Loading…
Loading…
Tender Value
₹7.9 Cr
EMD Value
₹7.9 L
Closing Date
5 Sept 2026, 3:00 pm7d left
GM - Contract
Utility Identification & diversion / shifting of utilities for 12.576 km Elevated Viaduct from Canal road (chainage 6904.984) to Bardabad Dead End (chainage 19481.228) of Ahmedabad Metro rail project, phase – 3B
332257
GMRC/Utility Shifting/Ph-3B/2026
Open
Civil Works - Others
Works
Gandhinagar
11 documents required · 10 mandatory · 1 optional
₹25,000
₹7.9 L
6 Aug 2026
6 Aug 2026
6 Aug 2026
5 Sept 2026
6 Aug 2026
BILL OF QUANTITIES
1. The Bill of quantities shall be read in conjunction with the Instructions to Bidders, Conditions of
Contract, Scope of Work, and Specifications.
2. The quantities given in the Bill of quantities are estimated quantities. The basis of payment will be
actual quantities of work indented and carried out and valued at the rates and prices tendered in the
priced Bills of quantities, where applicable and otherwise at such rates and prices as the Engineer may
fix within the terms of Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall include all equipment, plant, tools,
spares, labour, supervision, overheads, consumables, materials, erection, maintenance, testing of
input material delivered, profit, taxes and duties together with all general risks, liabilities and obligations
set out and implied in the Contract and other incidentals to comply with the requirements of technical
specifications and scope of work.
4. The rates and prices shall be quoted entirely in Indian Currency.
5. The whole cost of complying with the provisions of the contract shall be included in the items provided
in the priced Bill of Quantities and where no rates are provided the cost shall be deemed to be
distributed among the rates and prices entered for the related items of work.
6. The contractor shall keep the entire carriageway neat and clean throughout the contract period. The
contractor shall maintain guard rails, railings, crash barriers, road furniture etc. in good condition by
cleaning them frequently as advised / required by using suitable detergents/chemicals.
The staff of the contractor shall wear safety jackets, shoes, helmets etc. while on duty and any violation
will attract a fine of Rs. 5,000/ for each incident.
Failure to erect safety signage or trying to carry out the works without proper precautions/safety
measures as required will attract a fine of Rs. 5,000/ for each incident.
7. The Tendered rate for incident Management shall include all equipment, labour, material, consumable,
tools, spares, and other incidentals to comply with the requirement of the scope of the work and
technical specifications.
8. General directions and descriptions of work and materials are not necessarily repeated or summarized
in the Bill of Quantities. Reference to the relevant sections of the bidding document shall be made
before entering rates or prices against each item in the Bill of Quantities.
9. 10% of the payment will be released by the Employer only after submission of No Objection Certificates
(NOCs) from various utility-owning agencies and/or local authorities to GMRC, wherever applicable as
decided by the Employer/Engineer-in Charge.
10. Procurement of materials belonging to other utility owning agencies (i.e BSNL and other utility owning
Agencies) shall be arranged through the respective utility owners the Contractor shall be responsible
only for execution of the utility shifting/diversion works and shall be eligible for reimbursement/payment
towards the shifting cost under relevant BOQ items.
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
Annexure 1, Summary of Utility Shifting Works
(percent above / below / at par over
SN Description Total (in Rs.) the basic cost)
Figure In Words
1 Section A: General Items
Section B: Drainage/Strom
water pipeline works
Section C: Water supply pipeline
Section D: Provisional sum
4 R&B SOR 2023-24/DSR
5 Section E: BSNL Works
Grand Total (excluding GST)
Grand Total (excluding GST)
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
Name of work Utility Identification & diversion / shifting of utilities for 12.576 km Elevated Viaduct from Canal road
(chainage 6904.984) to Bardabad Dead End (chainage 19481.228) of Ahmedabad Metro rail project,
BILL OF QUANTITIES
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
Section - A General items
Providing Excavation for utility mapping and shifting based on
site condition. This shall includes following items
1. Excavation through existing concrete/ water bound macadam
road / bituminous road / concrete road/soil/morrum/ hard rock
/soft rock/ old structures below ground as encountered of all
thickness including dismantling other structures, dead utilities,
dewatering, pumping and bailing out water, strutting and shoring,
etc. for utility identification shall be done by either manually or
with necessary precautions so that existing utility shall not
damage. At each pier location sizes of excavation pits will be
2. Temporary support for utility if required.
3. utility mapping and submission of utility mapping in soft and
hard copy with plan, elevation and cross-sections coordinates in
autocad and with photographs for submission to DDC review.
4. If boring will required, same will be paid in separate item (Ref
5. If utility shifting is required it shall be paid under separate item
6. Back fill of excavated soil upto natural ground level with
sufficient compaction for required stability of piling rig during
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
2 Boring 100mm dia borehole, 6m deep at pile locations to find out RM 3600.00 597.95
underground utilities as directed by Engineer in charge.
Earth work in excavation by mechanical means (Hydraulic
excavator) / manual means over areas (exceeding 30cm in
3 depth. 1.5 m in width as well as 10 sqm on plan) including cum 3500.00 150.40
disposal of excavated earth, lead upto 50m and lift upto 1.5m,
disposed earth to be levelled and neatly dressed.: All kinds of soil
Dismantling manually/ by mechanical means including stacking
4 of serviceable material and disposal of unserviceable material sqm 2500.00 363.10
within 50 metres lead as per direction of Engineer-in-charge :
bituminous road
PCC - M10 Levelling - Providing and casting in situ cement
5 concrete in grade M-10 (approx..corresp. to prop. 1:3:6) using cum 800.00 3972.00
granite quartzite trap metal of size 12 mm to 25 mm incl.
consolidation curing etc complete. With Form Work
Brick work with common burnt clay modular bricks of class
6 designation 7.5 in foundation and plinth in: Cement Mortar 1:4 (1 cum 1200.00 5512.63
cement : 4 coarse sand).
7 Providing Cement Plaster in Coarse sand: 15 mm cement plaster Sqm 3600.00 282.50
: 1:6 (1 cement: 6 coarse sand)
Providing and fixing at or near ground level precast cement
concrete in kerbs, edgings etc. as per approved pattern and
setting in position with cement mortar 1:3 (1 Cement : 3 coarse
8 sand), including the cost of required centering, shuttering Cum 400.00 7395.64
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate
mm nominal size)
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
Filling with available fly ash and earth (excluding rock) in trenches
or embankment in layers (each layer should not exceed 15 cm),
with intermediate layer of compacted earth (Soil density of 98%)
9 after every four layers of compacted depth of fly ash, sides & top cum 6000.00 261.86
layer of filling shall be done with earth having total minimum
compacted thickness 30 cm or as decided by Engineer -in-charge,
including compacting each layer by rolling/ ramming and watering,
all complete as per drawing and direction of Engineer-in-charge.
10 Carriage of Materials by Mechanical Transport including loading cum 5000.00 240.66
,unloading and stacking : Earth
Total Section - A
Section - B Drainage/Storm water pipeline works
Providing and supplying RCC pipes (of sulphate resisting
cement) in standard lengths of following class and diameter
1 suitable for either collar joints or rubber ring joints including all
taxes, insurance, transportation, freight charges, octroi,
inspection charges, loading, unloading, conveyance to
departmental stores, stacking etc. complete
1.1 Class NP3 Test pressure 0.7 kg/sqcm : 1200mm dia Rmt 1500.000 5899.00
1.2 Class NP3 Test pressure 0.7 kg/sqcm : 900mm dia Rmt 1000.000 3601.00
1.3 Class NP3 Test pressure 0.7 kg/sqcm : 600mm dia Rmt 250.000 1946.00
1.4 Class NP3 Test pressure 0.7 kg/sqcm : 450mm dia Rmt 500.000 1361.00
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
1.5 Class NP3 Test pressure 0.7 kg/sqcm : 400mm dia Rmt 50.00 1150.00
1.6 Class NP3 Test pressure 0.7 kg/sqcm : 300mm dia Rmt 3000.00 755.00
1.7 Class NP3 Test pressure 0.7 kg/sqcm : 200mm dia Rmt 50.00 417.00
LL & J of RCC Pipes: Class NP2, NP3, NP4
Lowering, laying and jointing R. C. C. pipes in C. M. 1:1 1/2 of
following diameters in proper position, grade and alignment as
2 directed by Engineer-in-charge. including conveyance from
stores to site of work, Labour, giving hydraulic testing as per IS
(Note: For each 1.5m next lift consider 10% rise in previous lift)
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
Total Section - B
Section- C Water Supply Pipeline works
Providing and supplying D. L. K-9 grade pipes for following
nominal bore diameter with internal cement mortar Ening
Including all taxes, Insurance, transportation, freight charges,
1 octroi, Inspection charges, loading, unloading, conveyance to
departmental stores, stacking etc. complete. (IS 8329-2000). For
sewerage project cement mortor lining shall be with sulphate
resistance cement.
1.1 DI Pipe K-9 D/F (Double Flanged)
a 700 mm dia Rmt 10 25790.00
b 600 mm dia Rmt 10 19152.00
c 450mm dia Rmt 300 12073.00
d 300mm dia Rmt 200 6315.00
e 200mm dia Rmt 100 3760.00
f 150mm dia Rmt 50 2881.00
g 100 mm dia Rmt 500 2045.00
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
1.2 DI Pipe K-9
a 700 mm dia Rmt 2 12858.00
b 600 mm dia Rmt 2 9945.00
c 450mm dia Rmt 20 6437.00
d 300mm dia Rmt 16 3654.00
e 200mm dia Rmt 10 2160.00
f 150mm dia Rmt 2 1597.00
g 100 mm dia Rmt 20 1087.00
Providing flanged joints to double flanged C.I./ D.I. pipes and
specials, including testing of joints
a 700 mm dia Each 2 1444.15
b 600 mm dia Each 2 1444.15
c 450mm dia Each 20 1106.44
d 300mm dia Each 16 508.05
e 200mm dia Each 10 363.26
f 150mm dia Each 2 328.31
g 100 mm dia Each 20 281.36
Total Section - C
Tender No: GMRC/Utility Shifting/R/Ph-III B/2026 BOQ
S. No Description Unit Total Qty Rate Total Amount
S. No Description Unit Total Qty Rate Total Amount
Section - D - provisional Sum
Provisional Sum - R&B SOR 2023-24/DSR 2023/GWSSB 2022-
23 for Canal Road to Badrabad
Total Section - D
GMRC Page 10 of
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
S.No Description Unit Total Qty Rate Total
Section E: BSNL Works
Horizontal Boring by HDD method with bore 150mm dia. Inserting
maximum 3 PLB Pipes
2 Supply of HDPE Pipe - 40mm Rmt 3000.00 68.285
Laying of PLB/HDPE pipe, coupled with HDPE
3 Sockets, end cape including price of supply and laying of 6mm PP Rmt 3000.00 6.987
rope through pipe .
4 Supply of 288F cable Rmt 3000.00 275.696
Blowing of 144/288F in existing/old duct, including opening of main
5 holes, Cleaning of Existing/old duct Rmt 3000.00 15.334
pipe and blowing of Optical fiber cable.
6 Supply of FRP manhole Nos. 22.00 32,282.521
Digging and installation of FRP M/H PIT(1.5x1.5x1.5)M,CC base for
FRP M/H 6inch thick, transportation of M/H from store, fixing of FRP
from store, fixing of FRP M/h in pit and refilling of pit up to road
level with cementing.
8 Supply of Straight/Branch Joint Closure Nos. 6.00 2,507.699
GMRC Page 11 of
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
9 Labour charges for installation of closure Nos. 6.00 4,000.200
10 Supply of 24F cable material Rmt 2000.00 63.42
Labour charges for laying of 24F cable material (Cable
pulling upto 48F cable)
Total Section E
Grand Total (excluding GST) (A+B+C+D+E)
Grand Total (excluding GST) (A+B+C+D+E)
1. Tenderer is requested to quote only percentage above or below or at par
2. For the purpose of comparative evaluation of tenders, the amount worked out from the quoted percentage (above/below/at
par) or/and quoted rate of item as applicable, in equivalent INR shall be compared amongst various tenders to determine
the lowest evaluated tender applying provision of clause 1.1.3.1 (ix) of NIT.
3. Evaluation of the tender will be done on amount excluding GST.
4. GST will be reimbursed on submission of proof of payment.
5. If the percentage of GST is changed, it shall be adjusted after notification
6. * 10% of the payment will be released by the Employer only after submission of No Objection Certificates (NOCs) from
various utility-owning agencies and/or local authorities to GMRC, wherever applicable as decided by the
Employer/Engineer-in Charge.
GMRC Page 12 of
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
Annexure 2, DETAILS OF TAXES AND DUTIES (Tax Bifurcation) INR: Indian Rupees
GST (Goods and Services Tax) Total
Customs Duty Amount of
CGST SGST IGST Any other Tax
SN Amoun Amoun Duties in
Amount Amount INR
t on t on Amount
Amo Amoun on on Amoun
which Rate which Rate Amount Rate on which Rate Amount Rate (6) = sum
unt t which which t
tax/ (%) tax/ (%) (INR) (%) tax/ duty (%) (INR) (%) of (1) to
(INR) (INR) tax/ duty tax/ duty (INR)
duty duty levied (5)
Note :1 Contractor at any point of time shall be bound to share the details pertaining to the Input Tax Credit availed or to be availed along with the
supporting documents.
Note:2 In the Tax Schedule Contractor shall require to furnish component wise tax details.
Note:4 GST TDS will be deducted from the invoice considering the prevailing rates
Note 5 : It shall be sole responsibility of Contractor to pass all the accrue or to be accrued Input tax credit to GMRC as per Section 171 of CGST
GMRC Page 13 of
Tender No: GMRC/Utility Shifting/Ph-3B/2026 BOQ
PROFORMA FOR STATEMENT OF MINOR DEVIATIONS
(Refer C15 & C26 of ITT)
1The following are the particulars of minor deviations from the requirements of the Tender Document:
Sr. No Clause Deviations Price adjustment for each
1 The Tenderer shall indicate price adjustment against each deviation in Annexure 13A of BOQ. This price is
the price which the tenderer shall reduced from this tender price if deviation(s) is/are accepted by the
2 Where there is no deviation, the statement should be returned duly signed with an endorsement indicating
that the tenderer has not proposed any deviations from tender documents.
3 If the tenderer proposes deviations in tender documents, and/or any other terms and conditions of the
tender, other than in this Annexure, it will have no effect.
Signature of authorized signatory on behalf of tenderers
GMRC Page 14 of
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
1. 20260806-NIT.pdf
2 ITT Utility Shifting- 3B.pdf
3 FOT Utility Shifting- 3B.pdf
4 GCC Utility Shifting- 3B.pdf
5 SCC Utility Shifting- 3B.pdf
6. SOW utility shifting -3B.pdf
7.SHE Utility Shifting 3B.pdf
8. BOQ Utility shifting- 3B.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].