Loading…
Loading…
Tender Value
₹33.1 L
EMD Value
₹33,100
Closing Date
10 Aug 2026, 12:00 pmClosed
TDO, Taluka Panchayat, Gondal
Construction of Checkdam cum Causeway to Dhandhleshwar Temple road at village Lilakha, Construction of Checkdam cum Causeway near Vallbhbhai Vasharambhai Vekariyas Farm at Valadhari, Providing paving block in Gondal taluka panchayat office campus & Construction of Community hall at village Vavdi Vida
327822
2/2026-27
Open
Civil Works
Works
Rajkot
8 documents required · 7 mandatory · 1 optional
₹5,000
Taluka Development Officer
₹33,100
27 Jul 2026
27 Jul 2026
27 Jul 2026
10 Aug 2026
27 Jul 2026
Name of Work : Construction of Checkdam cum Causeway to Dhandhleshwar Temple road
at village Lilakha, Construction of Checkdam cum Causeway near
Vallbhbhai Vasharambhai Vekariyas Farm at Valadhari, Providing paving
block in Gondal taluka panchayat office campus & Construction of
Community hall at village Vavdi Vida
Taluka : Gondal District : Rajkot
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
1 51.92 Cu.M. Excavation for foundation upto 164.82 Rupees One One
all depth including sorting out Hundred Sixty Cu.M.
and stacking of useful Four and Eighty
materials and disposing off the Two Paise.
excavated stuff upto all lead.(B)
Dense or Hard soil
2 193.71 Cu.M. Excavation for foundation upto 279.81 Rupees Two One
all depth including sorting out Hundred Cu.M.
and stacking of useful Seventy Nine
materials and disposing off the and Eighty One
excavated stuff upto all lead.(C) Paise.
3 1.01 Cu.M. Excavation for foundation up to 291.30 Rupees Two One
all depth including sorting out Hundred Ninety Cu.M.
and stacking of useful materials One and Thirty
and disposing of the excavated Paise.
stuff upto all lead. (D) Soft rock
not requiring Blasting
4 68.62 Cu.M. Box cutting the road surface to 114.44 Rupees One One
proper slope and camber for Hundred Cu.M.
making a base for road work Fourteen and
including removing the Forty Four
excavated stuff and depositing Paise.
on the road side slope as
directed upto all lead.
5 49.43 Cu.M. Providing and laying cement 2739.85 Rupees Two One
concrete 1:4:8 (1- Cement : 4- Thousand Cu.M.
coarse sand : 8- Crushed Stone Seven Hundred
Aggregates 40 mm nominal Thirty Nine and
size) and curing complete Eighty Five
excluding cost of formwork in (A) Paise.
Foundation and Plinth
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
6 40.00 R.Mt. Supplying and fixing reinforced 723.93 Rupees Seven One
concrete heavy duty non- Hundred R.Mt.
pressure pipes with collars for Twenty Three
culverts including setting and and Ninety
joining the pipes in C.M. 1:2 Three Paise.
watering and laying (to level or
slope) of I.S. class NP2 of
following internal diameters.(iii)
7 243.80 Cu.M. Providing and casting in situ 3749.16 Rupees Three One
Ordinary cement concrete M- Thousand Cu.M.
150 for R.C.C. Raft and cut-off Seven Hundred
walls including necessary Forty Nine and
shuttering laying, vibrating, Sixteen Paise.
ramming and curing complete.
8 265.50 Cu.M. Filling available excavated 137.47 Rupees One One
earth (excluding rock) in Hundred Thirty Cu.M.
trenches. plinth, sides of Seven and
foundations etc. in layers not Forty Seven
exceeding 20 cm. in depth Paise.
consolidating each disposited
layer by ramming and watering.
9 96.00 Cu.M. Supplying & stacking of crushed 761.73 Rupees Seven One
stone aggregates , chipings of Hundred Sixty Cu.M.
40 to 63 mm size of hard stone One and
free of disintegrated pieces Seventy Three
deletarious and organic (for Paise.
wbm) and grading as per I.R.C
code including filling the
measure boxes with all lead
10 10.50 Cu.M. Supplying and stacking of stone 439.11 Rupees Four One
dust materials on road site Hundred Thirty Cu.M.
including filing the measure Nine and
boxes with all lead. Eleven Paise.
11 96.00 Cu.M. Spreading the stone aggregate 274.73 Rupees Two One
for rolling and W.B.M. including Hundred Cu.M.
filling the interstices to required Seventy Four
camber and gradient (excluding and Seventy
spreading of Blindage)(ii) 40mm Three Paise.
to 63mm size aggreagates.
12 10.50 Cu.M. Spreading blindage or road 162.21 Rupees One One
crust filling the gaps in metal Hundred Sixty Cu.M.
and leveling to camber and Twenty One
gradient as directed.(i) Murrum Paise.
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
13 341.24 Sq.M. Rolling and consolidation of 22.74 Rupees Twenty One
soling including filling in Two and Sq.M.
depression which occur during Seventy Four
the process, with power roler 8 Paise.
tonne to 12 tonne.
14 53.10 Cu.M. Providing and casting in situ 4316.23 Rupees Four One
ordinarycement concrete M-200 Thousand Cu.M.
for average 75 mm thick wearing Three Hundred
coat laid as directed including Sixteen and
tamping ,vibrating, finishing, Twenty Three
curing and filling in joints with Paise.
bitumen complete.
15 7676.50 Kg. Providing TMT Bar FE 415 68.32 Rupees Sixty One
reinforcement for R.C.C. work Eight and Thirty Kg.
including bending, binding and Two Paise.
placing in position complete upto
floor two level
16 34.12 Cu.M. Construction of 10 cm average 4316.23 Rupees Four One
thick cement concret road with Thousand Cu.M.
ordinary cement concrete M-200 Three Hundred
with trimix type laying , vibrating, Sixteen and
and finishing system including Twenty Three
sprinkling floting coat of neat Paise.
cement slurry at rate
kg./Sq.M. with providing and
filling expansion joint etc.
complete for wearing coat in
17 13.28 Cu.M. Providing and Laying ordinary 6888.14 Rupees Six One
cement concrete 1:2:4 (1- Thousand Eight Cu.M.
Cement 2- coarse sand : 4- Hundred Eighty
graded stone aggregates 20 mm Eight and
nominal size) and finishing Fourteen Paise.
smooth with curing etc. complete
including the cost of formwork
but excluding the cost of
reinforsement for R.C.C work in
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
18 2.10 Cu.M. Masonary work using Aerated 4598.27 Rupees Four One
light weight concrete block Thousand Five Cu.M.
having crushing strength not Hundred Ninety
less than 35 kg/sqcm for super Eight and
structure above plinth level upto Twenty Seven
floor two level in cement mortar Paise.
1:5 ( 1 cement : 5 fine sand )
complete as per Technical
19 457.50 Sq.M. Providing and fixing pre-cast 705.12 Rupees Seven One
Rubber Dye / steel Dye inter Hundred Five Sq.M.
locking concrete block 60mm and Twelve
thick with grade of concrete Paise.
M300 pnumatic compressed /
vibrated mechanically and as per
approved design Confirming to
IS 15658 : 2006 including
mm Sand layer for levelling and
filling the joint with sand in
proper line and level as per
guidlines of IRC : SP 63-2018
20 1.70 Cu.M. Providing and laying cement 3772.12 Rupees Three One
concrete 1:2:4 (1- Cement : 2- Thousand Cu.M.
Coarse sand : 4- graded stone Seven Hundred
aggregates 20 mm nominal size) Seventy Two
and curing complete excluding and Twelve
cost of formwork in (A) Paise.
Foundation and Plinth
21 20.91 Cu.M. Brick work using common burnt 4376.38 Rupees Four One
clay building bricks having Thousand Cu.M.
crushing strength not less than Three Hundred
35 Kg./Sq.Cm. in foundation and Seventy Six and
plinth in C.M. 1:5 (1 – Cement, 5 Thirty Eight
– Fine sand) (B) Conventional Paise.
22 5.20 Cu.M. Providing and laying ordinary 10658.15 Rupees Ten One
cement 1:2:4 (1 -Cement : 2- Thousand Six Cu.M.
coarse sand :4 graded stone Hundred Fifty
aggregates 20 mm nominal size) Eight and
and finishing smooth with, curing Fifteen Paise.
etc. complete including the cost
of formwork but excluding the
cost of reinforcement for R.C.C.
work in (B) COLUMNS :
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
23 1.73 Cu.M. Providing and laying ordinary 8593.79 Rupees Eight One
cement 1:2:4 (1 -Cement : 2- Thousand Five Cu.M.
coarse sand :4 graded stone Hundred Ninety
aggregates 20 mm nominal size) Three and
and finishing smooth with, curing Seventy Nine
etc. complete including the cost Paise.
of formwork but excluding the
cost of reinforcement for R.C.C.
work in (A) BEAMS :
24 16.52 Cu.M. Brick work using common burnt 4671.52 Rupees Four One
clay building bricks having Thousand Six Cu.M.
crushing strength not less than Hundred
35 Kg./Sq.Cm. in super structure Seventy One
in C.M. 1:5 (1 – Cement, 5 – and Fifty Two
Fine sand) (B) Conventional Paise.
25 3.39 Cu.M. Filling in foundation and plinth 299.66 Rupees Two One
with murrum or selected soil in Hundred Ninety Cu.M.
layers of 20 cm. thickness Nine and Sixty
including watering, rarn.ming Six Paise.
and consolidating etc. complete.
26 0.80 Cu.M. Providing and laying ordinary 10219.39 Rupees Ten One
cement concrete 1:2:4 (1 – Thousand Two Cu.M.
cement, 2 – course sand, 4 – Hundred
graded stone aggregate 20 mm. Nineteen and
Nominal size) and curing Thirty Nine
complete including the cost of Paise.
formwork for R.C.C. lintel
(excluding the cost of
27 3.30 Cu.M. Providing and laying ordinary 7665.59 Rupees Seven One
cement concrete 1:2:4 (1 – Thousand Six Cu.M.
cement, 2 – coarse sand, 4 – Hundred Sixty
graded stone aggregate 20 mm. Five and Fifty
nominal size) and finishing Nine Paise.
smooth with curing etc. complete
including the cost of form work
but excluding the cost of
reinforcement for R.C.C. work in
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
28 5.61 Cu.M. Providing and laying ordinary 8355.04 Rupees Eight One
cement concrete 1:2:4 (1 – Thousand Cu.M.
cement, 2 – coarse sand, 4 – Three Hundred
graded stone aggregate 20 mm. Fifty Five and
nominal size) and finishing Four Paise.
smooth with curing etc. complete
including the cost of form work
but excluding the cost of
reinforcement for R.C.C. work in
29 2.18 Cu.M. Providing and laying cement 6660.13 Rupees Six One
concrete 1:2:4 (1 – cement, 2 – Thousand Six Cu.M.
coarse sand, 4 – graded stone Hundred Sixty
aggregate 20 mm. nominal size) and Thirteen
for reinforcement concrete Paise.
chhajas not exceeding 10 Cm.
thickness up to floor two level
including finishing the exposed
surface with cement mortar 1:3
(1 – cement, 3 – fine sand) to
give a smooth and even surface
centering and form work and
curing complete excluding cost
of reinforcement.
30 13.68 Sq.M. Providing and fixing 35 mm thick 5338.30 Rupees Five One
shutters for Doors, windows and Thousand Sq.M.
clearestory windows including Three Hundred
Indian teak wood frames 10 cm. Thirty Eight and
x 7 cm. size including anodized Thirty Paise.
alluminium fixtures and
fastenings including primer coat
of approved quality and two
coats of oil painting etc.
complete. (ii) Fully panelled
31 119.68 Sq.M. Providing 10 mm. thick cement 194.94 Rupees One One
plastering in single coat on Hundred Ninety Sq.M.
brick/concrete walls for interior Four and Ninety
plastering finished even and Four Paise.
smooth in cement mortar 1:3 (1
– cement, 3 – coarse sand)
including floating coat.
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
32 138.06 Sq.M. Providing 20 mm. thick sand 330.72 Rupees Three One
faced cement plaster wall up to Hundred Thirty Sq.M.
height 10 meters above ground and Seventy
level consisting of 10 mm. thick Two Paise.
backing coat of C.M. 1:3 (1 –
cement, 3 – sand) and 8 mm.
thick finishing coat of C.M. 1:1 (1
– cement, 1 – sand) etc.
33 119.68 Sq.M. Wall painting (two coats) with 88.38 Rupees Eighty One
plastic emulsion paint of Eight and Thirty Sq.M.
approved brand and Eight Paise.
manufacture on undecorated
wall surface to give an even
shade including throughly
brushing the surface free from
mortar droppings and other
foreign matter and sand papered
34 138.06 Sq.M. Finishing wall with weather proof 122.13 Rupees One One
exterior emulsion paint on wall Hundred Sq.M.
surface (two coats) to give an Twenty Two
required shape even shade after and Thirteen
thoroughly brushing the surface Paise.
to remove all dirt, and remains of
loose powdered materials.etc
35 10.00 No. Providing and fixing G.I. Rain 101.90 Rupees One One
Hundred One No.
water spout of 50mm dia. and
30cm. length. Paise.
36 130.00 Kg. Providing and fixing M.S. grills of 123.42 Rupees One One
required pattern to wooden Hundred Kg.
frame of windows etc. with M.S. Twenty Three
flats and of required spacing and and Forty Two
frame around square or round Paise.
bars with round headed bolts
and nuts or by screws plain
37 4.67 Cu.M. Providing and laying in 2961.50 Rupees Two One
foundation and plinth under floor Thousand Nine Cu.M.
lime concrete with hand broken Hundred Sixty
stone aggregate 40 mm. One and Fifty
nominal size and 40 % mortar Paise.
comprising of 1 – lime putty : 2 –
fine sand and curing complete
excluding cost of form work.
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
38 59.22 Sq.M. Providing and laying 24" X 24" 1546.84 Rupees One One
vitrified 8 mm thick tiles flooring Thousand Five Sq.M.
over 20 mm (Average) base of Hundred Forty
cement mortar 1:6 (1- Cement, 6- Six and Eighty
Coarse Sand) on new surface or Four Paise.
fixing on existing flooring by
adhesive material including
dismentalling of existing flooring
and jointed with colour cement
slurry including finished with
flush pointing & cleaning the
surface etc. complete for light
39 37.38 Sq.M. Providing and laying broken 779.69 Rupees Seven One
chine mosaic flooring for Hundred Sq.M.
terrace using 12 mm to 20 mm Seventy Nine
broken pieces of glazed tiles to and Sixty Nine
be laid over cement mortar 1:3 Paise.
to plain or slope and to be
tempered to bring mortar
creme out upto surface using
white cement including rounding
off junctions and extending
them upto 15 cm along the
wall,clearing with water and
oxalic acid etc. as directed.
40 4.00 Point Point wiring for Light / Bell with 404.00 Rupees Four One
2-1.5 sq.mm & earthwire of 1.5 Hundred Four Point
sq.mm (Green) both are of ISI only.
marked 1.1 KV grade FRLS
PVC insulated multistrand
copper wires, in following type of
pipe to be erected concealed in/
on surface on wall/ceiling
complete with 6A Modular type
switch / bell push & accessories
and earth continuity of following
type, erected on PVC / Metallic
box, single mounting base frame
covered with textured/metallic
front plate modules erected on /
in wall / ceiling as per pipe
erected, with necessary Lamp
holder/ceiling rose /
H.D.Connector as directed. (a)
with medium class Rigid PVC
pipe and accessories Cat. II
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
41 4.00 Point Point wiring for FAN with 2-1.5 585.80 Rupees Five One
sq.mm & earthwire of 1.5 Hundred Eighty Point
sq.mm (Green) both are of .ISI Five and Eighty
marked 1.1 KV Grade FRLS Paise.
PVC insulated multistrand
copper wires, in following type of
pipe to be erected concealed in /
flushed on wall/ceiling complete
with 6A Modular type switch and
hum free EME four or more step
type electronic fan regulator with
separately mounted and
accessories with earth continuity
of following type erected on PVC
/ Metallic box, single mounting
base frame covered with
textured/metallic front plate
modules erected on / in wall /
ceiling as per pipe erected. with
necessary ceiling rose /
H.D.Connector as directed. (a)
with medium class Rigid PVC
pipe and accessories Cat. II
42 2.00 Point Point wiring for Looped Plug with 222.20 Rupees Two One
6A Modular type switch & 5 pin Hundred Point
socket erected on PVC / Metallic Twenty Two
box, single mounting base frame
covered with textured / metallic
front plate modules erected on
/ in wall / ceiling with following
type accessories Cat. II
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
43 1.00 Point Point wiring for Individual Plug 434.30 Rupees Four One
with & earthwire of 1.5 sq.mm Hundred Thirty Point
(Green) both are of ISI marked Four and Thirty
1.1 KV grade FRLS PVC Paise.
insulated multistrand copper
wires, in following type of to be
erected concealed in / on
surface of wall / ceiling complete
with Modular type switch & 5 pin
Plug erected on PVC / Metallic
box covered with appropriate
front plate modules erected on /
in wall / ceiling as per pipe
erected with following type of
accessories. [I] For 6A Plug with
2-1.5 sq.mm Cu. Wire (a) with
medium class Rigid PVC pipe
and accessories Cat. II
44 1.00 No. Providing following type of 131.30 Rupees One One
Modular Type Accessories Hundred Thirty No.
mounted with pvc / metallic box, One and Thirty
single mounting base frame Paise.
covered with textured / metallic
front plate , modules erected
with necessary connection. As
desired by Engineer In charge
(9) 16 Amp. SP one way switch
45 1.00 No. Providing following type of 141.40 Rupees One One
Modular Type Accessories Hundred Forty No.
mounted with pvc / metallic box, One and Forty
single mounting base frame Paise.
covered with textured / metallic
front plate , modules erected
with necessary connection. As
desired by Engineer In charge
(10) 6/16Amp. Universal socket
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
46 20.00 R.Mt. Providing and erecting ISI mark 32.32 Rupees Thirty One
Medium class RIGID PVC Two and Thirty R.Mt.
PIPES of following size Two Paise.
complete to be erected on/in
wall or ceiling erected with
necessary PVC fittings &
Junction boxes fixed with
adhesive solution & Clamps with
following dia of pipes, in
approved manner as directed (b)
47 20.00 R.Mt. Mains with 1.1 KV grade FRLS 80.80 Rupees Eighty One
PVC insulated ISI marked and Eighty R.Mt.
stranded Copper conductor wire Paise.
in following type of pipe to be
erected concealed in /flushed on
wall/ceiling, with 1.5 sq. mm
copper conductor FRLS PVC
insulated stranded wire of green
colour for earth continuity of
following size (a) with medium
class Rigid PVC pipe and
accessories (b) 2 wire 2.5 sq.
48 10.00 R.Mt. Mains with 1.1 KV grade FRLS 146.45 Rupees One One
PVC insulated ISI marked Hundred Forty R.Mt.
stranded Copper conductor wire Six and Forty
in following type of pipe to be Five Paise.
erected in / on wall / ceiling with
2.5 sq. mm copper conductor
FRLS PVC insulated stranded
wire of green colour for earth
continuity of following size (a)
with medium class Rigid PVC
pipe and accessories (b) 2 wire
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
49 4.00 No. Supplying and erecting LED 652.46 Rupees Six One
indoor fittings with LEDs of Hundred Fifty No.
wattage 0.2 Watt to 0.5 Watt Two and Forty
assembled on single MCPCB, Six Paise.
with housing used as a heat sink
shall be made of thick sheet
Steel conforming to IS:
513/CRCA polyester powder
coated and high U.V. &
corrosion resistance with
diffuser and/or Polycarbonate
optics with company mark/name
120 to 300 V,Power Factor more
than 0.9, THD < 10 %,
CCT 4000 K to 6500K,
Uniformity ratio >0.7,
Luminaire efficiency>
LED driver efficiency > 85 %
CREE / OSRAM / PHILIPS
Lumileds / NICHIA /
SEOUL/Bridgelux(U.S.A.) make
LED used for luminaire. (Each
fitting required LM-79 & LM-80
Certificates) (A) Tube Light with
integral/ non-integral driver (e)
20 -22 Watts, Surge-4 KV, IP-
20, 4 feet Cat-ll
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
50 2.00 No. Supplying and erecting LED 242.40 Rupees Two One
indoor fittings with LEDs of Hundred Forty No.
wattage 0.2 Watt to 0.5 Watt Two and Forty
assembled on single MCPCB, Paise.
with housing used as a heat sink
shall be made of thick sheet
Steel conforming to IS:
513/CRCA polyester powder
coated and high U.V. &
corrosion resistance with
diffuser and/or Polycarbonate
optics with company mark/name
120 to 300 V,Power Factor more
than 0.9, THD < 10 %,
CCT 4000 K to 6500K,
Uniformity ratio >0.7,
Luminaire efficiency>
LED driver efficiency > 85 %
CREE / OSRAM / PHILIPS
Lumileds / NICHIA /
SEOUL/Bridgelux(U.S.A.) make
LED used for luminaire. (Each
fitting required LM-79 & LM-80
Certificates) (B) LED Lamps
integral type,cool white with PC
diffuser suitable for B22 LAMP
holder (b) 5 to 8 watts
51 1.00 No. Miniature circuit breaker single 116.15 Rupees One One
pole 6A to 32A suitable to Hundred No.
operate on 240 V A.C. system Sixteen and
and having breaking capacity Fifteen Paise.
10 KA to be erected in existing
box. confirming to IS 8828/1996
with ISI Mark Cat.III
52 1.00 No. Providing & erecting 240 V MCB 262.60 Rupees Two One
double pole switch for lighting Hundred Sixty No.
Load (B Curve) having 10 KA Two and Sixty
breaking capacity & confirms to Paise.
IS : 8828 in existing box having
following capacity (b) 40 Amp.
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
53 1.00 No. Providing and erecting Sheet 999.90 Rupees Nine One
Steel powder coated MCB Hundred Ninety No.
distribution board - flush / Nine and Ninety
surface mounted fitted with Paise.
busbar, neutral link, earth bar
and DIN rail, confirming to IS
without MCB to house
appropriate nos. of MCBs.(The
DBs should be used of same
company of MCB to be used) (F)
Single phase 8 way SS Double
54 1.00 No. Approved make ELCBs / RCCBs 2030.10 Rupees Two One
conforming to IS: 12640 and Thousand Thirty No.
having sensitivity of 30 mA and and Ten Paise.
Short Circuit withstand capacity
of 6 KA and suitable for
operation on single phase
V. having characteristic of quick
action & tripping with all advance
feature & do not incorporate any
electronic component. for
following Max. rating erected as
directed (ii) 40Amps. DP cat.-II
55 0.30 Kg. Providing and erecting Annealed 717.10 Rupees Seven One
bare Copper wire 8 to 16 SWG. Ten Paise.
56 2.00 No. Providing and erecting Approved 1717.00 Rupees One One
make Ceiling fan with double Thousand No.
ball bearing ISI mark with Seven Hundred
condenser A.C. 23OV.50 Seventeen only.
c/s.1200 mm. sweep complete,
canopy and 30 cms. down rod
erected on existing hook or
clamp with 24/0.2 , 3 core
flexible wire with earthing. [Make
shall be approved by Engineer in
57 2.00 No. Supplying & erecting fan hook 126.25 Rupees One One
box of 10 mm M.S. round bar Hundred No.
bounded to the RCC bars up to Twenty Six and
50mm length each side and Twenty Five
pierced through a 16 Gauge Paise.
M.S. box / Heavy Duty PVC box
complete erected concealed in
Ceiling with necessary finishing.
Item Quantity Item of Work Estimated Rate in Unit Total Amount
Item Quantity Item of Work Estimated Rate in Unit Total Amount
No. Estimated may be according to
more or less Figure Words Estimated
58 2.00 No. Providing 2.5mm.thick laminated 20.20 Rupees Twenty One
acrylic sheet to cover the fan and Twenty No.
hook or Fan box. Paise.
59 1.00 No. Providing and fixing 20 cm x 1 5 279.68 Rupees Two One
cm x 2.5 cm. thick year plate of Hundred No.
marble stone set in C.M. 1:4 Seventy Nine
including finishing and engraving and Sixty Eight
letters etc. complete. Paise.
60 3.00 No. Providing and fixing Number 306.14 Rupees Three One
plate of Marble plate stone of Hundred Six No.
required size set in C.M. 1:4 and Fourteen
including finishing and Paise.
engeaving letters etc.
Total Amount Rs.
Total Amount Rs.
Rupees Thirty Three Lakh Six Thousand Eight Hundred Ninety Nine and Seventeen Paise.
I/We _______________________________ am/are willing to carry out the above work at ______________%
above/below __________ percent (should be written in figures and words) of the estimated rate mentioned
above. Amount of my/our tender works out as under: -
Estimated amount put to tender Estimated amount put to tender
Add _______________ % above Deduct ____________ % below
Total amount Rs. ___________ Net amount Rs. _____________
Total amount Rs. ___________ Net amount Rs. _____________
Add. Asst. Engineer
Taluka Pancyayat Signature of the Bidder
Taluka Development Officer
Taluka Pancyayat
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
SCH B.pdf
JAHER_NIVIDA.pdf
SPECIAL CONDITION.pdf
SBD.pdf
GR (1).pdf
Tender Specification.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .