Dy.Minicipal Commissioner - West Zone
Regarding the repair of footpaths in the Navrangpura and Ambawadi areas of the Navrangpura Ward, in response to a CCRS complaint.
367832
3/26-27 (T.N.96)
Open
Civil Works - Others
Works
Ahmedabad
4 documents required · 0 mandatory · 4 optional
₹900
Municipal Commissioner, Ahmedabad
₹10,000
23 Nov 2026
23 Nov 2026
23 Nov 2026
26 Nov 2026
23 Nov 2026
120 days
2. Tender Estimated Cost Rs. 9,99,419.00(exclusive of GST). GST will be paid extra by
AMC/Authority at prevailing rate to the contractor.
1% of the Tender Cost in the form (Rs.10000.00)
3. Earnest Money
(D.D./Pay Order / Local Micr Check/B.G.)
4 Tender Fee Rs Demand Draft of Rs.900.00
6. Time-Limit 12 months
7. Validity Period 120 Days
(i) Last Date of Online Submission
a) In Sealed cover in duplicate copies by Registered Post
(ii) Mode of Sending A.D, or by Courier.or hand delivery
b) Tender sent by ordinary post will be rejected out right.
(iii) Description essential to be
a) Name of work, Tender Notice No. & Tender No.
made on sealed cover b) Date of receiving tender by Corporations.
(iv) Mode of quoting rates in
The Price bid shall be submitted online only.
Schedule of Quantities and Rates It shall not be submitted Physically.
9. Date of Opening Dt.27.11.2026 , 15:00 hrs.
Submission of EMD. Tender fee and other Documents
during office hours: On date.27-11-2026, 12:00 pm West
Place of Submission & Opening of
10. Zone, 2nd Floor, A.M. Office, Stadium Sub Zonal Office,
Tender Nr. Panchshil Water Tank, Naranpura Railway Crossing
(1) Rs.1000/- per day (for tenders amounting upto 10 Lakhs), (2)
11. Penalty Due to Delay of work Rs.2500 per day (for tenders amounting above 10 Lakhs and upto
Lakhs), (3) Rs.5000 per day (for all tenders amounting above
Lakhs) but not more then 10% of bill
12. Defect Liability As per ‘B-1 Form Close
Whenever a work is allotted by Engineering staff, whether minor or
major of part thereof of any amount, the contractor shall be bound to
Time permitted to start parts of
13. start the works within 48 hours of intimation of work. Communication
done telephonically via SMS, Via Whatsapp and through letter / E-
mail shall be considered legal and binding for the same. Failure of
comply to start the works in 48 hours of intimation as above by
contractor the contractor shall be levied penalty of (1) Rs.1000/- per
day (for tenders amounting upto 10 Lakhs), (2) Rs.2500 per day (for
tenders amounting above 10 Lakhs and upto 30 Lakhs), (3) Rs.5000
per day (for all tenders amounting above 30 Lakhs). Three times
failures by contractor shall make contractor responsible to be black
listed unless and otherwise justified properly in writing / binding
within 15 days of last notice of penalty.
14. ftuLx[t¾xhlu «J<obtl GST yjd&e åþfJJtbtk ytJNu
The staff of the contractor shall wear safety jackets, shoes,
helmets etc. while on duty and any violation will attract a fine of Rs.
5,000/- for each incident.
15 Safety Failure to erect safety signage or trying to carry out the works
without proper precautions/safety measures as required will attract a
fine of Rs. 5,000/- for each incident.
Contractor's Sign Addl.C.E.(west zone)
ybœtJtœ BgwÂlÂmvj ftuvtuohuNl
bntldh muJtmœl - vrùbÍtul
y.Bgw.ftu. Ítul Ítulj ytuVem,
ztuo.hbKCtE vxuj CJl, WMbtlÃþht ath hM<t vtmu, ybœtJtœ. vrùb Ítul xuLzh ltuxem
lk-03/2026-27 btk ytJhe juJtguj ftbtule ÂJd<
1. Wvhtuf< xuLzhtu su btLg hSMx[uNl ^htJ<t ftuLx[t¾xh©eytuyu ztWljtuz fhe ChJt.
2. yt xuLzhtu zwÃjefux ftuveytu mt&u Chelu Wvh lt mhltbu ÁcÁ / hSMxh yu.ze./ MvezvtuMx/ fwhegh&e rlg< mbgbtk
btufjJtlt hnuNu.
3. ftuLx[tfxh©eytuyu xuLzhle mt&u BGþrlrmvj btLg hSMx[uNlle/ dJobuLx hSMx[uNlle ftuve, xuLzh ftuve <&t yLg vwhtJt mt&u
yawf mtbuj fhJtle hnuNu ylu fJh Wvh xuLzh lkch <&t ftuLxufx lkch sYh MvÐ œNtoJJtltu hnuNu. su ftuLx[tfxh©eytuyu
hSMx[uNl heLgw fhtJuj l ntug.
4. ftuLx[tfxhtuyu xuLzhbt cukfl wltb, Ft<t lkch, btEfh lkch ylu mhltBþ MvÐ yûthu jFÔþ.
5. xuLzh Ve vu ytuzoh / zebtLz z[tVx&e aqfJJtlehnuNu. œhuf xuLzh œeX yjd xuLzh xuLzhVe ChJtle hnuNu.
6. ytuAe hfble xuLzh Ve, R.yub.ze. fu xuLzh Ve, R.yub.ze. ÂJltlt xuLzhtu hœct<j (fuLmj) dKtNu.
7. xuLzh mt&u BþfJtbtk ytJ< hfblt ftb btxu htufzt, jtufj btRfh auf, rzbtLz z[tVx, vu ytuzoh fu cukf duhkxelt MJYvbtk <&t
Yt. yuf fhtuz&e Wvhle ykœtS< hfblt ftb btxu R.yub.ze.le hfb btºt rzbtLz z[tVx, vu ytuzoh fu ckuf duhkxelt MJYvbtk
8. cukf duhuLxe btºt ybœtJtœ Nnuhle s MJefthJtbtk ytJNu.
9. xuLzh Ve <&t R.yub.ze.le hfblt ze.ze./ aufle vtA¤ ftuLx[tfxh©eyu vtu<&t btuctRj lkch yJ~g jFJtltu hnuNu.
ftuLx[t¾xhu vtu<&t ze.ze. xuLzh R~gw > <theF ct>lt s ytvJt.
10. Nh<e xuLzh hœ ct<j dKtNu.
11. stu xuLzhbtk MvÐ WÕjuF fhtguj ntug <tu atubtmtlu fthKu Ft<tfeg MËalt yLJgu ßgthu ßgthu ftb ck^ htFJtLþk &tg <u
mbglu ftble BþÆ<btk bkswhe ytvJtbtk ytJNu. vhkðþ yt yLJgu ftuE CtJ J^thtu ytvJtbtk ytJNu lne. sule ltuk^ œhuf
12. xuLzhtu ftuEvK fthK ytÃgt rmJtg MJefthJt fu lrnk MJefthJt <ule mkÃËKo m•tt BGþrl.rmvj frb§h©ele hnuNu.
13. xuLzhbtk stu ftuR mwDtht JDtht ntug <tu <u ykdu xuLzh Ch<t vnujt AuÕju r>Jmu rlg< JucmtEx y&Jt fauheyu sYhe <vtm
fhelu s xuLzh btufjÔþk.
14. mefgtuhexe zevtuÍex/ vVtuboLm duhuLxele hfb Yt. yuf fhtuz mw^ele ykœtS< hfblt ftb btxu htufzt, jtufj btRfh auf,
rzbtLz z[tVx, vu ytuzoh fu cukf duhkxelt MJYvbtk <&t Yt. yuf fhtuz&e Wvhle ykœtS< hfblt ftb btxu mefgtuhexe zevtuÍex/
vhVtuboLm duhkxele hfb btºt rzbtLz z[tVx, vu ytuzoh fu ckufduhkxelt MJYvbtk ytvJtle hnuNu.
15. mœh xuLzhbtk " GST rlgb Bþsc jtøþ vzNu. " <u Bþsc dKºte fhe xuLzh ChJtlt hnuNu.
16. ybœtJtœ Bgwrlrmvj ftuvtuohuNl îtht ybœtJtœ Nnuh lt ltdheftulu vwhe vtzJtbtk ytJ<e mwrJ^tytulu jd<e Vhegtœ
ltuk^Jt btxu me.me.yth.yum «tusufx ybj bwfJtbtk ytJuj Au.su yk<do< su <u zevtxobuLx JtRÍ le fuxdhe lt «tuçjb lt
rlhtfhK btxu yum.yuj.yu mbg dt¤tu rl^tohe< fhJtbtk ytJuj Au.su yk<do< vrµbÍtullt lJhkdvwht Jtuzolt htuz ylu
Vwxvt< Jtr»tof huRx xuLzhbtk bhtb<-rlCtJltk htuz ylu Vwxvt& buLxulLm lt swœt swœt ftbtu btxu ltdhef yr^fth vºtfbtk
sKtJuj mbg bgtoœtbtk Vhegtœltu rlftj fhJt <ubs muJtfeg ftbdehe mbg bgtoœtbtk vqKo &tg <u btxu R-dJolLm
me.me.yth.yum. «tusufx yk<do< <t.21.08.2021 lt mhfgwjh <&t mexe Rsluh Ft<w vrhvºt
lk.2,<t.07.10.2023 lt vrhvºt,Bgw frb.©ebe <t.23.04.2026 le belexm ytuV bexekd lt bwœt lk.21 ylwmk^tlu
leau bwscle mtbuj fhuj Nh<tu bwscle vulÕxe Jmwj fhJtle Nh<u bkswhe y&uo mtœh fhuj Au
xuLzhbtk mtbuj fhuj Nh<tu yt «btKu Au
me.me.yth.yum.btk ltu^t<e Vhegtœ Jtuzolt Rsluh MxtV îtht ftuLx[tfxh/yusLmelu Jtuxmyuv/xujeVtulef btægb&e
y&Jt YcY juFe<btk Vhegtœ ytvJtbtk ytJNu.mœh Vrhgtœle ftbdehe yum.yuj.yu. le mbg bgtoœtbtk
ftbdehe vqKo > ctœ <ult Vtuxtud{tV,mxeoVefux ylu ftbdehe vqKo > le òK yum.yuj.yu. mbg bgtoœtbtk
Jtuzolt MxtVlu fhJtle hnuNu
stu ytvlu ytvuj Vrhgtœ yum.yuj.yu. mbg bgtoœtbtk vqKo lne &tg <tu vulÕxe le hfb ytvlt cejbtk&e
Jmwj fhJtbtk ytJNu.
ytvlu mtuvJtbtk ytJuj me.me.yth.yum. Vrhgtœtu ltu hevtuxo yXJtzef ^tuhKu rlg< Vtubuoxbtk «btrK< fhe Jtuzo
ytuVemu hsw fhJtltu hnuNu.
ftuLx[tfxh îtht yhsœthlu Vtul fgto ctœ mœh Vrhgtœ yLg Jtuzo fu yLg rzvtxobuLx fu y.Bgw.ftuvtuohuNl lt
ftgoûtuºtbtk l ytJ<e ntuR <ule òK Jtuzo MxtV lu <tðftrjf fhJtle hnuNu.
zebtLz z[tVx / auf “Bgwrlrmvj frb§h©e, ybœtJtœ” lt ltbltu fZtJJtu.
As per Government of Gujarat G.R.No.- EMD/10/2021/7729/DMO Dt.28/06/2021 & Circular of
Finance Department, AMC No.41, Date: 08/02/2022, approved Banks are...
(A) Guarantee issued by following banks will be accepted as SD/EMD on permanent basis. All
nationalized Banks
(B) Guarantees issued by following banks will be accepted as SD/EMD for the period up to
March- 31, 2022. The validity cut-off date in the GR is with respect to the date of issue of
Bank Guarantee irrespective of the date of termination of Bank Guarantee.
1 Commercial Banks :-
5. Kotak Mahindra Bank
6. IndusInd Bank
8. Tamilnadu Mercantile Bank
9. Ujjivan Small Finance Bank
10. A U Small Finance Bank
11. Federal Bank
12. Equitas Small Finance Bank
13. Bandhan Bank
14. Standard Chartered Bank
15. City Union Bank
2 Co-operative and Rural Banks Of Gujarat :-
1. The Mehsana Urban Co-operative Bank Ltd
2. The Ahmedabad Mercantile Co-Operative Bank Ltd
3. Nutan nagrik Sahakari Bank Ltd
4. The Kalupur Commerical Co-operative Bank Ltd
5. Rajkot Nagarik Sahakari Bank Limited
6. The Gujarat State Co-Operative Bank
7. Sarswat Bank
8. Saurashtra Gramin Bank
bu.Bgwrl.frb§h©e, ybœtJtœ Bgwrl. ftuvtuhuNllt mhfgwjh lk.-81, Bþsc <btb
«fthle fLMx[¾Nlle yu¾xeJexebtk BþÏg ftuLx[t¾xh, mc ftuLx[t¾xhlt su bswhtu ftbdehe fh<t
ntug <u <btb bswhtuLþk øþsht< rcÕz´d yuLz y^h fLMx[¾Nl Jfombtk hSMxuNl fhtJÔþ
AHMEDABAD MUNICIPAL CORPORATION
WEST ZONE ENGINEERING DEPARTMENT
Name of Work :- Regarding the repair of footpaths in the
Navrangpura and Ambawadi areas of the Navrangpura Ward, in
response to a CCRS complaint.
Sr. Quant Item Description Rate Per Amount
No. ity in Rs. in Rs.
1 150.00 Box cutting the road surface to proper slope
and camber for making a base for road work
including removing the excavated stuff and
depositing on the road side slope as directed
upto 50Mt.lead. (EXECUTED WITH
MANUAL LABOUR)(R&B SOR 23-24
ITEM CODE 26B008 PN 109 )
2 Dismantling the following including loading,
unloading and disposal of unserviceable
material for all lead or as directed by Engineer-
In-Charge and stacking the serviceable
material and backfilling the resulting trenches
and pits complete.
i 250 Dismantling tiled or stone floors laid in mortar
including stacking of serviceable material and
disposal of uservicalble material with all lead
and lifts. SOR 23-24 IT CD NO:20005 47.25 Smt
3 Conveyance charge of earth, lime, murrum,
building rubbish, manual garbage, sludge,
excavated rock , fly ash, aggregate of any
kind etc complete up to 10.0 KM lead. (R&B
SOR 23-24, P-6 - Item code- 030201A1)
(J) 100 Up to 5 Km. lead
(K) 100 g) Lead From 10 Km to 15 Km. 104.65 Cmt.
4 Providing, laying, spreading and compacting
graded stone aggregate to wet mix macadam
specification including premixing the Material
with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site,
laying in uniform layers in sub- base / base
course on well prepared surface and
compacting with vibratory roller to achieve the
desired density as per Codal
Provision.Approved Rate - Road Project
(a) 250 Production & Supply of WMM 1975.00 Cmt
(b) 250 Laying of WMM
5 Repairing damaged M.H. incl. removing
damaged brick and repairing by masonry in
C.M. 1:5 and plaster in C.M. 1:3 and fixing
C.I. steps and M.H. and carting the same as
directed. Approved Rate - Road Project
(a) 5.00 (A) up to 0.15 mt. (@ Two Coarse) 728.82 No.
(b) 1.00 (B) up to 0.35mt. (@ Four Coarse) 1155.44 No.
6 5.00 Repairing damaged I.C./ Raising removing
damaged brick work and repairing by brick
masonry in C.M. 1:5 and plaster in C.M. 1:3
and fixing C.I. steps and existing chamber
sheet cover, removing the debris from chamber
and carting the same as directed.Approved
Rate - Road Project 399.96 No.
7 30.00 Providing and laying cement concrete 1:3:6 (1-
Cement : 3- Coarse sand : 6- Hand broken
stone aggregates 40mm nominal size) and
curing complete. SOR 23-24 IT NO :05005A
8 100.00 Supplying and fixing of 300 mm-L x 150 mm-
B x 380 mm-H Kerb block for Footpath in M-
20 grade using 20 mm nominal size black trap
aggregate of Sevaliya/Timba or equivalent
quality for pre-cast blocks, reasonably exposed
finish/ formwork , mould with well equipped
with vibratory system for kerb stones of
approved design including curing, etc.
complete, including the cost of formwork etc.
complete. The rate shall also include
necessary cutting of asphalt, fixing the Kerb
stones in line and level on 5 cm thick sand
bedding with necessary equipments and
materials. The rate shall also include the flush
pointing in CM (1:3) for all joints of the
kerbstones. Filling of zari alone the sides of the
kerb stone fixed with Bituminous concrete
mixed in proper position as directed by
Engineer in change to form a portable mixture.
In any case Gravel or such type of materials
shall not be allowed for production. a) Laying
on 5 cm thick Sand Bedding 350.89 Rmt
9 250.00 Providing and Laying of Rubber Moulded
Paver Block Grey/Coloured 60 mm thick, M-
35 Grade of any size ; shape (Usually Uni-
Paver Blocks) using black trap good quality
aggragate of 20 mm nominal size for footpath,
parking areas, service lanes and other
areas as mentioned in the drawing /
instruction of engineer in charge. Cost includes
formworks using rubber mould, Rate providing
and laying paver blocks as per required
grading and specification. The paver block
shall be mechanically compacted. The work
of paving blocks shall be executed in line and
level by skill mason of flooring work only. It
should be laid in such a way that the no cutting
of the paver block to be necessary. if cutting of
paver block necessary then it should be cut by
machine only and carting. The finished surface
of the paver block shall have resonably good,
plain finished. Paver blocks shall be
compacted and shall be relaid if necessary.
Gravel or such type of materials shall not be 501.60 Rmt
allowed for production. Laying on 5cms
thick sand beddding.
10 30.00 Providing on rent LMV like tractor with
hydraulic trolley/Chotta hathi/Tempo with
driver & 4 Nos. of Labor with all tools like
bucket drum, showels, trikam, pavadas, etc. to Shift
carryout different repair / maintanance work as (Day
required. Work shall be carried out as per the or
instrucitons of Engineer In-Charge. No extra Nigh
charged shall be paid for night shift. 3000.00 t)
11 Labour work for fixing any kind of paving
with cement pointing in CM 1:2, including
watering, ramming etc comp. as directed
650.00 For pavement 68.64 Smt
12 55.00 Mazdoor at day /night (As per min.wages
circular of GOG) 363.30 No.
CONTRACTOR'S SIGNATURE ADDL.CITY ENGINEER
& STAMP (West Zone)
AHMEDABAD MUNICIPAL CORPORATION
ENGINEERING DEPARTMENT
GENERAL CONDITION
1. Contractor shall produce the relevant registration certificate of AMC / State Govt /Central
2. Contractor shall register the work to labour commissioner as per labour act.
3. Contractor shall not sub-let the work without permission of the authority
4. Contractor should have sufficient skilled and unskilled laborers so that he shall start work at
different sites simultaneously. Contractor's having labour force available during festivals
shall only apply. Contractor can not stop the work due to on availably of labour force. In case
progress is delayed, contractor shall be penalized 0.1% of Tender amount per day for work
done after time limit, maximum up to 10% for remaining work.
5. Bitumen rate difference will be paid as per tender conditions, if applicable.
6. Advance payment / machinery advance will not be paid.
7. Payment of running bill will be made as per recent A.M.C. policy in force.
8. No extra payment will be made due to increase of central / state Govt. Taxes.
9. If the work is not completed within time limit the penalty will be recovered from immediate
bills of contractors.
10. If the material i.e. MH cover C.C block etc. supplied from Municipal Corporation store then
contractor shall not claim for any extra rate for non execution of such item, partly/fully.
11. In the specifications, "as directed"/"Approved" shall be taken to mean, "as
directed"/approved" by the Engineer-in-charge.
12. Wherever a reference to any Indian Standard appears in the specifications, it shall be taken to
mean as a reference to the latest edition of the same in force on the date of agreement.
13. In "Mode of Measurement" in the specifications wherever a dispute arises in the absence of
specific mention of a particular point or aspect, the provisions on these particular points, or
aspects in the relevant Indian Standards shall be referred to.
14. All measurements and computations, unless otherwise specified, shall be carried out nearest
to the following limits:
(i) Length, width and depth (height)------- 0.01 Meter.
(ii) Areas -----0.01 Sq. Mt.
(iii) Cubic Contents ------0.01 Cu.Mt.
15. The distance, which constitutes lead, shall be determined along the shortest practical route
and not necessarily the route actually taken. The decision of the Engineer-in-charge in this
regard shall be taken as final.
16. Where no lead is specified, it shall mean "all leads"
17. Lift shall be measured from plinth level.
18. Definite particulars covered in the items of work, through not mentioned or elucidated in it,
specifications shall be deemed to be included there in.
19. Reference to specifications of materials as made in the detailed specification of the items of
work is in the form of a designation containing the number of the specification of the
material and prefix 'M' e.g. 'M-5'.
20. Approval to the samples of various materials given by the Engineer-in-charge shall not
absolve the contractor from the responsibility of replacing defective material brought on site
or materials used in the work found defective at a later date.
21. The contract rate of the item of work shall be for the work completed in all respects.
22. No collection of materials shall be made before it is got approved from the Engineer-in-
23. Collection of approved materials shall be done at site of work in a systematic manner.
Materials shall be stone at site of work in a systematic manner. Materials shall be stored in
such a manner as to prevent damage, deterioration or intrusion of foreign matter and to-
ensure the preservation of their quality and fitness for the work.
24. Materials, if and when rejected by the Engineer-in-charge, shall be immediately removed
from the site of work within 24 hours.
25. No materials shall be stored prior to, during and after execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
26. All works shall be carried out in workmanlike manners per the best techniques for the
particular item.
27. All tools, templates, machinery and equipment for correct execution of the work as well as
for checking lines, levels, alignment of the works during execution shall be kept in sufficient
numbers and in good working condition on the site of the work.
28. The mode, procedure and manner of execution shall be such that it does not cause damage or
over loading of the various components of the structure during execution or after completion
of the structure.
29. All necessary safety measures and precaution (including those laid down in the various
relevant Indian Standards) shall be taken to ensure the safety of men, materials and
machinery on the works as also of the work itself.
30. The testing charges of all materials shall be borne by the Contractor unless recovery at one
percent towards testing charges is separately made.
INSTRUCTION TO TENDERERS
TENDER VALIDITY PERIOD:
The tender shall be kept valid for acceptance for a period of One Hundred Twenty Calendar
days (120) from opening of price bids.
SECURITY DEPOSIT
Within 10 days of receipt of Acceptance from the Corporation, the successful tender shall
furnish to the Corporation Security Deposit of 5% (Five Percent) of the contract price cheque or
Bank Guarantee, pay order, or demand draft of Nationalized Banks and Schedule Banks only.
CONTRACTOR'S SIGNATURE ADDL.CITY ENGINEER
& STAMP (West Zone)
AHMEDABAD MUNICIPAL CORPORATION
ENGINEERING DEPARTMENT
GENERAL SPECIFICATION
Time limit for the work shall be 12 month period after the order to start the works. Progress of work
should be in proportion to time limit.
The contractor shall be remain responsible for Workmen’s compensation if any accident. The
contractor shall arrange for barricading at night and arrangement of Pagi at night to direct the traffic.
He shall be responsible for any damage to public. If any incident happen, during the execution of
work. In case of dispute for unseen or overlooked items the decision of the Dy. City Engineer shall
be final. The contractor shall have to give site clean of all rubbish during the work and at the time of
completion of work and hand over the site with final finishing of the work as directed. All the
rejected materials shall be removed from site within 24 hours by contractor at this risk and cost.
Debris shall have to cart daily from site.
For mixing mortar either for masonry or for plaster or for any other purpose contractor shall have to
prepare through of bigger size and mix the mortar in the required proportion. In on case he shall be
allowed to mix the mortar either on floor or any finished surfaces. The contractor shall have to make
his own arrangement for water required for the work.
If any extra item crops up during the progress of work the same shall be carried out by the contractor
and he shall be paid at the rate fixed by Add.C.E. as per the rate analysis based on latest SOR or if
item is not available in SOR than based on current market rates. In case of extra item decision of
Add. City Engg. shall remain final regarding rate.
If in the interest of the Corporation it is necessary to change either any site or the design of the
propose work the contractor shall carry out the same at his quoted rates without charges any extra
and the contractor will have to carry out the works and he will be paid at the rate quoted by him. No
claim for extra rate for subsequent changes in site and design is entertained.
The cubical contents of the cement bag shall be taken as 1-20 cft. Per bag and the contractors shall
have to prepare the measures boxes according to this measure.
Octroi exemption passes shall not be given for any materials required for the work. Contractor will
be fully responsible for compliance of the various provisions under contract Act. 1970 and the Rules
framed the to under.
The tender for the work shall remain open for a period (120) days from the date of opening of the
tenders for this work and that the tenderer shall not be allowed to withdraw on modify the offer on
his own during the period. If any tenderer withdraw or makes any modifications or addition in the
terms and conditions of his tender not acceptable to the Municipal Corporation the Municipal
Corporation shall without prejudice to any right or remedy be at liberty to forfeit in full the said
earnest money and black list the contractor.
If the work is not carried out within the specified time limit. from the date of order to start the work
the penalty of Rs.- (As per Form - B1) per day of delay shall be recovered from the immediate bills
payable to the contractor. Contractor has to make his own arrangement for procurement of steel and
Contractors should note the following conditions carefully:-
1. Conditional tender shall not be accepted.
2. All tenders are to be submitted in duplicate without which the tenders are liable to be
3. In case of tender downloaded from website, tender fee & EMD should be submitted in form
of demand draft or in cash.
4. Condition of Form - B1 Standard Specification of material & code of practice will be
applicable. Form B1 can be is available in website. Specification shall be as per ' R& B Dept.
- Govt. of Gujarat booklets of Building Works & and Road Works Specifications published
by Gujarat Book Depot, Sector-21. Gandhinagar. CONTRACTOR'S SIGNATURE
ADDL.CITY ENGINEER & STAMP ( West Zone) Mobile No.:-
CONTRACTOR'S SIGNATURE ADDL.CITY ENGINEER
& STAMP (West Zone)
AHMEDABAD MUNICLPAL CORPORATION
MAHANAGAR SEVA SADAN
Clause : 1 Contractor shall not employ any child having age 5 to 15 years as it is prohibited by Child
Labour Prohibition and Regulation Act 1986. Hon'ble Supreme Court has given certain guide
lines and as per the guide lines. If child labour is employed on the site work, the contractor
shall have to deposit Rs. 20,000.00 (Rupees Tw enty thousand only) in the child labour
welfare fund. If the employer refuses to deposit then action will be taken for contempt of
Supreme Court Judgement and also will be prosecuted by concerned authority. Because of
the breach of any provision of child labour prohibition and regulation Act 1986 by the
Contractor & Municipal Corporation becomes liable to pay any amount then the Municipal
Corporation shall recover the said amount from the contractor.
Clause : 2 The Standing Committee has decided to deduct 1/2% amount from each running bill as
per its Reso. No. 1783 Date 06--02-97, but the Municipal Corporation Board has recently
decided that the actual testing charge is taken and the remaining amount is refundable at the
time of final bill (As per Muni. Board Reso. No. 123 dated 25-02-97)
Clause : 3 Contractor has to follow prevailing Labour act and has to maintain labour register
acordingly,and has to follow other govt.rules.
Clause : 4 Quantity taken in tender are tentative and may differ as per execution of work. No claim
shall be entertain regarding QUANTITIES.
* MODIFICATION OF DOCUMENTS
Modification of specifications and correction/corrigendum in respect of the work if required will be
made by A.M.C. The same shall be placed on A.M.C website which may be downloaded by the
tendrers enclosed along with the tender duly signed. These shall form a part of tender. The tenderer
shall not add or amend the text of any of the documents except in so far as may be necessary to
comply with any addendum.
* ADDENDAUM / CORRIGENDUM .
Addendum or corrigendum conveying any change or correction in respect of the work shall form the
part of the contract documents. The full consideration shall be given to such addendum or
corrigendum or correction before submission tender duly filled in by the contractor. Therefore, the
contractor shall have to watch such addendum or corrigendum or correction published by A.M.C
through its website www.egovamc.com. Tenderes shall verify the number of addendum issued and
enclose the same with the tender documents,failing which the tender shall be liable for rejection and
no any complaint in respect to this shall be entertained under any circumstances.
CONTRACTOR'S SIGNATURE ADDL.CITY ENGINEER
& STAMP (West Zone)
AHMEDABAD MUNI CIPAL CORPO RATI ON ENGI NEER DEP ARTMENT
NAVRANGPURA WARD
TECHNICAL SPECIFICATION
Name of Work ;- Regarding the repair of footpaths in the Navrangpura and Ambawadi areas of the
Navrangpura Ward, in response to a CCRS complaint.
Following technical specifications shall be applicable to the relevant items of BOQ
Box cutting the road surface to proper slope and camber for making a base for road work
including removing the excavated stuff and depositing on the road side slope as directed
upto 200 Mt.lead.
Any soil which generally yields to the application of pickaxes and shovels, spades,
rakes or any such ordinary excavating implement or organic soil, gravel, silt, sand turf
loam, clay, peat etc. falls under this category. For materials and workmanship for
earthwork and excavation, relevant specification IS: 3764 & IS 1200 (Part I) shall be
To protect persons from injury and to avoid damage to property, adequate
barricades, construction signs, red lanterns and guards as required shall be placed and
maintained during the progress of the construction work and until it is safe for the traffic
to use the roadways. The relevant Indian standards and the rules and regulations of
local authorities in regards to safety provisions shall be observed.
The depth of the excavation shall be as required. The site shall be cleared and all
obstructions, loose stones, materials and rubbish of all kind, bush; wood and all type
trees shall be removed, as directed. The materials so obtained shall be the property of
AMC and shall be conveyed and stacked as directed, within 50-m. lead. The roots of the
trees coming in the sides of the trenches shall be cut and coated with hot Bitumen.
All types of trees, woods etc. which requires prior permission of Govt./ Forest
Authority / Municipal Commissioner, before cutting shall be cut after obtaining such
permission from them. The rate of site clearance is deemed to be included in the rate of
The excavation shall be carried out in true line and level and having width and
depth, as shown in the drawings or as directed. The Contractor shall do the necessary
shoring and strutting or shall provide necessary slopes to a safe angle or steps, as
required or directed, at his own cost. No extra payment shall be made for such
precautionary measures, taken. The bottom of the excavated area shall be leveled both
longitudinally and transversely, as directed, by removing excess soil and watering, as
required. No earth filling will be allowed for bringing it to level, if by mistake or any
other reason, excavation is made deeper or wider than shown on the drawings or as
directed. The extra depth or width shall be made up with sand filling, as specified for the
bottom level of the subsequent finishing at the cost of the Contractor or as directed by
Engineer-In-Charge.
The Contractor shall at his own expense and without extra charge make provision
of supporting all utility services, lighting the excavated areas, separating and stacking
serviceable materials nearly, shoring, timbering, strutting, bailing out water either sub-
soil or rainwater, including pumping at any stage of the work. all Excavation work must
executed with manual labour only.
4.2. Precautions :
The blasting operation shall remain in charge of competent and experienced supervisor
and workman who are thoroughly acquainted with the details of handling explosives and
blasting operations. The blasting shall be carried out during fixed hours of the day,
preferably during the mid-day-lunch hours or at the close of the work as ordered in
writing by the Engineer-in-charge. The hours of blasting shall be notified in advance to
the people in the vicinity. All the charges shall be prepared by the man in charge only.
Red danger flags shall be displayed prominently in all directions during the blasting
People except this who actually light the fuse shall be prohibited from entering into this
area. The flag shall be stationed as 200 m. from the firing site in all directions and all
persons including workmen shall be excluded from the flagged area at least 10 minutes
before the firing warning whistle being sounded for this purpose.
During excavation in rock by blasting, the lowest 15 cm. of the stratas shall be blasted
with light charges so as not to shatter or weaken the underlying rock on which the
foundation will be actually laid. If excavation in rock is done to larger width and lengths
than those shown on the drawings or as directed, no payment shall be made for such
over break. If excavation is done to depth grater than shown on the drawings or
directed, excess depth shall be made up with foundation grade concrete as directed at
the contractor’s cost.
The charged hole shall be drilled to the required depth and in suitable places when
blasting Is done with powder, the fuse cut to the required length shall be inserted in the
holes and the powder dropped in. The powder shall be gently tamped with copper rod
with rounded ends. The explosive powder shall then be covered with trapping materials
which shall be tamped lightly but firmly. When blasting is done with dynamite and other
high explosive dynamite cartridges shall be prepared by inserting the square cut ends of
fuse into the detonator, and finished with dippers at the open ends. The detonator
should be gently pushed into the premier leaving one third of the copper exposed
outside. The primer shall be housed into the explosive. Bore holes shall be of such size
that the cartridges can be easily passed down. The primer shall be cleared of all debris
and explosive inserted. The space for about 20 cms. above the charge shall then be
gently filled with dry clay pressed home and rest of the tamping is firmed with any
convenient materials gently packed with a wooden cover.
At a time, not more than 20 such charges shall be prepared and fired. The man in
charge shall blow a whistle in a recognised manner for cautioning the people. All the
people shall then be required to move to safe distances. The charges shall be lighted by
the man in charge only. The man-in-charge shall count the number of explosions. He
shall satisfy himself that the charges have been exploded before allowing the workman
to go to the work site.
The contractor shall be fully responsible to strictly follow the prevailing rules and
procedures regarding blasting procedures.
In case of a misfire the following procedure shall be observed :
Sufficient time shall be allowed to account for the delayed blast. The man in charge shall
inspect all the charges and determine the missed charge.
If it is the blasting powder charge, it shall be completely flooded with water. A new hole
shall be drilled at about 45 cm. from the old and fired. This should blast the old charge.
Should it not blast the old charge. Should it not blast the old charge, the procedure shall
be repeated till the old charge is blasted.
In case of charge of gelatin, dynamite etc. the man in charge shall gently remove the
tamping and the primer with detonator. A fresh detonator and primer shall then be used
to blast the charge. Alternatively the hole may then be drilled 15 cm. away and parallel
to it. This hole shall then be charged fired when the misfired hole should explode at the
same time. The man in charge shall report to the office at once all cases of misfire, the
cause of the same and what steps were taken in connection therewith.
If a misfire has been found to be due to defective detonator or dynamite, the whole
quantity in the box from which defective article was taken must be sent to the authority
as directed for inspection to ascertain whether all the remaining materials in the box are
also defective or not.
4.3. Accidents :
The contractor shall be solely responsible for any accident during the entire procedure of
handling explosive and blasting and shall pay necessary compensation to persons
affected or damage t lands or properly etc., due to the blasting without extra claims on
the department.
A careful and day-to day account of explosives shall be maintained by the contractor in
an approved manner and shall be open to inspection of the Engineer-in-charge at all
times. Surprise visit may also be paid by the Engineer-in-charge to the storage and in
case of any unaccountable shortage or unsatisfactory accounting, the contractor shall be
liable to be penalised by forfeiture of part or whole of his Security Deposit or by
cancellation of tender in which case be shall not be entitled for any compensation.
4.5. Disposal of Excavated materials :
No materials excavated from foundation trenches of whatever kind they may be, are to
be placed even temporarily nearer than1.5m. of distance prescribed by the Engineer
from the outer edges of excavation. All materials excavated shall remain the property of
Government. Rate for excavation includes sorting out of useful materials and stacking
them separately as directed within the specified lead. Materials suitable and useful for
back filling or other use shall be stacked in convenient places but not in such a way as to
obstruct free movement of men, animals and vehicles or encroach upon the area
required for constructional purpose. The site shall be left clean of all debris on
Disposal of excavated materials is subject to the following :
Unsuitable materials obtained from clearing site and excavation shall be disposed off
within a lead of 50 meters as directed. useful materials obtained from clearing site and
excavation shall be stacked within a lead of 50 M. beyond the building area as directed.
Materials suitable for back filling shall be stacked at convenient places within a lead of
50 M. from the structure for reuse. Useful stones from rock excavation shall be stacked
neatly within a lead of 50 M. and will be allowed to be used by the contractor on
payment at rates laid down in the contract or if not so aid down, at schedule of rates of
the Division or at a mutually agreed rates if there are no such rates in the Schedule of
If surplus materials are required to be conveyed beyond 50 M. conveyance will be paid
for under a separate item.
4.6. Mode of measurement and payment :
The work shall be measured for the work limited to the dimensions shown on drawings
or directed, Excavation to dimensions in excess of the above will not be measured or
paid for and if so ordered by the Engineer the contractor shall have to fill up the excess
depth with cement concrete specified for foundation without extra payment.
Driving of sounding bards, drill holes to explore the nature of substratum upto a total
length of meter distributed in 2 or 3 places in each foundation if necessary, will be
considered incidental work and eill not be paid for separately.
Removal of slips and blows in the foundation trenches will not be measured or paid for.
If it is necessary in the opinion of the Engineer-in-charge to carry foundation below the
levels shown on the plants the excavation for the first 1.5 M. of additional depth will be
included in the quantity for the particular classification and will be paid for as extra work
at rate to be decided under the general conditions of contract unless the contractor
unless the contractor is willing to accept payment as tendered rates.
The rate shall be for a unit of one cubic meter.
Dismantling tiled or stone floors laid in mortar including stacking of serviceable material
and disposal of uservicalble material with all lead and lifts. SOR 23-24 IT CD NO:20005
The rate shall be for a unit of Smt.
Conveyance charge of earth, lime, murrum, building rubbish, manure, garbage, sludge,
excavated rock, fly ash, aggregates of any kind Including spreading & levelling etc.
e) Lead From 4 Km to 5 Km.
f) Lead From 5 Km to 10 Km.
All the surplus earth etc. shall be carried away immediately from the site of work
to a place within 5km.distance or as directed and ordered by the Engineer, so as not
to cause any inconvenience to the public traffic finding which in view of public safety
and traffic convenience. The corporation shall carry out the work byany other
agency at the contractor’s risk and cost. If the instructions are not completed within
days from the date of order to cart the surplus materials and clear the site, the
said work shall be carried out by the Municipal Corporation at the risk and cost of
the contractor and no claim or dispute shall be entertained in this respect.
If the filling in trenches after settlement of the earth filling in trenches is to be
done and the same shall be carried out by the contractor without asking any extra
rate. The contractor shall have to cart the surplus earth after the trenches we will
watered and refilled with the sand. The rate of carting including carting of brickbats,
metal, rubble vegetable and garbage, if necessary to clear the road surface.
The rate shall be for a unit of one cubic meter.
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam
specification including premixing the Material with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site, laying in uniform layers in sub- base / base
course on well prepared surface and compacting with vibratory roller to achieve the desired
density as per Codal Provision.
Production & Supply of WMM
This work shall consist of laying and compacting clean, crushed, graded aggregate and granular
material, premixed with water, to a dense mass on a prepared sub-grade/sub- base/ base or
existing pavement as the case may be in accordance with the requirements of these
Specifications. The material shall be laid in one or more layers as necessary to lines,
grades and cross- sections shown on the approved drawings or as directed by the
The thickness of a single compacted Wet Mix Macadam layer shall not be less than 75 mm.
When vibrating or other approved types of compacting equipment are used, the
compacted depth of a single layer of the sub-base course may be upto 200 mm with the
approval of the Engineer.
Physical Requirements
Coarse aggregates shall be crushed stone. The aggregates shall conform to the physical
requirements set forth in Table 19-1.
Sevaliya/Timba/Ankodiya special aggregate is only acceptable.
If the water absorption value of the coarse aggregate is greater than 2 percent, the soundness test
shall be carried out on the material delivered to site as per IS:2386 (Part-5).
Table 19-1 : Physical Requirements of Coarse Aggregates for Wet Mix Macadam for
Sub-base/Base Courses
S. No. Test Test Method Requirements
1. Los Angeles Abrasion value or IS:2386 (Part-4) 40 percent (Max.)
Aggregate Impact value IS:2386 (Part-4) or
IS:5640 30 percent (Max.)
2. Combined Flakiness and Elongation indices (To IS:2386(Part-1) 35 percent (Max.)*
* To determine this combined proportion, the flaky stone from a representative sample
should first be separated out. Flakiness index is weight of flaky stone metal divided by
weight of stone sample. Only the elongated particles be separated out from the remaining
(non-flaky) stone metal. Elongation index is weight of elongated particles divided by total
non-flaky particles. The values of flakiness index and elongation index so found are added up
Grading Requirements
The aggregates shall conform to the grading
given in Table 19-2.
Table 19-2 : Grading Requirements of Aggregates for Wet Mix Macadam
IS Sieve Designation Percent by weight passing the IS Sieve
600 micron 8-22
Material finer than 425 micron shall have Plasticity Index (PI) not exceeding
The final gradation approved within these limits shall be graded from coarse to fine and shall
not vary from the low limit on one sieve to the high limit on the adjacent sieve or vice versa.
Construction Operations:- Preparation of Base
The surface of the sub-grade/sub-base/base to receive the Wet mix macadam course shall be
prepared to the specified grade and camber and cleaned of dust, dirt and other extraneous
material. Any ruts or soft yielding places shall be corrected in an approved manner and rolled
until firm surface is obtained.
Where the Wet mix macadam is to be laid on an existing metalled road, damaged area
including depressions and potholes shall be repaired and made good with the suitable
material. The existing surface shall be scarified and re-shaped to the required grade and
camber before spreading the coarse aggregate for Wet mix macadam.
Preparation of Mix
Wet Mix Macadam should be prepared in an approved mixing plant of suitable capacity
having provision for controlled addition of water and forced/positive mixing arrangement like
pugmill or pan type mixer of concrete batching plant. For small quantity of wet mix work, the
Engineer may permit the mixing to be done in concrete mixers.
Quantity of water should not vary from OMC determined as per IS : 2720 (part VIII) by more
than agreed limit. The mixed material should be uniformly wet and no segregation should be
Spreading of mix
Immediately after mixing, the aggregates shall be spread uniformly and evenly upon the
prepared subgrade/sub-base/base in required quantities. In no case should these be dumped in
heaps directly on the area where these are to be laid nor shall their hauling over a partly
completed stretch be permitted.
The mix may be spread either by a paver finisher or motor grader or as per instruction of
Engineer-in-Charge and/or his authorized representative. For portions where mechanical
means cannot be used, manual means as approved by the Engineer shall be used. The motor
grader shall be capable of spreading the material uniformly all over the surface. Its blade shall
have hydraulic control suitable for initial adjustments and maintaining the same so as to
achieve the specified slope and grade.
The paver finisher shall be self-propelled, having the following features:
(i) Loading hoppers and suitable distribution mechanism
(ii) The screed shall have tamping and vibrating arrangement for initial compaction to
the layer as it is spread without rutting or otherwise marring the surface profile.
(iii) The paver shall be equipped with necessary control mechanism so as to ensure that
the finished surface is free from surface blemishes.
The surface of the aggregate shall be carefully checked with templates and all high or low
sports remedied by removing or adding aggregate as may be required. The layer may be
tested by depth blocks during construction. No segregation of layer and fine particles should
be allowed. The aggregates as spread should be of uniform gradation with no pockets of fine
After the mix has been laid to the required thickness, grade and crossfall/camber the same
shall be uniformly compacted, to the full depth with suitable roller. If the thickness of single
compacted layer does not exceed 100 mm, smooth wheel roller of 80 to
100 kN weight may be used. For a compacted single layer upto 200 mm, the compaction shall
be done with the help of vibratory roller of minimum static weight of 80 to 100 kN or
equivalent capacity roller. The speed of the roller shall not exceed 5 km/h.
In portions having unidirectional cross fall/superelevation, rolling shall commence from the
lower edge and progress gradually towards the upper edge. Thereafter, roller should progress
parallel to the centre line of the road, uniformly over-lapping each preceding track by at least
one third width until the entire surface has been rolled. Alternate trips of the roller shall be
terminated in stops at least 1 m away from any preceding stop.
In portions in camber, rolling should begin at the edge with the roller running forward and
backward until the edges have been firmly compacted. The roller shall then progress
gradually towards the centre parallel to the centre line of the road uniformly overlapping each
of the preceding track by at least one-third width until the entire surface has been rolled.
Any displacement occurring as a result of reversing of the direction of a roller or from any
other cause shall be corrected at once as specified and/or removed and made good.
Along forms, kerbs, walls or other places not accessible to the roller, the mixture shall be
thoroughly compacted with mechanical tampers or a plate compactor. Skin patching of an area
without scarifying the surface to permit proper bonding of the added material shall not be
Rolling should not be done when the subgrade is soft or yielding or when it causes a wave-
like motion in the sub-base/base course or subgrade. If irregularities develop during rolling
which exceed 12 mm when tested with a 3 metre straight edge, the surface should be loosened
and premixed material added or removed as required before rolling again so as to achieve a
uniform surface conforming to the desired grade and crossfall. In no case should the use of
unmixed material be permitted to make up the depressions. Rolling shall be continued till the
density achieved is at least 98 per cent of the maximum dry density for the material as
determined by the method outlined in IS : 2720 (Part-8).
After completion, the surface of any finished layer shall be well-closed, free from
movement under compaction equipment or any compaction planes, ridges, cracks and loose
material. All loose, segregated or otherwise defective areas shall be made good to the full
thickness of the layer and recompacted.
Setting and drying:
After final compaction of wet mix macadam course, the road shall be allowed to dry for
Opening to Traffic
Preferably no vehicular traffic of any kind should be allowed on the finished wet mix
macadam surface till it has dried and the wearing course laid.
Surface Finish and
Quality Control of
The surface finish of construction shall conform to the requirements of Clause in Item No.
Quality control:
Control on the quality of materials and works shall be exercised by the Engineer as per Table
Table 19-3 : Test and Frequency for Materials for Wet Mix Macadam
Type of Test Frequency IS Code
Constr (As per Circular No. 66)
Wet Gradation One test per 200 Cu.m. IS:2386, Part-I-
Macada Aggregate Impact Value One test per 1000 Cu.m. IS:2386, Part-IV
m Combined One test per 500 Cu.m. IS:2386, Part-I
Elongation Indices
Atterberg Limits of One test per 200 Cu.m. IS:2720, Part-V
portion ofaggregates
425 micron sieve
Density of compacted One set of three tests per IS:2720, Part-VIII
layer 1000 sq.m
Rectification of Surface Irregularity
Where the surface irregularity of the wet mix macadam course exceeds the permissible
tolerances or where the course is otherwise defective due to subgrade soil getting mixed with
the aggregates, the full thickness of the layer shall be scarified over the affected area,
reshaped with added premixed material or removed and replaced with fresh premixed material
as applicable and recompacted. The area treated in the aforesaid manner shall not be less than
5 m long and 2 m wide. In no case shall depressions be filled up with unmixed and ungraded
material or fines.
Arrangement for Traffic
During the period of construction, arrangements for the traffic shall be provided. The
Contractor shall take all necessary measures for the safety of traffic during construction and
provide, erect and maintain such barricades, including signs, marking, flags, lights and
flagmen as per instruction of the Engineer-in-charge.
Measurements for Payment
The rate shall be for a unit of one cubic meter.
Repairing damaged I.C./ Raising removing damaged brick work and repairing by brick
masonry in C.M. 1:5 and plaster in C.M. 1:3 and fixing C.I. steps and existing chamber sheet
cover, removing the debris from chamber and carting the same as directed.Approved Rate -
The rate shall be for a unit of one No.
Repairing damaged I.C./ Raising removing damaged brick work and repairing by brick
masonry in C.M. 1:5 and plaster in C.M. 1:3 and fixing C.I. steps and existing chamber sheet
cover, removing the debris from chamber and carting the same as directed.Approved Rate -
Road Project Mazdoor at day /night (As per min.wages circular of GOG)
The rate shall be for a unit of one No.
Providing and laying cement concrete 1:3:6 (1- Cement : 3- Coarse sand : 6- Hand broken
stone aggregates 40mm nominal size) and curing complete. SOR 23-24 IT NO :05005A The
The rate shall be for a unit of Cmt
Supplying and fixing of 300 mm-L x 150 mm-B x 380 mm-H Kerb block for Footpath in M-20
grade using 20 mm nominal size black trap aggregate of Sevaliya/Timba or equivalent quality
for pre-cast blocks, reasonably exposed finish/ formwork , mould with well equipped with
vibratory system for kerb stones of approved design including curing, etc. complete, including
the cost of formwork etc. complete. The rate shall also include necessary cutting of asphalt,
fixing the Kerb stones in line and level on 5 cm thick sand bedding with necessary equipments
and materials. The rate shall also include the flush pointing in CM (1:3) for all joints of the
kerbstones. Filling of zari alone the sides of the kerb stone fixed with Bituminous concrete
mixed in proper position as directed by Engineer in change to form a portable mixture. In any
case Gravel or such type of materials shall not be allowed for production. a) Laying on 5 cm
thick Sand Bedding
The rate shall be for a unit of rmt
Providing and Laying of Rubber Moulded Paver Block Grey/Coloured 60 mm thick, M-35
Grade of any size ; shape (Usually Uni-Paver Blocks) using black trap good quality
aggragate of 20 mm nominal size for footpath, parking areas, service lanes and other
areas as mentioned in the drawing / instruction of engineer in charge. Cost includes
formworks using rubber mould, Rate providing and laying paver blocks as per required
grading and specification. The paver block shall be mechanically compacted. The work
of paving blocks shall be executed in line and level by skill mason of flooring work only. It
should be laid in such a way that the no cutting of the paver block to be necessary. if
cutting of paver block necessary then it should be cut by machine only and carting. The
finished surface of the paver block shall have resonably good, plain finished. Paver blocks
shall be compacted and shall be relaid if necessary. Gravel or such type of materials shall
not be allowed for production. Laying on 5cms thick sand beddding.
The rate shall be for a unit of smt
Providing on rent LMV like tractor with hydraulic trolley/Chotta hathi/Tempo with driver &
4 Nos. of Labor with all tools like bucket drum, showels, trikam, pavadas, etc. to carryout
different repair / maintanance work as required. Work shall be carried out as per the
instrucitons of Engineer In-Charge. No extra charged shall be paid for night shift.
The rate shall be for a unit of Shift (Day or Night)
Labour work for fixing any kind of paving with cement pointing in CM 1:2, including
watering, ramming etc comp. as directed
The rate shall be for a unit of smt.
Mazdoor at day /night (As per min.wages circular of GOG)
The rate shall be for a unit of No.
Seal and Signature of the Bidder Add.City Engineer(West Zone)
ybœtJtœ BGþrlrmvj ftuvotuhuNl
vr©b Ítul - Esluh Ftðþ
1. Ft<t îtht «t&b LOI (juxh ytuV RLxebuNl) RMgw fhJtbtk ytJNu. LOI (juxh ytuV RLxebuNl)
bégt ctœ rœl-10 btk 5 % (vtka xft) juFu auf&e / rzbtLz z[tVTx / vu ytuzoh / luNljtEÍz cukf
duhkxe&e zevtuÍex Che fhthvºt fhJtltu hnuNu. <u ctœ Jfo ytuzoh RMgw fhJtbtkk ytJNu ylu
Jfoytuzohle <theF&e mbg bgtoœt NÁ &guj dKJtbt ytJNu <ub A<tk vK ftb NY fhJtbtk lrn
ytJu <tu rlgbtlwmth ftgoJtne fhJtbt ytJNu.
2. Nh<e xuLzh MJefthJtbtk ytJNu lrn.
3. xuLzh Jujezexe 120 rœJm hnuNu.
4. xuLzh MJefthÔþk, hesu¾x fhÔþk, ftulu ytvÔþk ylu fgt CtJ&e ytvÔþk, <u ykdu zu. BGþrl. frb.©e ltu
rlKog ytFhe hnuN.u
5. xuLzh Chuj ftuLx[t¾xh vife ftuEvK ftuLx[t¾xhlu vK yt CtJu ftb ytvJtbtk ytJu <tu ceò btLg
ftuLx[t¾xh Jtk^tu jE NfNu lrn.
6. yufe JF<u yuf fh<tk Jæþ søgtytuyu ftb NY fhJtltu Jfoytuzoh b¤u <tu ftb yuf mt&u s c^u NY
fhÔþk vzNu. yuf ftb ÃþÁ &tg vAe cesw ftb NY fheyu yuÔþk atjNu lrn.
7. atÕþ ftbu ftuE vK mrJom jtEllu LþfNtl l &tg <u he<u ftb fhÔþk vzNu, òu ftuE mrJom jtEllu
LþfNtl &Nu <tu <ule mkÃËKo sJtc>the (òlbtjle) ftuLx[t¾xhle vtu<tle hnuNu. mtEx vh ftb
>hBgtl bswh fu sl<tlt ftuE btKmlt òl btj fu LþfNtl &tg <ule sJtc>the ftuLx[t¾xhle
hnuNu. vtujem Vhegt> &tg <tu <ule sJtc>the vK ftuLx[t¾xhle hnuNu. CuFz ^me l vzu <ule
sJtc>the vK vtujem Vhegt>btk ftuLx[t¾xhle hnuNu. CuFz ^me l vzu <u btxu mjtb<elt vdjtk
(suJt fu >tuhzwk ctk^e bsqh Ftztbtk W<thJt, mtuh´d ylu Mx[x´d fhJt rJduhu) je^t Jdh bsqhlu
Ftztbtk W<thNu <tu ftuLx[t¾xh s vtujem Vhegtœbtk sJtcœth hnuNu ylu BGþrl. ftuvtuohuNlltu ftuEvK
MxtV ytlt btxu sJtc>th hnuNu lrn.ytxÕþk mbSlu s xuLzh ChÔþk.
8. yt xuLzh su <u Jdolt btLg gtœelt ftuLx[t¾xhtu Che NfNu. dJbuoLxlt btLg ftuLx[t¾xhu y.BGþ.ftuvtuo.
btk btLg ftuLx[t¾xhle gtœebtk hSMx[uNl ðþhk< fhtJÔþk vzNu.
9. yt Wvhtk< y.BGþ.ftuvtuo.lt slhj ftuLx[t¾x fLzeNl vK btLg htFJtle hnuNu. Vtubo ce-1le Nh<tu
ck^lf<to hnuNu. ftb htuz ylu rcÕz´d Ftðþk - øþsht< htßglt MvuNeVefuNl «btKu fhJtLþk hnuNu
<&t MxtVle Mþalt vK mtEx Wvh atÕþ ftbu ægtlbtk juJtle hnuNu. ce-1 Vtubo <&t MvuNeVefuNl
øþsht< çþf Mxtuh, mu¾xh-21, dtk^eldh Ft<u&e ftuLx[t¾xhu ò<u bu¤Je juJtltu hnuNu. <u Jtkaelu vAe
10. ftuLx[t¾xhlu vubuLx BGþrl. ftuvtuo. Ltt rl<erlgb Bþsc fhJtbtk ytJNu.
11. ftuEvK ftgœtfeg jexeduNl yb>tJtœ Nnuhle ftuxobtk hnuNu.
12. bxehegj fu ceò xuMx´d hevtuxo ftuLx[t¾xhu vtu<tlt Fauo ftuvtuohuNl sKtJu <u søgtyu fhtJJtlt hnuNu.
yt ykdultu mkÃËKo Fao <&t BGþrl. MxtVlu juctuhuxhe Mþ^e <&t buLGþVu¾ah´d søgt Mþ^e jtJJt jE
sJtltu Fao vK ftuLx[tfhu CtudJJtltu hnuNu.
13. juch yu¾x «btKu hSMx[uNl ykdu ybj fhJtltu hnuNu <&t fuxjt juch jtJNtu <u vK sKtJJtLþk
hnuNu. juch yu¾x «btKu ftgoJtne lrn &E ntug <tu <u btxu ftuLx[t¾xh mkÃËKovKu sJtc>th hnuNu.
14. btj su <u Mxtumo Wvh y&Jt mtEx Wvh Mþalt Bþsc W<thJtltu <ubs dtuXJJtltu hnuNu.
15. muÕm xuût, ytu¾x[tug, mhatso, yLg xuût fu yLg ftuEvK fhJuht ChJtle sJtc>the ftuLx[t¾xhle
16. atEÕz juch yuBvjtug fhe NftNu lrn.
17. ftuLx[t¾xh îtht yuze.mexe.Rsluh©e / zu. mexe. Rsluh©ele mwalt bwsclt bxehegjltk muBvj hsw
18. ftuLx[t¾xhu atÕþ ftbu mtEx Wvh zeSxj fubuht&e ftb atÕþ > vnujtk, åttÕþ ftbu <&t ftb ÃËKo
>lt Vtuxtud{tV BGþrl. yturVmbtk ytvJtlt hnuNu.
19. ftuEvK fthKmh xuLzh hœ fhJtbtk ytJu <tu ftuLx[t¾xh <u ykdu ftuEvK «fthltu n¬tu fu J¤<hle
btkdKe fhe NfNu lrn. yt Nh< MJeftgo ntug <ubKu s xuLzh ChÔþk.
20. bxehegÕm suJt fu hu<e, #xtu, mebuLx, vtEv, rJduhu MxtLzzo bxehegÕm MvuNeVefuNl «btKult
jtJJtlt hnuNu. ßgtk ftuE atuFJx l &E ntug ðgtk ytE.yum. ftuz «btKu bxehegÕm jtJJtLþk <&t
xuMx´d fhtJJtLþk hnuNu.
21. htßg / fuL÷ mhfth©elt JF<tu JF<lt ftgœt Bþsc su ftuE hfble fvt< fhJtlt nwfb
mhfth©eyu fhuj ntuE <u Bþsc ftuLx[tfxlt cejbtk&e fvt< fhJtbtk ytJNu.
22. juch JuÕVuh Vkz btxu ntjbtk htßg mhfth©eyu fhujt nwfb Bþscle hfb cejbtk&e ftve juJtbtk
Wvhtu¾< Nh<tu <&t rlgbtu buk ft¤SÃËJof Jtkae Au ylu blu fçËj bksqh Au.
ftuLx[tfxhle mrn <&t me¬tu yuze.mexe Rsluh (v.Ítul)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
Tender No. 96.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .