| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.2 LAccepted-AOC | L1 | Accepted-AOC First lowest | |
| 2 | L2₹6.3 L+₹5,997.92 (0.96%)Rejected-AOC | L2 | Rejected-AOC Second lowest | |
| 3 | L3₹7.4 L+₹1.1 L (18.1%)Rejected-AOC | L3 | Rejected-AOC Third lowest | |
| 4 | L4₹7.6 L+₹1.4 L (21.8%)Rejected-AOC POTTRAYIL HOUSE ANAKKODE MANIKKASSERY | L4 | Rejected-AOC Fourth lowest |
| Sl No | Description | Qty | Unit | sebastian kappen L2 | SATHEESH BABU N L3 | RAMADASAN P N L4 | SHAMSUDHEEN .T.U L1 |
|---|---|---|---|---|---|---|---|
| 1.00V notch drain | |||||||
| 1.00 | 2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. | 95 | sqm | 7.68 ₹729.6 | 8.99 ₹854.05 | 9.27 ₹880.65 | 7.61 ₹722.95 Lowest |
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 17.1 | cum | 298.17 ₹5,098.71 | 348.93 ₹5,966.7 | 359.72 ₹6,151.21 | 295.33 ₹5,050.14 Lowest |
| 1.00 | 4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 11.4 | cum | 6,575.57 ₹74,961.5 | 7,694.9 ₹87,721.86 | 7,932.89 ₹90,434.95 | 6,512.9 ₹74,247.06 Lowest |
| 1.00 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns | 232 | sqm | 320.09 ₹74,260.88 | 374.57 ₹86,900.24 | 386.16 ₹89,589.12 | 317.03 ₹73,550.96 Lowest |
| 1.00 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 50.62 | cum | 7,655.7 ₹3,87,569.81 | 8,958.89 ₹4,53,543.81 | 9,235.97 ₹4,67,570.98 | 7,582.73 ₹3,83,875.71 Lowest |
| 1.01 | 50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete | 260.5 | sqm | 284.97 ₹74,234.69 | 333.48 ₹86,871.54 | 343.79 ₹89,557.3 | 282.25 ₹73,526.13 Lowest |
| 1.01 | 50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete. | 16 | each | 313.03 ₹5,008.48 | 366.32 ₹5,861.12 | 377.65 ₹6,042.4 | 310.05 ₹4,960.8 Lowest |
| 1.01 | OD5391/2025-2026:Engaging Man Mazdoor for various work to execute the work as per the directions of the departmental officers at site in charge | 8 | 1 nos | 896.97 ₹7,175.76 | 1,049.71 ₹8,397.68 | 1,082.18 ₹8,657.44 | 888.47 ₹7,107.76 Lowest |
Tender Value
₹7.6 L
EMD Value
₹18,972
Closing Date
17 Sept 2025, 11:00 amClosed
Assistant Executive Engineer
Head works Sub Division Malampuzha Irrigation
Malampuzha Dam,second largest dam is one of the main tourist attractions in Palakkad, Kerala. During festival seasons
2025_Irrig_796011_1
IRR/PI/TR/2254/2025_5_1_1/1
Open Tender
Repair and Maintenance Works
Item Rate
180 days
Malampuzha
Please prefer tender document
5 documents required · 5 mandatory
₹1,675
₹18,972
Yes
8 Oct 2025
11 Sept 2025
18 Sept 2025
11 Sept 2025
17 Sept 2025
11 Sept 2025
Amount
V notch drain
2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete.
OD5391/2025-2026:Engaging Man Mazdoor for various work to execute the work as per the directions of the departmental officers at site in charge
sebastian kappen (BID ID -2341026)
SATHEESH BABU N (BID ID -2342474)
RAMADASAN P N (BID ID -2342493)
Bidder Name
SATHEESH BABU N
sebastian kappen
SHAMSUDHEEN .T.U
RAMADASAN P N
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1316933.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .