Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹25.0 LAccepted-AOC NIJA MANZIL KALLELIBHAGOM KARUNAGAPPALLY KOLLAM | ₹25.0 L | L1 | Accepted-AOC First lowest |
| Sl No | Description | Qty | Unit | NIJAMON L1 |
|---|---|---|---|---|
| 1.00Cutting trees ,clearing vegetation, clearing unserviceable earth and side protection for pond | ||||
| 1.00 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete | 50 | hour | 353 ₹17,650 Lowest |
| 1.00 | 50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete. | 75 | each | 380 ₹28,500 Lowest |
| 1.00 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 3,420.13 | sqm | 18.5 ₹63,272.33 Lowest |
| 1.00 | 2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth | 10 | each | 562 ₹5,620 Lowest |
| 1.00 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 459.75 | cum | 365 ₹1,67,810.58 Lowest |
| 1.01 | OD63198/2025-2026:Dry rubble masonry with departmental stone in foundation and plinth without Through and bond stone upto plinth level including cost of labour and materials etc complete. | 332.22 | cum | 2,945 ₹9,78,399.68 Lowest |
| 1.01 | OD63200/2025-2026:Engaging labour for cutting the earth in cliff portion which canot be executed by mechanical means | 110 | each | 1,100 ₹1,21,000 Lowest |
| 1.01 | OD63206/2025-2026:Extra labour engaged for breaking the boulders into suitable size | 40 | each | 1,100 ₹44,000 Lowest |
| 1.01 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 4.78 | cum | 9,450 ₹45,208.8 Lowest |
Tender Value
₹25.0 L
EMD Value
₹50,000
Closing Date
25 Feb 2026, 5:00 pmClosed
Executive Engineer
O/o,Executive Engineer, Special Buildings Division Thiruvananthapuram
DEPOSIT-Cutting trees ,clearing vegetation, clearing unserviceable earth and side protection for pond at site for NCC headquarters and group battallion office at Mannanthala-Landscaping-General Civil Work
2026_PWD_825491_3
PWD/BLDG/TR/11360/2025_5_1_1/1
Open Tender
Civil Works - Buildings
Item Rate
180 days
Special Buildings Division Public Office Compound
Please refer Tender documents.
7 documents required · 7 mandatory
₹2,760
Yes
₹50,000
Yes
18 Aug 2026
17 Feb 2026
27 Feb 2026
17 Feb 2026
25 Feb 2026
17 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Cutting trees ,clearing vegetation, clearing unserviceable earth and side protection for pond | |||||
| 1.001 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete | - | hour | - | - |
| 1.002 | 50.2.33.5:Cutting branches of trees overhanging above any structures of girth between 40cm to 60cm including stacking of serviceable materials and disposal of unserviceable material, cost of labour, hire charges of rope and pully etc without making any damages to nearby structures etc complete. | - | each | - | - |
| 1.003 | 2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared | 0.4 | sqm | - | - |
| 1.004 | 2.33.1:Felling trees of the girth (measured at a height of 1 m above ground level) including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material.Beyound 30 cm girth up to and including 60 cm girth | - | each | - | - |
| 1.005 | 2.8.1:Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil | 1 | cum | - | - |
| 1.006 | OD63198/2025-2026:Dry rubble masonry with departmental stone in foundation and plinth without Through and bond stone upto plinth level including cost of labour and materials etc complete. | 0.6 | cum | - | - |
| 1.007 | OD63200/2025-2026:Engaging labour for cutting the earth in cliff portion which canot be executed by mechanical means | - | each | - | - |
| 1.008 | OD63206/2025-2026:Extra labour engaged for breaking the boulders into suitable size | - | each | - | - |
| 1.009 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 1 | cum | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_1409320.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.05 MB
epaymentform.pdf
Tender Documents • 0.05 MB
SBD.pdf
Tender Documents • 1.63 MB
Formoftender.pdf
Tender Documents • 0.25 MB
integritypact.pdf
Tender Documents • 0.03 MB
AFFIDAVIT.pdf
Tender Documents • 0.15 MB
BOQ_1409320.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .