Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-Finance ANWALKHEDA MR | ₹1.1 Cr | L1 | Accepted-Finance L1 |
| 2 | L2₹1.1 CrRejected-Finance | ₹1.1 Cr | L2 | Rejected-Finance L2 |
| 3 | L3₹1.1 CrRejected-Finance | ₹1.1 Cr | L3 | Rejected-Finance L3 |
Tender Value
₹1.2 Cr
EMD Value
₹7.8 L
Closing Date
5 May 2026, 12:00 pmClosed
SE BADAUN/PILIBHIT CIRLCLE PWD BLY
SE BADAUN/PILIBHIT CIRLCLE PWD BLY
Building work of Thana Barkhera 32 Chamta Hostel-Bairak and 01 Vivechana Room in district Pilibhit
2026_CEBLY_1142773_1
1403/533C(E.T.)-08/2025-26 Date 27-02-2026
Open Tender
Civil Works - Others
365 days
Bareilly
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,714
₹7.8 L
Yes
14 May 2026
27 Apr 2026
5 May 2026
27 Apr 2026
5 May 2026
27 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Excavation in foundation for dtructure as per drawing and technical specification including setting out, construction shoring and bracing removal of atumps and other deleterious and disposal upto lead of 50m dressing of sides and bottam and backfilling in trenches with excavated with excavated suitable material | |||||
| 2Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level 1:4:8 (1 Cement 4 coarse sand (zone-III): 8 graded stone aggregate 40 mm (nominal size) | |||||
| 3 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | - | Cum. | 1,461 | - |
| 4 | (4) Treatment of soil along external perimeter of building 7.5 liters/sqm. (5) Treatment of soil under apron along external perimter 5 liters/sqm. | - | sqm | 213 | - |
| 5 | R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone ballast in the proportion of 1:1.5:3 (M-20) in Footing foundation excluding supply of reinforcement and its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc.and also including supply of all materials, labour and tools and plants etc, required for proper completion of the works. Binding wire cost being inluded in the item. | - | Cum. | 6,224 | - |
| 6 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) (Column)
Ground floor/First floor/Second floorThird floor | - | Cum. | 7,467 | - |
| 7 | R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone ballast in the proportion of 1:1.5:3 (M-20) in Lintel excluding supply of reinforcement and its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc.and also including supply of all materials, labour and tools and plants etc, required for proper completion of the works. Binding wire cost being inluded in the item
Ground floor/First floor/Second floorThird floor | - | Cum. | 7,916 | - |
| 8 | P/F Mild steel or iron in plain work such as reinforced concrete or reinforced, brick work (when not included in over all rates ) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel and and over lapping & hooks.
Ground floor/First floor/Second floorThird floor | - | Qtl | 7,420 | - |
| 9 | Class-150 (Non Modular) brick work in 1:6 cement and Coarse sand mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work. | - | Cum. | 4,907 | - |
| 10 | Brick work in super-structure above plinth level up to floor two level (up to two storeys) including necessary cutting and moulding of bricks as required and also including honey comb brick work thickness of wall not to be less than 1.5 brick thick. (1:6 cement & coarse sand) (230mm wall)
Ground floor/First floor/Second floorThird floor | - | Cum. | 6,265 | - |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.39 MB
Tendernotice_2.pdf
PDF • 1.02 MB
BOQ_2134147.xls
BOQ • 0.42 MB
Download all tender documents and submit your bid