| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1st₹8.7 LAccepted-Finance | ₹8.7 L | 1st | Accepted-Finance 1st Lowest |
| 2 | 2nd₹8.8 LAccepted-Finance | ₹8.8 L | 2nd | Accepted-Finance 2nd Lowest |
| 3 | 3rd₹8.8 LAccepted-Finance MOH SHER MOHAMMAD PILIBHIT | PILIBHIT | UTTAR PRADESH | 262001 | ₹8.8 L | 3rd | Accepted-Finance 3rd Lowest |
Tender Value
₹8.9 L
EMD Value
₹18,000
Closing Date
17 Feb 2026, 2:00 pmClosed
Superintending Engineer
Superintending Engineer Electricity Civil Transmission Circle Transmission Building Mohaddipur Gorakhpur
Civil works related to maintenance of Central Store shed at 132 KV Sub Station Ballia
2026_UPCTL_1112212_1
Short Term T Notice 27(04)/ECTC/GKP/2025-26
Open Tender
Civil Works
30 days
Ballia
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Current Account 39356752800
₹18,000
28 Feb 2026
4 Feb 2026
18 Feb 2026
4 Feb 2026
17 Feb 2026
4 Feb 2026
Civil works related to maintenance of Central Store shed at 132 KV S/S Ballia.
Please Enable Macros to View BoQ information
B.O.Q Civil works related to maintenance of Central Store shed at 132 KV S/S Ballia.(SOR. 05/2024).
Centering and shuttering including strutting, propping etc. and removal of form work for :Foundations, footings, bases for columns(4.3.1)
Concrete work with 40 mm gauge brick ballast obtained from breaking brick bats (brick bats supplied by the department free of cost) in proportion of 12:6:1 in foundation and under floors including cost of all labour, materials, T&P etc required for proper completion of work.(29.01)
Brick work in foundation & plinth with old dismantled bricks (supplied by department free of cost) and coarse sand mortar in 1:6 including supply of all other materials, labour, removing mortar & cleaning of old & used bricks,T&P etc complete.(29.03)
Grouting of vertical or inclined post of pale/chain/security fencing in true level, alignment and in plumb or inclination as required, including cost of all labour, materials and T&P required for proper completion of work. ( Post and concrete for grouting shall be measured separately) (29.21)
Total Rs
Rupees Eight Lacs Eighty Seven Thousands Nine Hundred Sixteen & Paise Fifty Only
J.E S.D.O-II
Conditions:
1. All civil work shall be executed according to the approved drawings of UPPTCL.
2. The quantities in BOQ are tentative and may vary up to any extent or be deleted as per the requirement at site.
3. All civil work shall be carried out as per UPPWD/UPPTCL specification.
4. Rates in BOQ are exclusive of CGST,SGST.Labour tax shall be borne by contractor.
5. Pozzlona Portland cement confirming to IS 1489(Part 1) 1991 of approved quality like ACC,Ultra Tech,Birla or equi.shall only be used.
6. Overweight steel section within tolerance shall be measured at standard weight and underweight steel section within tolerence shall be measured at actual weight.
7. In case any change in Bill of Quantity is suggested by higher authority that will be binding on the contractor.The agreement shall be executed on the approved Bill of Quantity only.
8.Performance Guarantee shall be applicable as per GO 622/23-12-2012-2 Audit/08 dt 08 June 2012.adopted by UPPTCL BOD dated 27.06.2017
9. The 60% amount of bricks available from dismentaling shall be reovered @ Rs. 3744.00/thousand + GST to firm /contractor.
10. The 30% amount of bricks available from dismentaling shall be reovered as brick bats @ Rs. 1680.00/CuM + GST to firm /contractor.
11. The amount of steelavailable from dismentaling will be recovered Rs. 20.00/Kg + GST to firm /contractor.
J.E S.D.O-II
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 14.91 MB
TD2704.pdf
Tender Documents • 0.76 MB
BOQ_2056990.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid