| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.8 CrAccepted-AOC VILLAGE MEHENDIYA PO PS MEHENDIYA DIST ARWAL | ARWAL | BIHAR | 804401 | ₹5.8 Cr | L1 | Accepted-AOC Due to L1 |
| 2 | L2₹5.9 Cr+₹17.3 L (3.01%)Rejected-Finance VILL P O KAMTA P S PARASI DIST ARWAL | ARWAL | BIHAR | 804401 | ₹5.9 Cr+₹17.3 L (3.01%) | L2 | Rejected-Finance Due to L2 |
Tender Value
₹6.4 Cr
EMD Value
₹12.8 L
Closing Date
15 Sept 2025, 3:00 pmClosed
E-in-C-cum-Addl. Comm.-cum-Spl. Sec.
RWD (HQ) PATNA
Technical document other than my document
2025_RWD_144297_1
PMGSY-PDLP/25-26 Arwal/01
Open Tender
Civil Works - Roads
Percentage
365 days
Arwal
Please refer Tender documents.
3 documents required · 3 mandatory
₹10,000
₹12.8 L
Office of Respective Works Circle, RWD
16 Feb 2026
8 Sept 2025
15 Sept 2025
8 Sept 2025
15 Sept 2025
8 Sept 2025
10 Sept 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | L039 Anua to Bhagwatipur | - | - | - | - |
| 2 | Setting Out Pillars :- Providing & Fixing of Working benchmark Pillars 01 nos. per km & 04 Nos. of reference pillars required for 1 Km. as per drawings given and direction of E/I | 2 | Km | 11,703.16 | ₹23,406.32 |
| 3 | Clearing and Grubbing Road Land
Clearing and Grubbing Road Land ( By manual means) including uprooting wild vegetation , grass ,bushes ,shrubs , saplings and trees of girth upto 300mm , removals of stumps of such trees cut earlier & disposal of unserviceable materials & stacking of serviceable materials to be used or auctioned upto a lead of 1000 m including removal and disposal of top organic soil not exeeding 150mm in thickness as per technical specification - clause 201.1 and direction of E/I ( By Manual Means) In area of non-thorny jungle | 0.39 | Hect. | 75,360.38 | ₹29,390.55 |
| 4 | Scrarifying Existing Bituminous Surface to a Depth of 50 mm and disposal disposal of scrarified materials with a lift upto 3m and lead upto 1000m as per technical specification clause 301.4 | 1,303.13 | Sqm | 14.41 | ₹18,778.1 |
| 5 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m & 100 m as per Technical Specification Clause 303.1. (Including Royality & Labour Cess). | 476.1 | Cum | 244.59 | ₹1,16,449.3 |
| 6 | Granular Sub-base with Well Graded Material (Table 400.1) :- Construction of granular sub-base by providing well graded material, spreading in uniform layers with tractor mounted grader arrangement on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. (For Grading II Material) | 108.99 | Cum | 1,829.21 | ₹1,99,365.6 |
| 7 | WBM Grading 2 :-Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density grading 2 as per Technical Specification Clause 405. | 102.88 | Cum | 3,468.4 | ₹3,56,828.99 |
| 8 | WMM :- Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. | 526.46 | Cum | 2,907.59 | ₹15,30,729.83 |
| 9 | Prime Coat (Low Porosity) :- Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0kg/sqm using mechanical means as per Technical Specification Clause 502 | 5,264.63 | Sqm | 56.41 | ₹2,96,977.78 |
| 10 | Construction OF Dry Lean Concrete Sub Base Over a prepared sub grade with coarse and fine aggregate conforming to IS 383 , the size of Coarse Agg. Not exceeding 25mm , agg. Cememt ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1 , cement content not to be less than 150kg/cm, opc to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant , trasported to site, laid with a paver with electronic sensor , compacting with 8-10 tonnes vibrartory roller, finishing and curing. | 20.44 | Cum | 3,975.56 | ₹81,260.45 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.18 MB
BOQ_223807.xls
BOQ • 0.48 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .