| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.2 LAccepted-AOC | ₹17.2 L Quoted ₹17.0 L | L1 | Accepted-AOC accepted |
| 2 | L2₹17.2 LRejected-Finance | ₹17.2 L | L2 | Rejected-Finance Reject |
| Sl No | Description | Qty | Unit | V P V CONSTRUCTION L2 | AKS INFRAA L1 |
|---|---|---|---|---|---|
| 1.00 | Providing Drinage with Mini Culvert in Muthapudaiyanpatti Matha Kovil Street in Kannudaiyanpatti Panchayat Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B | 208.8 | cu.m | 300 ₹62,640 | 263 ₹54,914.40 |
| 2.00 | Supplying and filling in foundations and basement with filling M- sand in layers not exceeding 15 cm.thick,well watered,rammed and consolidated etc. complete complying with standard specifications. | 34.8 | cu.m | 2,200 ₹76,560 | 2,173 ₹75,620.40 |
| 3.00 | Plain Cement Concrete 1 : 4 :8 ( one part of cement, four parts of sand and eight parts of hard broken stone ) using 40 mm gauge hand broken hard broken granite stone jelly complying with standard specifications in foundations and basement. | 34.8 | cu.m | 5,557 ₹1.9 L | 5,557 ₹1.9 L |
| 4.00 | Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete | 87 | cu.m | 6,350 ₹5.5 L | 6,311 ₹5.5 L |
| 5.00 | Supplying and erecting , centering shuttering includung conveyance of all materials to worksite and all charges etc complete (Below GL) | 716.13 | sq.m | 550 ₹3.9 L | 547.5 ₹3.9 L |
| 6.00 | Plastering with cement mortar 1:4mix to 20 mm thick for RCC Slab, Column & Beam with proper curing including the cost and conveyance of materials to site and all labour charges etc complete., | 174 | sq.m | 596.5 ₹1.0 L | 596.5 ₹1.0 L |
| 7.00 | Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete | 0.36 | mt | 91,902.6 ₹33,084.94 | 91,902.6 ₹33,084.94 |
| 8.00 | Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost and Conveynce of all Charges etc Complete | 3.63 | cu.m | 9,291 ₹33,726.33 | 9,291 ₹33,726.33 |
| 9.00 | Provision for Name board | 1 | Nos | 5,000 ₹5,000 | 5,000 ₹5,000 |
| 10.00 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package} | 1 | Nos | 2,61,811 ₹2.6 L | 2,59,319 ₹2.6 L |
Tender Value
₹17.2 L
EMD Value
₹17,200
Closing Date
27 Feb 2026, 3:00 pmClosed
BDO VP
Panchayat Union Manapparai
Providing Drinage with Mini Culvert in Muthapudaiyanpatti Matha Kovil Street in Kannudaiyanpatti Panchayat Manapparai Block in Tiruchirappalli District under 15th CFC(VP) 2024-25
2026_RDTN_666911_1
B3/2622/2024 mad dt 20.02.2026
Open Tender
Civil Works - Roads
90 days
Manapparai
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹17,200
5 Mar 2026
26 Feb 2026
27 Feb 2026
26 Feb 2026
27 Feb 2026
26 Feb 2026
Providing Drinage with Mini Culvert in Muthapudaiyanpatti Matha Kovil Street in Kannudaiyanpatti Panchayat Earth work excavation and depositingon bank with all lead andlift in all classes of soil such as hard stiff claystiff black cotton hard red earth shales murrams, hard gravellyetc except sand and rock requiring blasting all incidental charges etc complete for Box cutting/ foundation asper SS 20B
Supplying and filling in foundations and basement with filling M- sand in layers not exceeding 15 cm.thick,well watered,rammed and consolidated etc. complete complying with standard specifications.
Plain Cement Concrete 1 : 4 :8 ( one part of cement, four parts of sand and eight parts of hard broken stone ) using 40 mm gauge hand broken hard broken granite stone jelly complying with standard specifications in foundations and basement.
Cement concrete 1:3:6 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete
Supplying and erecting , centering shuttering includung conveyance of all materials to worksite and all charges etc complete (Below GL)
Plastering with cement mortar 1:4mix to 20 mm thick for RCC Slab, Column & Beam with proper curing including the cost and conveyance of materials to site and all labour charges etc complete.,
Supplying fabricating and placing in position of ribbed steel rods for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors etc., complete
Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost and Conveynce of all Charges etc Complete
Provision for Name board
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.39 MB
Techbiddrainage.pdf
Tender Documents • 0.61 MB
BOQ_801151.xls
BOQ • 0.28 MB
pricebiddrainage.pdf
Additional Documents • 0.49 MB
Download all tender documents and submit your bid