| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹21.6 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹24.9 L+₹3.3 L (15.2%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹29.7 L+₹8.1 L (37.3%)Rejected-AOC | L3 | Rejected-AOC L3 |
Tender Value
₹28.4 L
EMD Value
₹50,000
Closing Date
25 Nov 2023, 6:00 pmClosed
Executive Engineer pazhassi Irriga
Office of the Executive Engineer pazhassi Project Division No 2 Kannur 670002
GENERAL Kadavathur Distributory PyIP Rejuvenation of Kadavathur Distributory of Mahe Branch Canal Desilting and lining work for the year 2023 24 General Civil Work
2023_Irrig_622973_1
IRR/PI/TR/2900/2023_5_1_1/1
Open Tender
Civil Works - Canal
Item Rate
365 days
Kadavathur
Please refer Tender documents.
10 documents required · 10 mandatory
₹2,760
Yes
₹50,000
Yes
6 Jan 2024
17 Nov 2023
29 Nov 2023
17 Nov 2023
25 Nov 2023
17 Nov 2023
Amount
Appendix-1 -Desilting and Felling trees
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
OD22219/2023-2024:Removing and cleaning the deposited silt from the UT/Flume by mechanical<br> means (Hydraulic Excavator)/manual means including providing safety measures like oxygen mask, lighting<br> arrangement and getting out the excavated silt and other debris within a distance of 50metre and including<br>all labour charges , watering charges etc complete as per the direction of officers at site All kinds of soil<br>Details of cost for 10 cum.<br>MACHINERY:
2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth
2.33.2:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 60 cm girth up to and including 120 cm girth
Appendix-2- Lining
15.2.1:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix)
2.1.1:Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5m in width as well as 10 sqm on plan including disposal of excavated earth up to 50 m and lift up to 1.5 m, disposed soil to be levelled and neatly dressed:All Kinds of soil
OD3834/2023-2024:Laterite roughly dressed stones of size 30 X 20 X 20 cm laid dry pitching including cost and conveyance of all materials and all labour charges etc. complete.
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
OD3877/2023-2024:Filling expansion joints with approved joint board 12mm thick giving 25mmx22mm size gap or exposed faces for sealing, including cost and conveyance of all materials and labour charges etc. complete.
OD3878/2023-2024:Sealing the expansion joint using approved quality sealing compound at gaps (25mmx22mm) already provided at the face of the expansion joint after cleaning the gaps thoroughly including cost and conveyance of all materials and all labour charges for heating the compound, pouring, finishing etc complete
Appendix -3 Construction of abutment ,Toe wall , DR Piching and and Flume
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
4.3.2:Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts
5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
5.1.2:Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size
OD22647/2023-2024:DR PACKING FOR EMBANKMENT - Rough stone dry packing for embankment with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
60.6:PVC WEEP HOLES- Providing weep holes using 75mm dia. PVC pipes working pressure 4kg /sq.cm including cost of materials, conveyance, labour charges etc. complete.
shabeer
SIBIN.T.K.
Bidder Name
P MANOHARAN
SIBIN.T.K.
shabeer
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_937903.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .