushing stsrength of not less than 35kgs/ Cm2s including cost,seigniorage and conveyance of all materials like cement, sand , bricks and water etc to site from approved sources and all labour charges curing, scaffolding etc. complete for basement and superstrucuture as per APSS No. 504 for Super Structure.
V.R.C.C (1:11/2:3) using 20 MM size HBG graded chips with nominal mix SS-5 using necessary quantity and excluding cost and conveyance of steel per cum of concrete including cost and conveyance of all materials and all labour charges, seigniorage, curing, centering ( Using Steel) etc., complete as per APSS No.403 with BIS 456-2000 but excluding the cost of steel and its fabrication charges.a) plinth beam
Providing High Yield Strength Deformed Bars of Fe 415 Grade of different diametres including cost & conveyance of steel including cost of binding wire and labour charges for fabrication such as cutting, bending and cranking rods, tying grills with binding wire etc complete.
Plastering with CM( 1:5) mix using 20mm thick including cost and conveyance of all materials like cement, sand and water and labour, curing, scaffolding, seigniorage charges etc., complete. As per APSS No.904
Supply and fixing of iron grill enclosure using L angles / flats / suqare with necessary locking arrangements including the cost and conveyance of all materials and labour charges etc complete
Plastic Emulsion painting in two coats in primary coat including cost and conveyance of all materials and labour charges etc complete
Painting with synthetic enamel paint two coats over a primary coat of approved make colour and shade duly cleaning the surface dusting of the loosed particles after rubbing, then applying two coats of synthetic enamel paint to obtain. Smooth surface and in case of bad workman ship applying one (or) more coats as required after rubbing down the surface including labour charges,cost of paint, operation charges etc complete for finished work
Earth work excavation and depositing on banks with an initial lead of 10m and initial lift of 2m in soils like in rock like shales, ordinary gravel and rock like shales, ordinary gravel stoney earth and earth mixed with fair sized boulders etc completewhich do not require blasting etc., complete for foundations as per APSS No.308 for Three Storied Rajagopuram
Sand with filling sand from approved sources in layers not exeeding 15 cm thick, consolidating each deposited layer basement with Sand with watering and ramming with heavy rammers including all water leads, including charges for all operations, incidential, labour charge as per APSS-310
Plain Cement Concrete ( 1 :4 : 8 ) proportion using 40mm size HBG metal from approved quarry including cost, seigniorage, conveyance of all material from approved source and all labour charges, curing, centering etc. complete for levelling Course Concrete. As per APSS 402
R.R. Masonry in CM ( 1: 6 ) using rough stone approved quarry including cost, seigniorage, conveyance of all material like cement, sand, granite stone water etc to work site from approved source and all labour charges, curing, centering etc. complete for levelling Course Concrete. As per APSS 612
V.R.C.C (1:11/2:3) using 20 MM size HBG graded chips with nominal mix SS-5 using necessary quantity and excluding cost and conveyance of steel per cum of concrete including cost and conveyance of all materials and all labour charges, seigniorage, curing, centering ( Using Steel) etc., complete as per APSS No.403 with BIS 456-2000 but excluding the cost of steel and its fabrication charges..a) plinth beam
b)lintles 1st story
c) Rcc Roof Slab 150cm Thick 1st story
Providing High Yield Strength Deformed Bars of Fe 415 Grade of different diametres including cost & conveyance of steel including cost of binding wire and labour charges for fabrication such as cutting, bending and cranking rods, tying grills with binding wire etc complete.
Ornamental brick masonry in (1:5) mix using 2nd class bricks including cost and conveyance of all materials and labour charges etc complete for Rajagopuram .up to Prastharam level
b)above Prastharam level for vimanam 1st story
Supplying and fixing of granite stone door frame including cost and conveyance of all materials and labour charges etc complete a) cost and conveyance of stone at site for Rajagopuram
b) Dressing of stone with reqquired ornamentation as epr plan such as rough dressing carving of padamam in top stone at centre and bottom stone side at center padmam and plan palamana dressing in 5 line dressing.
c) fixing in position above 9'-0" to 13'-0"
Special type ornamental plastering in CM 1” to 1¼” thick base plastering in (1½:1¾)in CM i(1:3) and top finishing ½ thick with (1:2) to bring the required ornamentation including cost and conveyanceof all materials,labour charges all incidential and operational charges curing etc complete finished item of work in site for external surface as per approved drawing and as directed during execution including preparation and fixing pre cost pillars,kudam,palaka vedika,lathalu in uttara, eludandkam,pothikas,nasigudu-pushpa puskala adisthranam wherever necessary. up to Sthambhavargam level
b)above Sthambhavargam level for Vimanam 1st story
c)Mahanasi Over Rajagopuram
Supply and fixing of scaffolding to structure including cost and conveyance of all materials such as casino poles,bamboos,bamboos flat form nails and coirope complete a) Up to 20'-0" Height
b) above 20'-0" to 30' Height
c) up to 30' to 45' height
Supply and fixing of iron grill enclosure using L angles / flats / suqare with necessary locking arrangements including the cost and conveyance of all materials and labour charges etc complete
Providing cement vigrahams using cement fine sand iron bars mesh,bricks bats,flat tiles ,pieces etc including cost and conveyance of all materials and labour charges etc complete..a) for 1st storyDwarapalakas for Rajagopuram
2nd storyDwarapalakas
3rd story Gopanadharies
Plastering in CM (1:5) 20mm thick including cost and conveyance of all materials and lab our charges etc complete a) inside Rajagopuram
b) 1st story inside
c) 2nd story inside
d) 3rd story inside
Flooring with Cheery red 18-20mm thick upto 2.43m granite stone slabs (i.e. of shades like paradiso / bala flower / copper silk / laka red / lavender blue) with borders and design as per the pattern approved by the Engineer-in-Charge of length not less than 2.43 mts set over base coat of cement mortar (1:8) , 20mm thick using screened sand over CC bed already laid or RCC roof slab including neat grey cement slurry of honey like consistency spread @ 3.3 Kg per sqm and jointed neatly with white cement paste mixed with pigment of matching shade to full depth including cost and conveyance of all materials like cement , sand , water , granite slabs etc., to work site and all operational, incidental labour & lift charges, half rounding the edges of treads , polishing charges and seigniorage charges and all other taxes on all materials, cost of base coat and overheads & contractors profit complete for finished item of work (S.S.701 & special) for Rajagopuram
Supplying and fixing of copper stupi with stupi dandam randram stoen (gandhapu-Raie) including the cost and conveyance of all materials and labour charges etc complete for Rajagopuram
Supplying and fixing of best teak wood door shutter with two leaves with single / double rows of padmas with necessary fittings and locking arrangements including the cost and conveyance of all materials and lab our charges etc complete for Rajagopuram
Painting to new walls with 2 coats of acrylic emulsion paint weather proof water-based, modified acrylic with silicon additives exterior grade having VOC (Volatile Organic Compound ) content less than 50 grams/ liter. of approved brand and colour over a base coat of appropriate primer of approved brand,of first grade making 3 coats in all to give an even shade after thouroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost and conveyance of all materials to work site and operational, labour charges and incidental charges such as scaffolding, lift charges etc., complete for finished item of work as per SS911 for External walls.for Rajagopuram
Painting with synthetic enamel paint two coats over a primary coat of approved make colour and shade duly cleaning the surface dusting of the loosed particles after rubbing, then applying two coats of synthetic enamel paint to obtain. Smooth surface and in case of bad workman ship applying one (or) more coats as required after rubbing down the surface including labour charges,cost of paint, operation charges etc complete for finished work for Rajagopuram
Providing Concealed wiring / in concealed wiring using 19MM dia PVC pipe using 1 /18 , 5/16 VIR copper wires for different points with necessary specials like bends , cupplings , celing roses , including the cost and conveyance of all materials and labour etc complete. for Rajagopuram
stage.html
html • 0.01 MB
aoc.html
html • 0.01 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.01 MB
Tender Document.docx
TENDER_DOCUMENT • 0.18 MB
Balasinganapalli L.S provisions 2-7-2026.xls
TENDER_DOCUMENT • 0.03 MB
Balasinganapalli boq.xls
TENDER_DOCUMENT • 0.10 MB
DETAILS OF BOQ balasingannapalli.docx
TENDER_DOCUMENT • 0.01 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].