Loading…
Loading…
Tender Value
₹1.9 Cr
EMD Value
₹1.9 L
Closing Date
18 Apr 2026, 6:00 pmClosed
Similar tender results from the same govt authority in the past 3 years.
Executive Engineer, Surendranagar Irrigation Division, Surendranagar
Construction of New Checkdam on Jamburi River Nr. Village Dosalighuna, Ta.:- Chotila Dist.:- Surendranagar
290468
20 of 2025-26
Open
Civil Works - Others
Surendranagar
6 documents required · 5 mandatory · 1 optional
₹3,600
Yes
Executive Engineer, Surendranagar Irrigation Division, Surendranagar
₹1.9 L
Yes
27 Mar 2026
27 Mar 2026
27 Mar 2026
18 Apr 2026
27 Mar 2026
BILL OF QUANTITIES
(A) Percentage Rate Tender (Up to INR 50 Cr.)
SURENDRANAGAR IRRIGATION DIVISION - SURENDRANAGAR
Name of Work : Construction of New Checkdam on Jamburi River Nr. Village Dosalighuna, Ta.:- Chotila Dist.:- Surendranagar
Memorandum showing Items of Woks to be carried out
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
Item No Quantities Item of work ESTIMATED RATES Unit Total amount
estimated but In Figures In words according to
may be more or estimated
less quantities
1 2558.00 Excavation in all sort of strata and formations incl. depositing the unuseful excavated stuff as and where directed 79.00 Rupees SeventyNine Cum.
incl sorting and stacking useful materials as directed upto 200 mt lead and all lift etc. complete incl. dewatering. Only
(a) In Overburden incl. HM
2 2254.76 Excavation in all sort of strata and formations incl. depositing the unuseful excavated stuff as and where directed 590.00 Rupees Five Hundred Cum.
incl sorting and stacking useful materials as directed upto 200 mt lead and all lift etc. complete incl. dewatering. Ninety Only
( c) In Hard Rock
3 16.946 Providing,cutting,bending,binding and fixing in position as per drawing .TMT BAR , reinforcement for R.C.C. works 76574.00 Rupees SeventySix M.T.
and anchor bars incl cost of black annealed 16 to 18 BWG M.S.. Wire etc.complete with all lead and lift. Thousand Five
(b) FE 500 Hundred SeventyFour
4 4292.34 Prov. & Laying in position cement concrete using cement , sand and crushed metal coarse aggregate by mass and 3423.00 Rupees Three Cum.
machine mix for PCC/RCC including necessary formworks compaction by vibrator,curing as directed with all lead Thousand Four
& lift etc complete. (Excluding cost of steel ) FOR .BODY WALL, APRON, TRAINING WALL, SIDE WALL, SPLAY Hundred TwentyThree
WALL, KEY WALL, CUT OF WALL ETC. Only
4/C) Controlled Concrete grade M-15 and MSA-40mm
5 140.00 Providing and fixing in position 100/110 mm dia PVC Pipe weep holes in the retaining walls/sidewall/abt etc 358.00 Rupees Three Hundred Rmt.
FiftyEight Only
6 2560.13 Backfill with selected earth Brought From out side Borrow Area Excavated useful Material including watering, 141.00 Rupees One Hundred Cum.
ramming consolidation by Hand Temping and all lead and lifts etc. complete. FourtyOne Only
7 199.00 Providing and laying graded filters of sand,gravel/metal and over size metal ( 100 to 150 mm) behind the 530.00 Rupees Five Hundred Cum.
retaining wall & wing walls as directed as per approved drawing with all lead and lifts etc complete. Thirty Only
8 900.36 Providing and laying rubble stone pucca pitching with panel ( of size not more than 10sqmt) of stone masonary 945.00 Rupees Nine Hundred Sqmt
30cm thick wall in C:M 1:5 without base inverted filter and header stone but wth 10cm thick murrum layer (for FourtyFive Only
base) inclduning packing and trimming and dressing slopes etc.
(a) 45 cm thick pitching with pointing in C:M 1:2
9 511.20 Providing and laying dry rubble stone pitching without base inverted filter and header stone but with 10 cms thick 294.00 Rupees Two Hundred Sqmt
murrum layer (for base) including hand packing & trimming & dressing slope etc complete (b) 23 cm thick stone NinetyFour Only
10 162.69 Drilling 25mm dia holes at distance as specified and depth upto 3.0mt for check dam foundation & fixing anchor 252.00 Rupees Two Hundred Rmt.
bars of specified diameter with cement grout incl cleaning holes as directed etc.(excluding cost of bars) FiftyTwo Only
11 1.00 Providing and fixing in position White marble plate of Size 45 x 45 x 1.8 cms including engraving The letters as 1350.00 Rupees One Thousand No.
per drawing/ directed etc. complete. Three Hundred Fifty
In Words Rs. (One Crore Ninety Lac Eighty Two Thousand Seven Hundred Fourty Two Rupees And Fourty Three Paisa Only)
I/We am/are willing to carry out the work at % above/ below present (should be written in figures and words)
of the estimated rates mentioned above. An amount of my/our tender works out as under:
* Estimated Amount * Estimated Amount
Put to tender Rs_____________________________ Put to tender Rs_________________
In Words (Rs. ) In Words Rs.( )
(Pease strike out whichever is not applicable)
Note-1: The Contractor shall exhibit a board with brief details of work as directed by the Engineer-In-Charge for which no extra payment shall bemade.
Note-2: Thel abour cess will be deducted as per prevailing rules i.e. 1% of the work done.
Note-3: GST and Incometax TDS will be deducted at a source while making payments of bills
Note-4: In all R.C.C. Items in Rate Analysis Standard Cement Consumption has been taken as per Govt. G.R. NO.: MIS102010/17/K1 Dated:30/07/2018 as stated in S.O.R. therefore in R.C.C. items where there is a change as per actual mix
design the cost of difference of cement consumption have been deducted from the rate of original item at the rate of input rate mentioned in all the tender.
Executive Engineer
Signature of Contractor. Surendranagar Irrigation Division
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1 TITLE PAGE.pdf
2 E-Tender Notice.pdf
3 Invitation For Bid P 1 to 6.pdf
4 SECTION-1 Instruction to Bidders P 7 to 27.pdf
5 SECTION-2 Qualification Information P 28 to 35.pdf
6 SECTION-3 Conditions of Contract P 36 to 64.pdf
7 SECTION-4 Contract Data P 65 to 74.pdf
8 SECTION-5 to 10 Annexure P 75 to 96.pdf
9 Annexure-1 Section-5 Tech Spec P 97 to 186.pdf
10 Annexure-2 Sec-7 Bill of Quantities Schedule B.pdf
Download all tender documents and submit your bid