Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | R1₹8.0 LAccepted-AOC | R1 | Accepted-AOC Accepted |
Tender Value
₹8.0 L
EMD Value
₹20,100
Closing Date
17 Jan 2020, 4:00 pmClosed
Assistant Executive Engineer,KIP RB Sub Dn.No,26 K
Assistant Executive Engineer,KIP RB Sub Dn.No,26 Karunagappally
Rectification work of Canal
2019_Irrig_320521_4
56/AEE/KIP/KPY/2019-20
Open Tender
Civil Works - Canal
Item Rate
120 days
Sooranad South
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,800
Yes
online
₹20,100
Yes
21 May 2020
9 Jan 2020
18 Jan 2020
9 Jan 2020
17 Jan 2020
9 Jan 2020
Amount
Scheme 1: Rectification of canal lining between ch: 1450 m and 1490 m
2.28.1 : Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od37624/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to line and levels including proper compacting, curing, watering etc complete with all leads and lift etc complete as per specification or as directed by departmental officers at site
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Scheme 2: Rectification of canal lining between ch: 1490 m and 1530 m
2.28.1 : Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.All kinds of soil
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od37624/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to line and levels including proper compacting, curing, watering etc complete with all leads and lift etc complete as per specification or as directed by departmental officers at site
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Scheme 3: Rectification of canal lining between ch: 1530 m and 1570 m
od38058/2019_2020/P2 : Earth work in rough excavation including disposal of excavated earth up to 50m and lift up to 1.50m, disposed soil to be levelled and neatly dessed in all kinds of soil for clearing the canal bed by desilting
50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od38068/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to lines and levels including proper compacting curing , watering etc. complete with all leads and lift etc. complete as per specification or as directed by Engineer in chaege
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Scheme 4: Rectification of canal lining between ch: 1570 m and 1610 m
od38058/2019_2020/P2 : Earth work in rough excavation including disposal of excavated earth up to 50m and lift up to 1.50m, disposed soil to be levelled and neatly dessed in all kinds of soil for clearing the canal bed by desilting
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od38068/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to lines and levels including proper compacting curing , watering etc. complete with all leads and lift etc. complete as per specification or as directed by Engineer in chaege
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Scheme 5: Rectification of pipe chamber between ch: 1750 m and 1850 m
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
26.28.3 : Chipping of unsound/weak concrete material from slabs, beams, columns etc. with manual Chisel and/ or by standard power driven percussion type or of approved make including tapering of all edges, making square shoulders of cavities including cleaning the exposed concrete surface and reinforcement with wire brushes etc. and disposal of debris for all lead and lifts all complete as per direction of Engineer-In-Charge25 mm average thickness
4.1.2 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:1/2:3 (cement : 11/2 coarse sand : 3 graded stone aggregate 20 mm nominal size)
13.7.1 : 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
Scheme 5: Rectification of canal lining between ch: 1610 m and 1650 m
od38058/2019_2020/P2 : Earth work in rough excavation including disposal of excavated earth up to 50m and lift up to 1.50m, disposed soil to be levelled and neatly dessed in all kinds of soil for clearing the canal bed by desilting
50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od38068/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to lines and levels including proper compacting curing , watering etc. complete with all leads and lift etc. complete as per specification or as directed by Engineer in chaege
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Scheme 6: Rectification of canal lining between ch: 1650 m and 1700 m
od38058/2019_2020/P2 : Earth work in rough excavation including disposal of excavated earth up to 50m and lift up to 1.50m, disposed soil to be levelled and neatly dessed in all kinds of soil for clearing the canal bed by desilting
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od38068/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to lines and levels including proper compacting curing , watering etc. complete with all leads and lift etc. complete as per specification or as directed by Engineer in chaege
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Scheme 7: Rectification of canal lining between ch: 1700 m and 1750 m
od38058/2019_2020/P2 : Earth work in rough excavation including disposal of excavated earth up to 50m and lift up to 1.50m, disposed soil to be levelled and neatly dessed in all kinds of soil for clearing the canal bed by desilting
50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge.
15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
od37624/2019_2020/P2 : Cement concrete 1:4:7 using 20mm metal to line and levels including proper compacting, curing, watering etc complete with all leads and lift etc complete as per specification or as directed by departmental officers at site
od37626/2019_2020/P2 : 9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg of hot bitumen, 1 kg of cement and 0.25 cubic metre of coarse sand for expansion joints.
Bidder Name
RAMAN PILLAI N
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_467320.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .