Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹39.5 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹40.1 L+₹57,644 (1.46%)Rejected-AOC | L2 | Rejected-AOC L2 |
Tender Value
₹40.6 L
EMD Value
₹50,000
Closing Date
28 Jan 2023, 5:00 pmClosed
Regional project Director,Regional project managem
REGIONAL PROJECT DIRECTOR,REGIONAL PROJECT MANAGEMENT UNIT,KRWSA, MATHA ARCADE, THODUPUZHA, IDUKKI - 685584
Rectification of 6 nos Small Water Supply Schemes in Manickal Grama Panchayath in Thiruvananthapuram District
2023_KRWSA_551042_1
KRWSA/RPMU/IDKI/SUS/TEN/36/22
Open Tender
Civil Works - Water Works
Item Rate
90 days
Manickal Grama Panchayath in Thiruvananthapuram Di
As per tender condition
5 documents required · 5 mandatory
₹2,500
₹50,000
15 Mar 2023
21 Jan 2023
30 Jan 2023
21 Jan 2023
28 Jan 2023
21 Jan 2023
21 Jan 2023 - 28 Jan 2023
Amount
APPENDIX A (Chitoorkonam)
100.3.2.5 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 6.0 to 7.5 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.6 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 7.5 to 9.0 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.7 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 9.0 to 10.50 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.7.1 Bailing out water with 5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete. NEW DATA (Prepared based on PHED SDB - Item No.1070
5.7 Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size)
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
100.98.236 Supply of uPVC Pipe, IS 4985: 2000 , 10kg/cm2, 90mm Dia.
100.1.1 Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil (Ref. Item No. 2.10.1 of DSR)
100.9.8 Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials). 90 mm nominal outer dia pipes."
Pump & Accessories
APPENDIX B (ERANGALIL)
100.3.2.5 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 6.0 to 7.5 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.6 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 7.5 to 9.0 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.7 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 9.0 to 10.50 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.7.1 Bailing out water with 5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete. NEW DATA (Prepared based on PHED SDB - Item No.1070
5.7 Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size)
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
100.98.236 Supply of uPVC Pipe, IS 4985: 2000 , 10kg/cm2, 90mm Dia.
100.1.1 Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil (Ref. Item No. 2.10.1 of DSR)
100.9.8 Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials). 90 mm nominal outer dia pipes."
Pump & Accessories
APPENDIX C (Pallivila BG)
100.3.2.5 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 6.0 to 7.5 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.6 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 7.5 to 9.0 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.7 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 9.0 to 10.50 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.7.1 Bailing out water with 5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete. NEW DATA (Prepared based on PHED SDB - Item No.1070
5.7 Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size)
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
100.98.236 Supply of uPVC Pipe, IS 4985: 2000 , 10kg/cm2, 90mm Dia.
100.1.1 Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil (Ref. Item No. 2.10.1 of DSR)
100.9.8 Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials). 90 mm nominal outer dia pipes."
Pump & Accessories
APPENDIX B (Sreekrisna BG)
100.3.2.5 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 6.0 to 7.5 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.6 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 7.5 to 9.0 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.7 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 9.0 to 10.50 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.7.1 Bailing out water with 5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete. NEW DATA (Prepared based on PHED SDB - Item No.1070
5.7 Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size)
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
100.98.236 Supply of uPVC Pipe, IS 4985: 2000 , 10kg/cm2, 90mm Dia.
100.1.1 Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil (Ref. Item No. 2.10.1 of DSR)
100.9.8 Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials). 90 mm nominal outer dia pipes."
APPENDIX A (Nettathani BG)
100.3.2.5 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 6.0 to 7.5 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.6 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 7.5 to 9.0 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.3.2.7 Earthwork open well excavation (above water) for wells of dia. upto 2.50 m in ordinary rock and conveying and depositing the spoil within initial lead of 50m and lift from 9.0 to 10.50 m including neat banking. NEW DATA (Prepared based on PHED SDB - Item No.1073 & 1076
100.7.1 Bailing out water with 5 HP engine and pumpset including conveyance to the site, errection, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc. complete. NEW DATA (Prepared based on PHED SDB - Item No.1070
5.7 Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) : 3 graded stone aggregate 20 mm nominal size)
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
100.98.236 Supply of uPVC Pipe, IS 4985: 2000 , 10kg/cm2, 90mm Dia.
100.1.1 Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil (Ref. Item No. 2.10.1 of DSR)
100.9.8 Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials). 90 mm nominal outer dia pipes."
Pump & Accessories
APPENDIX B (NARMADA)
2.8.1 Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil
4.1.8 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
5.2.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up tot floor five level excluding cost of centering, shuttering, finishing and reinforcement :1:1.5:3( 1 cement : 1.5 coarse sand : 3 graded stone
5.9.1 Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
5.9.5 Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers
5.22A.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more
5.22.6 Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
13.1.1 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand)
13.7.1 12 mm cement plaster finished with a floating coat of neat cement of mix:1:3 ( 1 cement : 3 fine sand)
13.48.1 Finishing with Deluxe Multi surface paint system for interiors and exteriors using primer as per manufacturers specifications:Two or more coats applied on walls @ 1.25 ltr/10 sqm over and including one coat of special primer applied @ 0.75 ltr /10 sqm
18.12.6 Providing and fixing G.I. pipes complete with G.I fittings including trenching and refilling etc. External work50 mm dia nominal bore
18.12.8 Providing and fixing G.I. pipes complete with G.I fittings including trenching and refilling etc. External work80 mm dia nominal bore
18.17.4 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) :50 mm nominal bore
18.17.6 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end) :80 mm nominal bore
100.98.235 Supply of uPVC Pipe, IS 4985: 2000 , 10kg/cm2, 75mm Dia.
100.1.1 Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidatingeach deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil
100.9.7 Laying UPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure (excluding cost of pipes and specials). 75 mm nominal outer dia pipes.
E JAYAN RAJ
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_808276.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .