Tender Value
₹1.6 Cr
EMD Value
₹3.3 L
Closing Date
16 Jul 2026, 5:00 pm
SE TNC SAWAI MADHOPUR
SE TNC SAWAI MADHOPUR
CONSTRUCTION WORK OF 132 KV LILO LINE FROM EXISTING 132 KV SC SAWAI Madhupur - UNIARA LINE TO 132 KV GSS SOP
2026_RRVPN_571947_1
3110002607
Open Tender
Supply, Erection and Commissioning
SE TNC SAWAI MADHOPUR
Please refer Tender documents.
3 documents required · 3 mandatory
₹5,900
AO TNC SAWAI MADHOPUR
₹3.3 L
Yes
SE TNC SAWAI MADHOPUR
1 Jul 2026
1 Jul 2026
17 Jul 2026
1 Jul 2026
16 Jul 2026
1 Jul 2026
13 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Details Survey as per tenrative route Which includes the following majar activities-
Pegging of line route, providing of servey pillar at an interval of 3-4 Km in the line route with required jungle clearance for survey, Profile preparation of approved route on graph sheet and marking of offset on eighter side of line, marking of side clearance for hills, sand dunes etc. as per specification and tower scheduling. | - | Km | 11,983 | - |
| 1.02 | Check survey as per approved route of line which includes -
Rechecking of the line route as per approved profil. Chainage tower centre marking, pit marking bisection of angle tower as requrred at site. | - | Km | 4,454 | - |
| 1.03 | Excavation
Excavation excluding back filling, including shoring, shuttering, dewatering etc. uptothe required depath as per foundation specification / drawing.
(i) Any Soil, soft rock other than hard rock | - | Cum | 536 | - |
| 1.04 | Excavation
Excavation excluding back filling, including shoring, shuttering, dewatering etc. uptothe required depath as per foundation specification / drawing.
(ii)Hard rock (with blasting subject to permission or without blasting) | - | Cum | 1,737 | - |
| 1.05 | Setting of Template & Stub / Anchor Bolt
Setting of template & stub / Anchor bolt & removal after concreting excluding cost of excavation and concretingbut including back filling with excavated / borrowed earth (with lead & lift) in layers withramming and watering as per specification
(i) Towers including extension upto 9Meters | - | MT | 23,712 | - |
| 1.06 | CONCRETING:
Providing and laying cement concrete for all types of foundation as per latest ISS:456 including cement, sand stone aggregate 20 mm nominal size, water etc. preparing surface, shuttering mixing, placing, ramming, curing, finishing as per specification and drawing.
(ii) 1:3:6 Mix | - | Cum | 11,666 | - |
| 1.07 | Providing and laying cement concrete for all types of foundation as per latest ISS:456 including cement, sand stone aggregate 20 mm nominal size, water etc. preparing surface, shuttering mixing, placing, ramming, curing, finishing as per specification and drawing.
(iv) 1:1.5:3 Mix | - | Cum | 14,663 | - |
| 1.08 | Steel Rainforcement
Cutting, Bending, Welding of joints if required fixing and Placing of steel rainforcement as per specification and drawing including material. | - | MT | 84,157 | - |
| 1.09 | Earthing
a) Earthing of towers with pipe type earthing excluding the supply of Pipes, wires, flates & connectors, but including coke / charcoal, etc. excavation, augering, and backfilling in all types of soil. | - | SET | 2,146 | - |
| 1.1 | Erection of Towers: -
Erection of supper structure including D shackles, ACD,Hangers, U-Bolts, Step Bolts, Danger Plate, Phase Plate, Number Plate etc. Also including tack welding of bolts & nuts upto bottom cross arm / beam level including application of Zinc Rich Paint.
(i) Erection of towers (With extensions upto 9 Meters) | - | MT | 6,673 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.45 MB
BID08UPDATEDLINE.pdf
Tender Documents • 20.26 MB
BOQ_1017721.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid