| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 CrAccepted-AOC 18 CORPORATION ROAD DEVAKOTTAI | SIVAGANGA | TAMIL NADU | 630001 | ₹2.4 Cr | L1 | Accepted-AOC below rate |
| 2 | L2₹2.5 CrRejected-AOC C BLOCK 4G YUGA KALPATARU NO 18 PILLAYAR KOIL STREET PADIKUPPAM ROAD KOYAMBEDU CHENNAI 600 107 | CHENNAI | TAMIL NADU | 600107 | ₹2.5 Cr | L2 | Rejected-AOC above rate |
| Sl No | Description | Qty | Unit | V MEENAL AND CO L1 | SRI SELLIAMMAN AND CO L2 |
|---|---|---|---|---|---|
| 1.00 | Providing of Granular Sub base using Grade I materials of table 400 -1 of Morth with minimum CBR 30 spreading in uniform layers with motor grader on prepared surface, mix in by palce method at OMC and compacting with Vibratory Roller to achieve the desired density including all labourcharges etc, complete as per technical specification and as directed by the departmental officers. Morth - Rev V No. 111,112,401,900 | 239 | M3 | 1,884 ₹4.5 L | 1,980 ₹4.7 L |
| 2.00 | Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. | 160 | M3 | 2,433 ₹3.9 L | 2,555 ₹4.1 L |
| 3.00 | Advance Patch work 13.20mm Providing Advancve Patch work using 50mm consolidated Thickness by using 1 m3 of 13.20mm IRC Metal with 44kg of Bittumen per 1 m3 of Metal For Pre Mixing For existing surface advance Patch work including cost and conveyance of materials to the work site and stacking them to the departmental metric guage for the premeasurement, heating the bitumen in bitumen boiler, heating the aggregates and mixing them with bitumen in mini hot mix plant for premix carpet only rolling by 60-70KN power roller for premix carpet and seal coat seperately including labour charges for spreading the mix for premix carpet application of bitumen for seal coat over premix carpet, including labour charges for spreading seal coat seperately over premix carpet etc. including higher charges and fuel charges for , bitumen boiler and all other tools and plant employed etc. complete as per of MoRTH Rev - V Specifications | 83 | M3 | 4,119 ₹3.4 L | 4,325 ₹3.6 L |
| 4.00 | Providing and laying tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 16,546 | M2 | 29 ₹4.8 L | 31 ₹5.1 L |
| 5.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications | 1,592 | M2 | 87 ₹1.4 L | 92 ₹1.5 L |
| 6.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications | 1,592 | M2 | 21 ₹33,432 | 22 ₹35,024 |
| 7.00 | Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications. | 548 | M3 | 10,508 ₹57.6 L | 11,034 ₹60.5 L |
| 8.00 | Providing and laying Bituminous concrete to 30/40mm thick using 0.13 cum of 19.00-9.50 mm graded metal and 0.17 cum of 9.50-2.36 mm graded metal and 0.26 cum of 2.36 mm & below metal with 47.28 kgs of 60/70 bitumen & 3.02 Kg of Plastic waste (Total-50.30 kg) and for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site, spreading the mix in required temperature for uniform thickness of 40mm / 30mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc., including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, Vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 507 of MORTH Rev-5 specifications. | 617 | M3 | 10,940 ₹67.5 L | 11,487 ₹70.9 L |
| 9.00 | Chipping of concrete and roughening the surface and Clearing away from the site etc complete as per standard specification Complete as per PWD SOR 2025-26, page no.30 Unique Code W-0036 | 9,728 | M2 | 43 ₹4.2 L | 46 ₹4.5 L |
| 10.00 | CEMENT CONCRETE - M7.5 (1:4:8) (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 208 | M3 | 5,221 ₹10.9 L | 5,483 ₹11.4 L |
Tender Value
₹2.9 Cr
EMD Value
₹2.9 L
Closing Date
9 Feb 2026, 3:00 pmClosed
Commissioner
Azad road , karur
Karur corporation_-TURIP 2025-26- Improvement and Renewal of CC Road and BT Road in Ward No.19,36,37,38,40,42,43,44,45,46,47,48 zone- 3 package-1, in Karur City Municipal Corporation.
2026_MAWS_649716_1
E1/8427/2025
Open Tender
Civil Works - Roads
90 days
KCMC
Please refer Tender Documents
3 documents required · 3 mandatory
₹10,000
₹2.9 L
13 Apr 2026
31 Jan 2026
9 Feb 2026
31 Jan 2026
9 Feb 2026
31 Jan 2026
31 Jan 2026 - 9 Feb 2026
Providing of Granular Sub base using Grade I materials of table 400 -1 of Morth with minimum CBR 30 spreading in uniform layers with motor grader on prepared surface, mix in by palce method at OMC and compacting with Vibratory Roller to achieve the desired density including all labourcharges etc, complete as per technical specification and as directed by the departmental officers. Morth - Rev V No. 111,112,401,900
Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications.
Advance Patch work 13.20mm Providing Advancve Patch work using 50mm consolidated Thickness by using 1 m3 of 13.20mm IRC Metal with 44kg of Bittumen per 1 m3 of Metal For Pre Mixing For existing surface advance Patch work including cost and conveyance of materials to the work site and stacking them to the departmental metric guage for the premeasurement, heating the bitumen in bitumen boiler, heating the aggregates and mixing them with bitumen in mini hot mix plant for premix carpet only rolling by 60-70KN power roller for premix carpet and seal coat seperately including labour charges for spreading the mix for premix carpet application of bitumen for seal coat over premix carpet, including labour charges for spreading seal coat seperately over premix carpet etc. including higher charges and fuel charges for , bitumen boiler and all other tools and plant employed etc. complete as per of MoRTH Rev - V Specifications
Providing and laying tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications
Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications
Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications.
Providing and laying Bituminous concrete to 30/40mm thick using 0.13 cum of 19.00-9.50 mm graded metal and 0.17 cum of 9.50-2.36 mm graded metal and 0.26 cum of 2.36 mm & below metal with 47.28 kgs of 60/70 bitumen & 3.02 Kg of Plastic waste (Total-50.30 kg) and for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site, spreading the mix in required temperature for uniform thickness of 40mm / 30mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc., including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, Vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 507 of MORTH Rev-5 specifications.
Chipping of concrete and roughening the surface and Clearing away from the site etc complete as per standard specification Complete as per PWD SOR 2025-26, page no.30 Unique Code W-0036
CEMENT CONCRETE - M7.5 (1:4:8) (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Vibrated Cement Concrete M20 (Design mix) using 20 mm ISS HBG graded metal including cost and conveyance of all materials to site form work and centering soft water labour charges for mixing, transporting, vibrating and compacting finishing and curing concrete, working at heights, hire charges forHire charges for Tools and plants, including all other incidental charges, etc., complete as per standard specifications for CC Pavement
Providing and fixing Bitumen Pad for Expansion joint in between pavement slabs to12mm thick and fixed as shown in the drawing including cost and conveyence of expansion joints including shalimarpad and joint sealent etc, complete as per standard specification
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
techsummary_778969.pdf
BOQ Comparative Chart
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.90 MB
Bid1.pdf
Tender Documents • 0.25 MB
BOQ_778969.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid