| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.3 LAccepted-AOC | L1 | Accepted-AOC Lowest | |
| 2 | L2₹4.4 L+₹11,538.52 (2.69%)Rejected-AOC | L2 | Rejected-AOC Highest rate hence rejected |
Tender Value
₹4.4 L
EMD Value
₹10,993
Closing Date
15 May 2023, 5:00 pmClosed
Seeja KR
O/o Assistant Executive Engineer Electrical Wing (I) Sub division, Aluva
Fully Comprehensive Annual Maintenance of Karukapilly LIS, and Kuryathode LIS, Under Electrical Lift Irrigation Section Ramamangalam-General Electrical Work
2023_Irrig_553954_16
PWD/BLDG/TR/9490
Open Tender
Electrical Works
Item Rate
365 days
Aluva
Please refer Tender documents.
11 documents required · 11 mandatory
₹970
₹10,993
17 Jun 2023
29 Apr 2023
16 May 2023
29 Apr 2023
15 May 2023
29 Apr 2023
29 Apr 2023 - 12 May 2023
Amount
Overhauling
OD55139/2022-2023:Dismantling the 5 HP motor into stator and rotor, cleaning the windings attending minor repairs, re taping the coils if necessary, varnishing the coils with best quality insulation varnish, cleaning and greasing the bearings with good quality grease, heating the windings, reassembling, test running including scrapping, cleaning and painting with enamel paint.
OD55140/2022-2023:Dismantling the 120 HP motor into stator and rotor, cleaning the windings attending minor repairs, re taping the coils if necessary, varnishing the coils with best quality insulation varnish, cleaning and greasing the bearings with good quality grease, heating the windings, reassembling, test running including scrapping, cleaning and painting with enamel paint.
OD55141/2022-2023:Dismantling the 125 HP motor into stator and rotor, cleaning the windings attending minor repairs, re taping the coils if necessary, varnishing the coils with best quality insulation varnish, cleaning and greasing the bearings with good quality grease, heating the windings, reassembling, test running including scrapping, cleaning and painting with enamel paint.
Lowering / Refitting
OD55142/2022-2023: Lowering down and erecting 5 HP motor/vacuum motor pump set, starter and other electrical accessories,( Accessories when necessary ) and erecting the motor on the base plate coupling with pump, erecting the starter regulator TP switch etc in position giving connections checking correct alignment and trial run on full load
OD55143/2022-2023: Lowering down and erecting 120 HP motor, starter and other electrical accessories,( Accessories when necessary ) and erecting the motor on the base plate coupling with pump, erecting the starter regulator TP switch etc in position giving connections checking correct alignment and trial run on full load
OD55144/2022-2023: Lowering down and erecting 125 HP motor, starter and other electrical accessories,( Accessories when necessary ) and erecting the motor on the base plate coupling with pump, erecting the starter regulator TP switch etc in position giving connections checking correct alignment and trial run on full load
Accessories Supply and Other Items( SITC Should be completed with in 3 Months after executing the Agreement)
OD55146/2022-2023:Supply and filling of transformer oil of good quality to the Transformer /starter/ regulator etc as required
OD55147/2022-2023: Supply and renewal of the LED Indication lamps in panel board after dismantling the damaged one
OD55148/2022-2023:Supply and Installing 20 W LED Tube light.
OD55152/2022-2023:Replacing the damaged bearing, supply and fixing new industrial type ball bearing 6319 2Z C3, SKF / FAG or equivalent, suitable for 120 HP motor / pump set as per the direction of Departmental staff at site.
OD55153/2022-2023:Dismantling the damaged power contactor and Supply, fixing and testing of following capacity 3 pole power contactor, AC 3 rating at 415 V, with AC Coil, Auxiliary contacts, 2 NO/2NC, L&T MNX 185 or equivalent suitable for 120 HP motor's fully automatic star delta starter
90.3.18.1:Supply, fabrication, conveyance and fixing the following sizes of B class GI pipe bent to shape / cut and welded to shape and fixing the same to wall / parapet using clamps as noted along with each size, painting with 2 coats of synthetic enamel paint over a coat of zinc chromate primer, making good the damages, colour washing etc as required.25 mm dia with HG company fabricated clamps
90.15.4.1:Supply Conveyance, installation, testing and commissioning of 20W LED street light output greater than 105lumen/W 4000-6000 K with IP 66 protection LED Chip make Cree/Lumilled/Nichea with power factor greater than 0.95 at full load, internal surge protection up to 8 KV,and Aluminium pressure die-cast Powder coated housing,acrylic cover complete with THD Less than10%, power factor greater than 0.98, RoHS compliant, duly wired up for use on 230 V AC supply. Driver compartment should be seperatly accessible for maintenance (LM 79&80 certificates from NABL accredited Third party lab to be produced mentioning chip manufacturer)
90.14.11.15:MCCB AccessoriesSupply and fixing rotary handle, External type (including BUC handle with door interlock ) in the existing MCCB of rating up to 315-630 A
2.10.1:Supplying and fixing 5 amps to 32 amps rating, 240/415 volts, "C" curve, miniature circuit breaker suitable for inductive load of following poles in the existing MCB DB complete with connections, testing and commissioning etc. as required.Single pole
2.12.1:Supplying and fixing following rating, double pole, 240 volts, isolator in the existing MCB DB complete with connections, testing and commissioning etc. as required.40 amps
2.14.2:Supplying and fixing following rating, double pole, (single phase and neutral), 240 volts, residual current circuit breaker (RCCB), having a sensitivity current upto 300 milliamperes in the existing MCB DB complete with connections, testing and commissioning etc. as required.40 amps
2.10.4:Supplying and fixing 5 amps to 32 amps rating, 240/415 volts, "C" curve, miniature circuit breaker suitable for inductive load of following poles in the existing MCB DB complete with connections, testing and commissioning etc. as required.Triple pole
2.13.1:Supplying and fixing following rating, four pole, 415 volts, isolator in the existing MCB DB complete with connections, testing and commissioning etc. as required.40 amps
2.15.1:Supplying and fixing following rating, four pole, (three phase and neutral), 415 volts, residual current circuit breaker (RCCB), having a sensitivity current upto 300 milliamperes in the existing MCB DB complete with connections, testing and commissioning etc. as required.25 amps
OD247441/2022-2023:Fabricate, Supply and installation of a power failure self trip station, assembled within a GRP (3mm thick)/powder coated GI (1mm thick)/PVC enclosure (4mm thick), circuit wired with a 225 A power contactor, single phase preventer for 125 HP Slip ring motor, with remote ON/OFF push buttons with indication lamps and RYB LED indication lamps at front panel of the box, and control circuit interlocked with suitably supplied and installed auxiliary contacts on the contactor, including provision of suitable PVC cable glands for IN/OUT cables, and including fasteners etc. for installation on to wall/frame/panel/etc.
Periodical Maintenance
OD55154/2022-2023:Fully Comprehensive Annual Maintenance of 5 HP Vacuum motor pump set , D.O.L starter ,controlling electrical accessories , etc complete for a period of 12 months including attending all repairs , reconditioning the damaged parts , replacing spares with original make as per sample , dismantling and refitting , removing foreign bodies , renewal of gland packing , gasket packing , rubber packing , greasing the bearing etc as and when required including overhauling of pump,maintaince of the motor pump sets , pipes , starter and valves electrical accessories etc complete in good working condition(excluding motor rewinding)all time during the period of contract and the faults should be rectified with in the time allowed
OD55155/2022-2023: Fully Comprehensive Annual Maintenance of 120 HP squirrel cage induction motor with split case / End suction pump set , starter, controlling electrical accessories , panel board, etc complete for a period of 12 months including attending all repairs ,overhauling & reconditioning of starter , replacing of damaged coupling bush, carbon brush and coupling bolts, refilling of oil, reconditioning the damaged parts , replacing spares with original make as per sample , removing foreign bodies , renewal of gland packing , gasket packing , rubber packing , greasing the bearing etc as and when required including overhauling of pump and starter ( excluding motor rewinding ) and maintain the motor pump sets starter , electrical accessories etc complete in good working condition all time during the period of contract and the faults should be rectified with in the time allowed .
OD55157/2022-2023: Fully Comprehensive Annual Maintenance of 125 HP Slip ring induction motor with split case / End suction pump set , starter, controlling electrical accessories , panel board, etc complete for a period of 12 months including attending all repairs ,overhauling & reconditioning of starter and slip ring unit, replacing of damaged coupling bush, carbon brush and coupling bolts, refilling of oil, reconditioning the damaged parts , replacing spares with original make as per sample , removing foreign bodies , renewal of gland packing , gasket packing , rubber packing , greasing the bearing etc as and when required including overhauling of pump and starter ( excluding motor rewinding ) and maintain the motor pump sets starter , electrical accessories etc complete in good working condition all time during the period of contract and the faults should be rectified with in the time allowed .
OD55156/2022-2023: Fully Comprehensive Annual Maintenance of 120 HP Slip ring induction motor with split case / End suction pump set , starter, controlling electrical accessories , panel board, etc complete for a period of 12 months including attending all repairs ,overhauling & reconditioning of starter and slip ring unit, replacing of damaged coupling bush, carbon brush and coupling bolts, refilling of oil, reconditioning the damaged parts , replacing spares with original make as per sample , removing foreign bodies , renewal of gland packing , gasket packing , rubber packing , greasing the bearing etc as and when required including overhauling of pump and starter ( excluding motor rewinding ) and maintain the motor pump sets starter , electrical accessories etc complete in good working condition all time during the period of contract and the faults should be rectified with in the time allowed .
Lifting
OD55160/2022-2023: Lifting the 5 HP motor after disconnecting the wire connection, decoupling the pump, detaching from the base plate, starters, TP switches etc. using chain block, rope, chain etc. and placing them conveniently on the platform.
OD55161/2022-2023: Lifting the 120 HP motor after disconnecting the wire connection, decoupling the pump, detaching from the base plate, starters, TP switches etc. using chain block, rope, chain etc. and placing them conveniently on the platform.
OD55162/2022-2023: Lifting the 125 HP motor after disconnecting the wire connection, decoupling the pump, detaching from the base plate, starters, TP switches etc. using chain block, rope, chain etc. and placing them conveniently on the platform.
Overhauling
OD55163/2022-2023:Dismantling the 5 HP motor into stator and rotor, cleaning the windings attending minor repairs, re taping the coils if necessary, varnishing the coils with best quality insulation varnish, cleaning and greasing the bearings with good quality grease, heating the windings, reassembling, test running including scrapping, cleaning and painting with enamel paint.
OD55164/2022-2023:Dismantling the 100 HP motor into stator and rotor, cleaning the windings attending minor repairs, re taping the coils if necessary, varnishing the coils with best quality insulation varnish, cleaning and greasing the bearings with good quality grease, heating the windings, reassembling, test running including scrapping, cleaning and painting with enamel paint.
Lowering / Refitting
OD55165/2022-2023: Lowering down and erecting 5 HP motor/vacuum motor pump set, starter and other electrical accessories,( Accessories when necessary ) and erecting the motor on the base plate coupling with pump, erecting the starter regulator TP switch etc in position giving connections checking correct alignment and trial run on full load
OD55166/2022-2023: Lowering down and erecting 100 HP motor, starter and other electrical accessories,( Accessories when necessary ) and erecting the motor on the base plate coupling with pump, erecting the starter regulator TP switch etc in position giving connections checking correct alignment and trial run on full load
Accessories Supply and Other Items( SITC Should be completed with in 3 Months after executing the Agreement)
OD55171/2022-2023: Supply and renewal of the LED Indication lamps in panel board after dismantling the damaged one
OD55172/2022-2023:Supply and Installing 20 W LED Tube light.
OD55174/2022-2023:Supply and renewal of Three Phase Digital Voltmeter accuracy class 1 in panel board after dismantling the damaged one, L&T or Equivalent make.
OD55176/2022-2023:Replacing the damaged bearing, supply and fixing new industrial type ball bearing 6317 2Z C3, SKF / FAG or equivalent, suitable for 100 HP motor / pump set as per the direction of Departmental staff at site.
OD55177/2022-2023:Dismantling the damaged power contactor and Supply, fixing and testing of following capacity 3 pole power contactor, AC 3 rating at 415 V, with AC Coil, Auxiliary contacts, 2 NO/2NC, L&T MNX 140 or equivalent suitable for 100 HP motor's fully automatic star delta starter
OD248409/2022-2023:Supply & fixing of 2 lock 1 key Castell key lock set for 100A to 800 A SDF
OD248410/2022-2023:Supplying and fixing 5 amps to 32 amps rating, 240/415 volts, "C" curve, miniature circuit breaker suitable for inductive load of following poles in the existing Panel board mounted in DIN rail complete with connections, testing and commissioning etc. as required after dismantling the existing fuse base. Single pole
Periodical Maintenance
OD55178/2022-2023:Fully Comprehensive Annual Maintenance of 5 HP Vacuum motor pump set , D.O.L starter ,controlling electrical accessories , etc complete for a period of 12 months including attending all repairs , reconditioning the damaged parts , replacing spares with original make as per sample , dismantling and refitting , removing foreign bodies , renewal of gland packing , gasket packing , rubber packing , greasing the bearing etc as and when required including overhauling of pump,maintaince of the motor pump sets , pipes , starter and valves electrical accessories etc complete in good working condition(excluding motor rewinding)all time during the period of contract and the faults should be rectified with in the time allowed
OD55180/2022-2023:Fully Comprehensive Annual Maintenance of 100 HP squirrel cage induction motor with split case / End suction pump set , starter, controlling electrical accessories , panel board ,etc complete for a period of 12 months including attending all repairs ,overhauling & reconditioning of starter , replacing of damaged coupling bush, carbon brush and coupling bolts, refilling of oil, reconditioning the damaged parts , replacing spares with original make as per sample , removing foreign bodies , renewal of gland packing , gasket packing , rubber packing , greasing the bearing etc as and when required including overhauling of pump and starter ( excluding motor rewinding ) and maintain the motor pump sets starter , electrical accessories etc complete in good working condition all time during the period of contract and the faults should be rectified with in the time allowed .
Lifting
OD55181/2022-2023: Lifting the 5 HP motor after disconnecting the wire connection, decoupling the pump, detaching from the base plate, starters, TP switches etc. using chain block, rope, chain etc. and placing them conveniently on the platform.
OD55182/2022-2023:Lifting the 100 HP motor after disconnecting the wire connection, decoupling the pump, detaching from the base plate, starters, TP switches etc. using chain block, rope, chain etc. and placing them conveniently on the platform.
POWER ELECTRICALS
Bidder Name
KEYAS ELECTRICALS
POWER ELECTRICALS
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_847618.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .