| 1 | L1₹2.8 LAccepted-AOC | ₹2.8 L | L1 | Accepted-AOC Lowest quoted bidder |
| 2 | L2₹2.8 LRejected-AOC | ₹2.8 L | L2 | Rejected-AOC Second lowest quoted bidder |
| Sl No | Description | Qty | Unit | O.K JAMSHEER L2 | mansoorali v L1 |
|---|---|---|---|---|---|
| 1.00DETAILED ESTIMATE | |||||
| 1.00 | 60.8:Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete | 1,092 | 1 cud m | 115 ₹1.3 L | 114 ₹1.2 L |
| 1.00 | 60.5:MS Rings - 100mm dia | 84 | set | 49 ₹4,116 | 48 ₹4,032 |
| 1.00 | OD9215/2025-2026:Conveyance of the wooden shutters from storage shed to the VCB site including loading, unloading ,carefully stacking and all labour charges etc.complete | 6.03 | cum | 18 ₹108.54 | 187.95 ₹1,133.34 |
| 1.00 | OD9219/2025-2026:Coal tarring one coats on old work using 0.16 litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively. | 256.78 | sqm | 34 ₹8,730.38 | 33.21 ₹8,527.53 |
| 1.00 | 13.59:Coal tarring two coats on new work using 0.16 litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively. | 56.78 | sqm | 69 ₹3,918.10 | 68.48 ₹3,888.57 |
| 1.01 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil | 209.03 | cum | 251 ₹52,465.28 | 250.26 ₹52,310.60 |
| 1.01 | OD9213/2025-2026:Fixing the woodwn shutters carefully in the grooves of the regulator piers without any damages to the shutters and grooves as per serially numbered in the shutters including all labour charges,etc. complete | 230 | no | 87 ₹20,010 | 86 ₹19,780 |
| 1.01 | OD9214/2025-2026:Supplying and filling the puddle clay between wooden shutters for making the same water tight including cost ,conveyance by both lorry and boat including all labour charges etc. complete | 23.22 | cum | 809 ₹18,784.98 | 800 ₹18,576 |
| 1.01 | OD9217/2025-2026:Removing the wooden shutters from the grooves of the VCB without any damages to the shutters and carefully stacking including all labour charges etc. complete | 230 | no | 29 ₹6,670 | 29 ₹6,670 |
Tender Value
₹2.5 L
EMD Value
₹6,345
Closing Date
27 Oct 2025, 6:00 pmClosed
Abdurahiman Pulikkathumbayil
Assistant Executive Engineer, MI Subdivision Malappuram
GENERAL-Annual maintenance for the year 2025-26-VCB cum bridge across Cherupuzha at Koottilangadi GP, Mankada LAC, Malappuram District.-General Civil Work
2025_Irrig_807089_2
IRR/IA/TR/3467/2025_5_3_2/1
Open Tender
Civil Works - Others
365 days
Kootilangadi
Please refer Tender documents.
11 documents required · 11 mandatory
₹560
Yes
₹6,345
Yes
17 Jan 2026
18 Oct 2025
29 Oct 2025
18 Oct 2025
27 Oct 2025
18 Oct 2025
Amount
DETAILED ESTIMATE
60.8:Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete
60.5:MS Rings - 100mm dia
OD9215/2025-2026:Conveyance of the wooden shutters from storage shed to the VCB site including loading, unloading ,carefully stacking and all labour charges etc.complete
OD9219/2025-2026:Coal tarring one coats on old work using 0.16 litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively.
13.59:Coal tarring two coats on new work using 0.16 litre and 0.12 litre coal tar per sqm in the first coat and second coat respectively.
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil
OD9213/2025-2026:Fixing the woodwn shutters carefully in the grooves of the regulator piers without any damages to the shutters and grooves as per serially numbered in the shutters including all labour charges,etc. complete
OD9214/2025-2026:Supplying and filling the puddle clay between wooden shutters for making the same water tight including cost ,conveyance by both lorry and boat including all labour charges etc. complete
OD9217/2025-2026:Removing the wooden shutters from the grooves of the VCB without any damages to the shutters and carefully stacking including all labour charges etc. complete
OD9216/2025-2026:Conveyance of wooden shutters from VCB site to the store by lorry including loading , unloading, carefully stacking and all labour charges etc. complete
OD9212/2025-2026:Removing puddle clay already filled in the gap between shutters of the regulator for clearing the vent way including all labour charges etc. complete
OD9218/2025-2026:Labour work for clearing obstructions, cutting woods obstructed in the vents during rain to ensure the seamless flow of water through the vents
O.K JAMSHEER (BID ID -2411641)
Bidder Name
O.K JAMSHEER
mansoorali v
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1356816.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
Tendernotice_2.pdf
PDF • 2.04 MB
NITCherupuzha.pdf
Tender Documents • 0.03 MB
SBDCherupuzha.pdf
Tender Documents • 2.03 MB
BOQ_1356816.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid