| 1 | L1₹390.0 CrAccepted-AOC | ₹390.0 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹397.9 Cr+₹7.9 Cr (2.02%)Rejected-Finance 8TH FLOOR BUILDING NO 9A DLF CYBER CITY PHASE III GURGAON 122002 | GURGAON | GURGAON | HARYANA | 122002 | ₹397.9 Cr+₹7.9 Cr (2.02%) | L2 | Rejected-Finance L2 |
| 3 | L3₹413.5 Cr+₹23.5 Cr (6.03%)Rejected-Finance 2ND ROSHAN TOWER S B SHOP BISTUPUR AREA EAST SINGHBHUM JHARKHAND | BISTUPUR | EAST SINGHBHUM | JHARKHAND | 831001 | ₹413.5 Cr+₹23.5 Cr (6.03%) | L3 | Rejected-Finance USD 29,887
EURO 104886
INR 717422696 |
| 4 | L4₹508.1 Cr+₹118.1 Cr (30.3%)Rejected-Finance C 4 DISTRICT CENTRE SAKET NEW DELHI 110017 | SOUTH | DELHI | 110017 | ₹508.1 Cr+₹118.1 Cr (30.3%) | L4 | Rejected-Finance L4 |
| 5 | L5₹508.1 Cr+₹118.1 Cr (30.3%)Rejected-AOC CRYSTAL TOWER 4TH FLOOR TELIBANDHA RAIPUR | RAIPUR | RAIPUR | CHHATTISGARH | ₹508.1 Cr+₹118.1 Cr (30.3%) | L5 | Rejected-AOC rejected L5 |
Tender Value
Refer Docs
EMD Value
₹1.7 Cr
Closing Date
9 Aug 2024, 4:00 pmClosed
ED Procurement Maha-Metro Nagpur
The office of ED Procurement, Maha-Metro Nagpur
DESIGN, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF RECEIVING CUM AUXILIARY MAIN CUM TRACTION SUB STATIONS INCLUDING EHV CONNECTION FROM GRID SUBSTATION, 33 KV CABLE NETWORK, ASS AND SCADA SYSTEM FOR NAGPUR METRO RAIL PHASE-2 PROJECT.
2024_MMRCN_1008784_1
N2-031/TR-03/2023
Open Tender
Electrical Works
Lump-sum
1260 days
Nagpur
Please refer Tender documents.
5 documents required · 5 mandatory
₹1.2 L
₹1.7 Cr
Yes
Nagpur
29 May 2025
18 Feb 2024
9 Aug 2024
18 Feb 2024
9 Aug 2024
18 Feb 2024
6 Mar 2024
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | DESIGN, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF RECEIVING CUM AUXILIARY MAIN CUM TRACTION SUB STATIONS INCLUDING EHV CONNECTION FROM GRID SUBSTATION, 33 KV CABLE NETWORK, ASS & SCADA SYSTEM FOR NAGPUR METRO RAIL PHASE-2 PROJECT.
USD part of Bid Price in $ only | - | Nos | 1 | - |
| 2 | DESIGN, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF RECEIVING CUM AUXILIARY MAIN CUM TRACTION SUB STATIONS INCLUDING EHV CONNECTION FROM GRID SUBSTATION, 33 KV CABLE NETWORK, ASS & SCADA SYSTEM FOR NAGPUR METRO RAIL PHASE-2 PROJECT.
EURO part of Bid Price in € only | - | Nos | 1 | - |
| 3 | DESIGN, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF RECEIVING CUM AUXILIARY MAIN CUM TRACTION SUB STATIONS INCLUDING EHV CONNECTION FROM GRID SUBSTATION, 33 KV CABLE NETWORK, ASS & SCADA SYSTEM FOR NAGPUR METRO RAIL PHASE-2 PROJECT.
INR part of Bid Price in ₹ only | - | Nos | 1 | - |
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
PriceBid_BOQ_N2_031_TR_03.rar
BOQ Document • 0.08 MB
BOQ_1764175.xls
BOQ Document • 0.26 MB
139823842.pdf
Tender Document • 0.59 MB
Part-2GeneralParticularSpecificationAnnexures.pdf
Tender Document • 28.26 MB
Part-2TenderDrawing1.pdf
Tender Document • 30.27 MB
Part-2TenderDrawing2.pdf
Tender Document • 14.76 MB
Part-3GCCPCCIEEMAContractFormsSHEManual.pdf
Tender Document • 13.73 MB
Part-4CommercialPackageSectionXI.pdf
Tender Document • 1.51 MB
Part-1BiddingDocuments.pdf
Tender Document • 1.71 MB
139823844.html
Tender Document • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .