Loading…
Loading…
| # | Company | Amount |
|---|---|---|
| 1 | ₹96.1 L 17 AMRIT KAUR MARKET SWAMI RAM TIRATH NAGAR PAHAR GANJ NEW DELHI 110055 | ₹96.1 L |
Tender Value
₹96.3 L
EMD Value
₹96,330
Closing Date
20 Nov 2023, 11:00 amClosed
Rectification of defective works at Construction of Office Building for National Jute Board at Rajarhat, New Town, Kolkata 700156 at the risk and expense of the main contractor i.e., Ms Saket Infradevelopers Pvt. Ltd
NBCC/WB/2023/322
NBCC/WB/2023/322
Open Tender-Domestic
Civil Works General
24 Paraganas North, West Bengal
₹2,950
₹96,330
31 Jul 2026
2 Nov 2023
20 Nov 2023
20 Nov 2023
27 Nov 2023
site to the nearest dumping yard
Cleaning of underground concrete water tanks and
Repairing of the undulated paver block with all required
materials all complete.
Repairing of the backside Aluminium composite panel
inlcuding the requirement of any new material.
Cleaning of all rainwater catch pits and their inter
connecting pipelines lines
Repairing of the aluminium windows/doors with supply
11 MR and fixing of new glass panes and other required materials No. 15 2411.19 36167.80
etc. all complete
Making good the silicon at all defective places in the
structural glazing and complete the silicon works wherever
not completed with all required materials like scaffolding,
craddle etc. complete in all respect.
Rectification of the defective water proofing works in the
basement, lift pit and terrace.
Replacement of the broken openable glasses, structural
glazing glasses sealing of the gap between the aluminium
windows and civil structure etc. including all required
materials to avoid the leakage/seepage of water inside the
complete building.
Realignment/repairing/refixing of the kerb stone to avoid
any stagnation of water.
Replacement of the damaged aluminium handles in the
alumnium openable windows..
Grouting of the vitrified tiles at various floors, toilet floor
and wall tiles wherever not completed
Digitally signed by ANIRBAN
buffing and polishing of the installed stainless steel railing
in the building.
19 MR refixing of the SS railing at the entrance staircase (material LS 1 9644.75 9644.75
available at site)
20 MR Grinding, polishing of the Kota Stone. Sqm 400 843.92 337566.10
replacement of the damaged precast slabs over the cable
trench with the new ones
removing of protective covering from the ACP and the fire
doors installed in the building.
Edges of the beam beyond the false ceiling area needs to be
23 MR rectified, plastered, putty, primer and painting to achieve Sqm 80 1506.99 120559.32
the desired finish
Sealing of the gap between the toilet louvers and civil work
25 MR Replacement of the louvers glass with the new one No 15 241.12 3616.78
Cleaning of all metal false ceiling installed in the toilets at
Cleaning of the shaft aluminium doors frame, aluminium
glass, aluminium windows etc.
Repairing of the cracks in the gypsum false ceiling at all the
floors (Note: for payment of the repair of the cracks in the
28 MR false ceiling, complete false ceiling area shall be measured. Sqm 4000 120.56 482237.29
The rate should be quoted accordingly.)
29 MR Grouting of the toilet wall and floor tiles Sqm 1000 45.81 45812.54
Fixing of the batteries/cell, servicing of the urinal sensor to
bring it into the full working condition
Covering of the gap found between the face plate of the
switches and the wall
Rectification of the aluminium shaft doors where the gap
has been found between the aluminium frames and the
walls. (Note: The rate should be including of all civil works
required to make good the same.)
Replacement of the broken vitrified tiles with the new one
with all required finishings. (Note: the material is available
at site and will be supplied free of cost)
Replacement of the broken toilet tiles with the new one
34 MR with all required finishings (Note: the material is available Sqm 20 964.47 19289.49
at site and will be supplied free of cost)
Fixing of the reamining portion of the lift lobby tiles (Note:
35 MR the material is available at site and will be supplied free of Sqm 0.2 6027.97 1205.59
Rectification of the damaged false ceiling with the new one
with the required putty, primer and painting works. The
old damaged false ceiling shall be removed from its place.
This exercise to be dona at all the defective locations like JC
sir chamber, JCI MD chamber, first aid rooms, meeting
rooms near balcony etc. where the dampness in the flase
ceiling has been observed
Rectification of the dampness observed in the wall by
removing the old plaster, waterproofing of the wall,
plastering, putty, primer, painting etc. to achieve the finish
Rectification of the bad kota stone works found in the
balcony. Filling of the gap found in the kota stone joints.
The rate shall be inlusove of any new material required to
complete the work
Providing silicon in the ACP installed at balcony area and
40 MR Replacement of the damaged flush door single leaf No. 2 3616.78 7233.56
Fixing of the ganite facia in the toilet (Note: the material is
41 MR available at site and will be supplied free of cost) Metre 5 241.12 1205.59
Replacement of the damaged panic bar in the fire door
43 MR Replacement of the lock in the fire door No. 4 1808.39 7233.56
ELECTRICAL WORKS
Replacement of the old fused tubelights with new LED
44 MR tubelights 40 Watt including scaffolding, tools, tackles, No. 196 1446.71 283555.5254
accessories etc.
Replacement of the synchronizing relay, , repairing of the
defective ACB in respect of the main DG changeover panel,
battery charger, digital meter. Rate should be inclusive of 1
Digitally signed by ANIRBAN
servicing/overhauling of sump pumps, Plumbing pumps,
WTP equipment and STP equipment/pumps and their
respective electrical panels along with the applicable
automation/level sensor works to bring them into the fully
fledged working condition. The rate should be inclusive of
one year warranty.
Servicing of the WTP electrical panel, STP electrical panel,
47 MR fire control panel including the supply and fixing of any LS 1 20495.08 20495.08475
new materials as required
Cleaning of the lighting fixtures, diffusers etc. installed in
the false ceiling at all the floors
Replacement of the 2*2 downlights which are not working
Replacement of the 12 watt led lights which are not
Rectification of the issues found in the circuit and bring the
light fixtures into the working condition
Termination of the unwanted cables/wires above the false
ceiling and making good the same
53 MR Mechanical seal change of pumps Nos. 4 44840.35 179361.408
54 MR AHU Coil descaling/servicing Nos. 9 2802.52 25222.698
55 MR Fire damper servicing Nos. 54 1121.01 60534.4752
Supply & Installation of Actuator & Control panel for Fire
57 MR Repairing of the TFA motor Nos. 1 31528.37 31528.3725
58 MR Cooling Tower Descaling and Servicing Nos. 3 28025.22 84075.66
59 MR Cooling Tower Motor Servicing and Overhauling Nos. 6 7006.31 42037.83
VFD Mother Board Change for secondary chilled water
SITC of Al powder coated Grille Supply Air & Return Air
62 MR SITC of Black Paint Coller damper Sqm 4 9458.51 37834.047
63 MR SITC of Al powder coated Diffuser SA with VCD Sqm 6 20318.28 121909.707
64 MR SITC of Al powder coated Diffuser SA without VCD Sqm 10 17515.76 175157.625
65 MR AHU & TFA starter Panel Servicing Nos. 18 1401.26 25222.698
66 MR Servicing of MCC Panel Nos. 1 7706.94 7706.9355
67 MR SITC of Butterfly Valve 100 NB- Ground Floor Nos. 1 8225.40 8225.40207
Chilled Water Pipe Insulation Local Rectification of Major
68 MR damaged araes Lot 1 84075.66 84075.66
Supply, Installation, Testing & Commissioning of VFD 11
Supply, Installation, Testing & Commissioning of VFD 1.5
Supply, Installation, Testing & Commissioning of Co2
Supply, Installation, Testing & Commissioning of DP Sensor
73 MR SITC of Cabling (3C X 1.5 Sqmm) Metre 200 497.91 99582
replacement of 1 no. defective W3000 controller in the
replacement of one number defective touch display in the
replacement of 1 no. defective discharge pressure sensor
in the chiller.
77 MR Refrigerant R134A supply Lot 1 218369.1 218369.1
Two days visiting charges of climaveneta for attending
bearkdown complaint
79 MR Transporation charges for the above materials Lot 1 5832.66 5832.66
Digitally signed by ANIRBAN
FIRE FIGHTING AND DETECTION WORKS
Refixing of the defective gun metal short branch pipe 2.5
inch male (supply only)
Refixing of the defective hydrant female coupling (supply
Refixing of the defective double hose box with lock and key
provision (supply only)
Refixing of the defective hose reel pipe with gun metal
coupling 63mm x 15 meter long (supply only)
Refixing of the defective conventional hooters with 4 watt
speaker (supply only)
Refixing of the defective addressable control module
Refixing of the broken double hose box glass (supply only)
replacement of the defective addressable smoke detectors
replacement of the defective response indicator (supply
89 MR Refixing of the defective pressure gauges No. 6 1958.92 11753.52
Supply of 4 way fire brigade inlet built with CI body and
having 4 nos, of gun metal 63 mm
Labour and installation charges of the above fire fighting
and fire detection material
92 MR Freight charges of above material Job 1 12092.10 12092.10
Reburbishment of complete fire fighting system, fire
detection system, fire alarm system, public address system.
Commisisioning of these system shall have to done as per
the entire satisfaction of the Client and all these systems to
be handed over in full fledged working condition
STP, WTP, Plumbing and Servicing works
Supply and fixing of the missing STP equipment like filter
Supply and fixing of the missing STP equipment like treated
water transfer pump fixing with required plumbing
94 MR materials and electrical materials. (Note: the pumps are No. 2 12055.93 24111.86
available at site and will be provided free of cost)
Supply and fixing of the missing STP equipment like tube
Supply and fixing of the missing STP equipment like bio
culture chemical
Supply and fixing of the missing STP equipment like
submerged aerator
Supply and fixing of the missing STP equipment like
hypochlorite chemical
rectification of the possible defects/leakages in the
plumbing pipeline as the filled overhead tanks gets emptied
on its own. The exercise shall be done in the complete
99 MR building at all the plumbing pipelines and the leakages have LS 1 36167.80 36167.80
to be arrested. The plubing line shall be fully charged and
will be watched for 7 days to observe any leakages.
rectification of the already installed sanitary fixtures as it
has been found to be overflowing. The exercise to be
carried out in the complete building. All the sanitary
100 MR fixtures shall have to be checked. The defective items have No. 15 964.47 14467.12
to be replaced and all the sanitaries should have to be
brought in the full fledged working condition
Grand Total incl. GST 9633031.285
Grand Total incl. GST 9633031.285
Digitally signed by ANIRBAN
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
01NITITT NJB.pdf
Tender Document
02GCC 2013final.pdf
Tender Document
03NJB list of approved makes.pdf
Tender Document
04RectificationDetailedBoQ.pdf
Tender Document
corrigendum-2002-Corrigendum01.pdf
pdf • 0.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .